Across the 31 Florida jurisdictions we have verified, 3 of 307 project rules need no permit at all, 91 turn on a size or scope condition the jurisdiction publishes, and 213 require a permit regardless. Shed work is where the answer most often comes with a published condition rather than a flat yes: 17 of the 31 jurisdictions that answer publish one. The numbers are not statewide: shed thresholds alone run from 50 to 600 sq ft depending on the jurisdiction.
Jurisdictions read
31
Rules with an answer
307
No permit needed
3
Depends on size or scope
91
Permit always required
213
How to read this page
"No permit" means the jurisdiction publishes that the work needs no building permit. "Depends" means
it publishes a size, height, depth, cost or scope condition that decides the answer, quoted in its own
words in the last column; the number beside it is the figure that condition turns on, and which side of
the number is exempt is stated by the condition, not by us. Exempt from a building permit is not exempt
from zoning, setbacks, height limits, flood rules, an HOA, or a separate electrical, plumbing or
mechanical permit, and several of the conditions below say exactly that.
17 of 31 make the shed answer turn on a size or scope condition the jurisdiction publishes, and the 19 that state a number publish figures from 50 to 600 sq ft. 14 require a permit for shed work regardless of size.
A building permit is not required for plastic or rubber manufactured type sheds 68 square feet or less in area, though they must comply with zoning setbacks and be moved and secured if there is the threat of a tropical storm.
A portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size.
Sheds with impervious roof coverings of 120 square feet or less do not require a Zoning permit, provided other county regulations (setbacks, floodplain rules, one detached accessory building per parcel, etc.) are met.
sheds less than 150 sq ft are exempt; sheds over 150 sq ft require a building permit; the county pages do not clearly place a shed of exactly 150 sq ft.
A shed built by the property owner on the owner's own personal residence, with no electrical, HVAC, fuel gas, or plumbing, is exempt from a building permit up to a 120-square-foot footprint.
Sheds over 100 square feet in area require a building permit; sheds of any size are still subject to Development Services and Environmental Services review for location, setbacks from boundary lines, easements, and floodplain.
A prefabricated shed used as a tool/storage shed or playhouse is exempt from a building permit if its floor area does not exceed 120 square feet and it is not over 8 feet high, measured from mean roof height; zoning and flood regulations still apply regardless. Sheds exceeding that size, or not used for tool/storage/playhouse purposes, require a permit.
Sheds of 150 square feet or less are on the county's no-permit list only if approved by and on file with the Florida DBPR Manufactured Building Program, with tie-downs installed and required property setbacks met.
Sheds less than 100 sq ft and no taller than 10 ft on residential property need no permit unless they are connected to utilities; sheds larger than 100 sq ft require permits. The county page does not address a shed of exactly 100 sq ft.
Prefabricated reach-in storage structures of closet use are exempt only up to 5 ft mean height, 50 sq ft area and 250 cubic ft with no electrical or plumbing; all larger or walk-in structures require a permit.
gross floor area, plus all covered area, of a residential storage accessory building, for eligibility to request the no-permit exemption under Ordinance 2010-17.
Plastic or rubber storage containers less than 7 feet tall and less than 65 square feet that meet any applicable setback requirements do not need a building permit; all other storage or utility sheds require a permit.
Clay County's own step-by-step guide for shed permits, 'How to Apply for a Pre-Fabricated Shed,' walks applicants through the Citizens Access Portal application and does not describe any small-shed size exemption from permitting.
Collier County treats a shed as an accessory structure and requires a building permit for it, filed under the Carport/Shed (PRCP) application category with construction plans and a site plan.
A building permit is required for a residential shed of any size. Sheds 150 square feet or larger (or with a job cost of $5,000 or more) additionally require structural design drawings signed and sealed by a Florida-licensed design professional and a plans-examiner review before the permit is issued; sheds under that size and cost, with no final inspection required, can often be issued the same visit.
The City of Miami's exemption list (City Code Sec. 10-5(b)) contains no shed or accessory-building exemption, and the City lists prefabricated sheds among the small residential projects for which homeowners need permits through its Walk-Thru Express review.
Osceola County's Permit Information page lists 'Shed or storage building' among the residential examples that require a building permit, with no size-based exemption stated.
An accessory enclosure (shed) of at most 6 ft x 6 ft x 6 ft high, for a single-family dwelling only, needs only a Type 1 Site Plan Review Permit (zoning review, exempt from inspection and Building Code review). Larger sheds need a building permit.
Seminole County's Building Permitting page lists building a barn, metal building, shed or detached garage among the work that typically requires a permit, and its fee schedule (Revised October 2026) has Sheds, Pre-built and Sheds, Site-Built lines.
St. Johns County's Land Development Code states directly that private garages and storage buildings (the county's term covering sheds and similar accessory structures) require a building permit, and requires such structures to stay accessory in size and eave height to the main residential building.
St. Lucie County's published list of items that do not require a permit does not include any size-based exemption for storage sheds or accessory structures, unlike some other Florida counties that exempt small sheds.
Escambia County, Jacksonville and Santa Rosa County require no fence permit at all. 12 of 31 make the fence answer turn on a size or scope condition the jurisdiction publishes, and the 4 that state a number publish figures from 6 to 8 feet. 16 require a permit for fence work regardless of size.
Escambia County's Building Services Department does not require a building permit to install a fence anywhere in unincorporated Escambia County or the Town of Century, which Escambia County Building Services also permits directly (subject to a separate Town of Century approval step).
Santa Rosa County's rules below cover only unincorporated areas, which include the population centers of Navarre and Pace; the incorporated cities of Milton, Gulf Breeze, and Jay run their own building departments and are not covered here.
Masonry or concrete fences 4 feet or less in height, and fences of any other material 6 feet or less in height, are exempt from a building permit under the county's Chapter 6 building-code amendment.
Masonry fences, walls, and columns (residential and commercial) always require a building permit. Non-structural residential fences such as wood, chain link, and vinyl are exempt from a building permit when located on a one or two family lot that is not in a flood hazard area.
A permit is required only when the fence is supported by brick, block, or concrete columns; ordinary residential fences are exempt but setbacks must be checked with Development Code Review.
Standard wood, vinyl or chain-link fences up to 6 feet tall outside designated flood zones generally need no zoning clearance, building permit or floodplain permit; a Zoning Clearance is required in the front setback or on a corner lot; a Floodplain Permit is required in a Special Flood Hazard Area; taller fences and masonry or metal walls need a building permit.
Solid fences over eight feet high and all masonry walls or fences with masonry pilasters require a permit; chain link fences of any height and stockade fences up to eight feet high are exempt.
A chain link, wood, or vinyl fence does not need a building permit when it meets the county's standards for height, placement, and finished side facing the neighbor or right-of-way; fences and walls that do not meet those standards require a permit. A permit is also required when the property is in a flood zone or the fence is part of a larger project scope.
In unincorporated Volusia County, a building permit is no longer required to install a residential fence, following a county ordinance change effective June 5, 2025.
Fence permits are required in all commercial, industrial, and residential zoning districts; agricultural zoning districts (AG, AR, AR1, AR2, PDP(RUR)) are exempt from the Fence Ordinance.
Marion County's building permit fee schedule includes a specific charge for fences, walls, and entrance-ways, and the county's general permitting rule requires a permit before erecting, enlarging, or altering any structure.
The City of Miami Building Department, not Miami-Dade County, issues building permits for property inside City of Miami limits; unincorporated Miami-Dade County and the separately incorporated cities (Miami Beach, Coral Gables, Hialeah, Miami Gardens, North Miami, Doral and others) run their own permitting.
Osceola County's Permit Information page lists Fence among the residential work examples that require a building permit, under the general rule that any regulated structural work requires a permit.
Seminole County's current permit fee schedule (Revised October 2026) prices a fence permit with a specific Fence line item, and its Building Permitting page no longer lists fences among the work that typically requires a permit, so treat a permit as required unless the county approves an exemption request.
St. Johns County's Building Department requires a permit before anyone constructs, enlarges, alters, or repairs a structure, and its fee schedule has no fence-specific line item, so fence permits are charged from the general valuation-based Building Services fee table.
Fence repairs of less than 2 panels, excluding pool barriers, are on the county's list of items not requiring a permit (repairs under $2,500 that do not affect structural integrity, with an exemption application still required for verification); installing a new fence, larger repairs, or any pool barrier fence requires a permit.
13 of 20 make the patio answer turn on a size or scope condition the jurisdiction publishes. 7 require a permit for patio work regardless of size. 11 publish no answer we could verify.
Permits shall not be required for the enclosure of an existing covered patio, balcony, or porch with screening only; a permit is required to build a new patio cover, screen enclosure, or other patio structure.
Sand-set pavers that are not part of a pool or spa deck do not require a building permit; other patio construction methods are not separately addressed by name.
The City of Jacksonville's consolidated Duval County Building Inspection Division puts a plain patio slab on its official list of work that does not require a permit.
A permit is required to construct, enlarge, alter, or repair a structure, including structural slabs, unenclosed structures, porches, and screen, glass, or vinyl rooms; the county refers residents to Florida Building Code 105.2 and Land Development Code 6-117 for work not requiring a permit.
Patio covers, sunrooms, and screen or pool enclosures are handled as aluminum structures requiring a permit; a plain open, unroofed, at-grade patio slab is not separately addressed in any published county page found.
open patio slabs, walkways and pavers outside the building do not require a building permit, as long as all exempt work on the home in any 12-month period does not exceed $5,000.00; slabs for screened patios and pool slabs are not covered by that exemption; patio covers need a building permit.
Sand-set pavers that are not a pool or spa deck and not within five feet of a pool need no permit (1 and 2 family dwellings, excluding driveways or turnouts). A slab that is not for a future structure, has no footers and is not within 5 feet of a pool needs only a zoning Site Plan Review Permit. The county's list does not say which permit any other slab needs; it sends unlisted work to the Permit Center Help Desk at 561-233-5120.
Non structural concrete flatwork under 500 square feet per parcel that will not be built on is on the county's no-permit list; slabs intended for a future structure require a permit with sealed plans.
Permit requirement depends on location and function: concrete slabs adjacent to a principal or accessory structure, slabs intended to support a structure, elevated slabs, and pavers within required setbacks or adjacent to structures require a permit.
No permit is required for a residential patio placed directly on grade without footings, in any material; a permit is required for patios that involve footings, are part of a larger project scope, or are on commercial or multi-family property.
Sand-set pavers that are not a pool or spa deck and are not within five feet of a pool do not require a permit, for 1 and 2 family dwellings; pavers used as a pool deck, pavers within five feet of a pool, or other patio construction requires a permit.
Volusia County's building code requires a permit for anyone who intends to construct, enlarge, or alter a structure in unincorporated areas, and the county's local list of work exempt from permitting (which covers only minor gas, mechanical, and plumbing items) does not name patios.
Charlotte County does not have a permit type called Patio; concrete and paver patios in unincorporated areas are permitted under the county's Residential Slab permit, which covers all concrete flatwork, structural or not, including pavers.
Martin County lists patios, patio covers and patio roofs among the projects that require a permit, and publishes a separate Patio Slab checklist asking for a survey, drainage, setbacks, a foundation plan and concrete details.
St. Johns County requires a permit under its general rule for constructing or altering a structure, and patios are named alongside decks in the county's floodplain management code, which regulates patio slabs, fill, and construction in Coastal High Hazard Areas and Coastal A Zones.
11 of 31 make the roof replacement answer turn on a size or scope condition the jurisdiction publishes, and the 8 that state a number publish figures from $500 to $7,500. 20 require a permit for roof replacement work regardless of size.
A roofing permit is required for reroofing. Florida law exempts work valued at less than $7,500 on a single-family dwelling on written request, but not structural, electrical, plumbing, mechanical or gas work and not property in a flood hazard area; no Broward County page says whether a reroof can use that exemption, so confirm with the Building Code Division.
A Re-Roofing Permit is required for re-roofs exceeding 2 squares (1 square equals 100 square feet, so 2 squares equals 200 square feet); roof repair work under two squares does not require a permit.
Roof replacement is done under a re-roofing permit. The county lists non-structural roof repair or replacement on a single-family residence valued under $7,500 as a possible exemption under House Bill 803, on an approved exemption application only, and not for property in a flood hazard area or for structural, electrical, plumbing, mechanical or gas work.
Under s. 553.79(1)(g) F.S., effective 2026-07-01, the county must exempt work on a single-family dwelling valued at less than $7,500 upon written request, but the exemption does not apply to structural, electrical, plumbing, mechanical, or gas work or to property in a flood hazard area.
Roofing work needs a roofing permit, except replacement or repair of a roof covering by a licensed roofing contractor not exceeding $2,000.00 in materials and labor and not exceeding two roofing squares. Work valued under $7,500 on a single-family home, duplex or townhouse may qualify for the state exemption on written request, but not in a flood hazard area and not for structural, electrical, plumbing, mechanical or gas work; the county does not say whether a roof replacement qualifies.
The county says a replacement roof needs a roof permit. Florida law exempts work valued at less than $7,500 on a single-family dwelling on written request, but not structural, electrical, plumbing, mechanical or gas work and not property in a flood hazard area; no Orange County page says whether a reroof can use that exemption, so confirm with the Division of Building Safety.
non-structural roof work (e.g. roof covering only, not sheathing or framing) with a total project value under $7,500 on a single-family home outside a flood hazard area may qualify for a written permit-exemption approval from the County Building Official instead of a standard permit; structural roof work, any work on a flood-zone property, or any project at or above $7,500 requires a standard roofing permit.
All re-roofing needs a permit. Minor roof repairs of less than 25 percent, as determined by the Building Official or Plans Examiner Supervisor, do not. Florida law also exempts work valued at less than $7,500 on a single-family dwelling on written request, but not structural work or property in a flood hazard area, and Polk County has not said that this covers re-roofing.
Brevard County requires a Residential Reroof permit for the repair or replacement of roof covering such as shingles, tiles, metal, or skylights, with no permit required for reroofing work on mobile homes or tiny houses on wheels.
Clay County's HB 803 minor-work exemption guidance lists 'Roofing' under structural work that does not qualify for the exemption regardless of project cost, so reroofing always requires a standard building permit rather than any owner-requested exemption.
Collier County's locally adopted building code amendment exempts from permit only the repair of any roof covering not exceeding $1,500.00 in value of materials and labor, or repair work not exceeding two roofing squares (200 square feet) in extent; this exemption is for roof repair, not for roof replacement/reroofing (removing and replacing the covering), which requires a standard Reroof permit.
Roof repairs covering less than 100 square feet of existing roof are exempt from a building permit; this exemption does not extend to a full roof replacement.
The City of Jacksonville's consolidated Duval County Building Inspection Division lists re-roofs under Alterations on its official list of work that requires a building permit, and it publishes a separate roofing permit fee tier that excludes only the original roof installed with brand-new construction.
Lake County's fee schedule prices residential roofing by square footage, and the Office of Building Services publishes a dedicated Re-Roof/Roof Over checklist (CL16) requiring a permit application, a notarized Reroof Scope of Work/Roofing Affidavit (BF61), and progress photographs of sheathing and underlayment for the final inspection.
Leon County requires a building permit to replace or re-cover a roof, processed as a Reroof permit and billed as a flat fee on the county's fee schedule.
In unincorporated Manatee County, a new roof or re-roof always requires a building permit, and residential re-roofs can use the county's Roof Express option, which needs no documents before permit issuance beyond the required Florida Product Approval NOAs.
Martin County lists reroofing among the projects that require a permit, and its HB 803 page names roofing as structural work outside the under-$7,500 exemption.
The City of Miami requires a building permit for all roofing work on residential and commercial properties, with a Uniform Roofing Application and a Miami-Dade County Notice of Acceptance or Florida Product Approval for every roofing material.
The state exemption for work valued at less than $7,500 does not apply in Palm Beach County: the county says all of Palm Beach County is designated a flood hazard area under the Florida Building Code.
Pasco County classes roofing as structural work, so the state exemption for work valued at less than $7,500 does not cover it and a permit is required regardless of cost. Small roof repairs and liquid roof coatings are on the county no-permit list.
Santa Rosa County requires a building permit for new roofs, full roof replacement (tear-off/re-roof), and recovering an existing roof, subject to Florida Building Code criteria on when recovering (versus full tear-off) is allowed.
A building permit is not required for repair of a small, incidental roof leak limited to one roofing square and $500 or less in cost; a permit is required for roof replacement and for repair or replacement of structural roof components such as sheathing.
St. Johns County requires a permit under its general rule for repairing or altering a structure, and the county's own Re-Roof Mitigation Worksheet ties reroofing directly to a permit number and specific inspections (an in-progress inspection and a final inspection) under the state's hurricane mitigation retrofit law.
Replacing or re-covering a roof on a home in unincorporated Volusia County requires a building permit, and the county publishes a specific minimum roofing permit fee.
10 of 31 make the pool answer turn on a size or scope condition the jurisdiction publishes, and the 13 that state a number publish figures from 24 to 42 inches. 21 require a permit for pool work regardless of size.
Storable swimming or wading pools capable of holding water to a maximum depth of 42 inches, or pools with nonmetallic molded polymeric or inflatable fabric walls regardless of dimension, are exempt from a building permit except for non-cord-and-plug electrical work.
Portable or manufactured pools and spas less than 24 inches deep need no permit; all in-ground pools, larger above-ground pools, and spas require a Building Permit (Type 3(E) for 1 and 2 unit dwellings) plus applicable electrical, plumbing, and pool-barrier sub-permits, and must satisfy Florida's residential pool safety-feature requirements under F.S. 515.27 before final inspection.
Prefabricated above-ground swimming pools accessory to a one- or two-family home that are less than 24 inches deep and hold 5,000 gallons or less are exempt from permit.
Portable or manufactured pools or spas less than 24 inches deep do not require a permit; in-ground pools, permanent spas, and portable or manufactured pools or spas 24 inches deep or more require a permit.
Alachua County requires a building permit for both in-ground and above-ground residential pools, billed at flat fees of $380.00 and $205.00 respectively.
Clay County's Building Division FAQ walks through the pool safety requirements a homeowner must choose from when installing a pool: a barrier (fence, wall, or screen at least 4 feet high with a self-closing, self-latching gate whose latch sits at least 54 inches high), a safety pool cover meeting ASTM F1346-91, exit alarms on doors and windows, self-closing/self-latching doors, or a pool alarm meeting ASTM F2208.
Collier County requires a building permit for both inground and aboveground residential pools and spas, filed under the Pools (PRSPL) application category.
Swimming pools are explicitly listed as requiring a building permit on the City of Jacksonville's consolidated Duval County Building Inspection Division site, which also publishes a dedicated Swimming Pool and Spa checklist for one- and two-family properties.
The City of Miami lists pools among the residential projects for which homeowners need permits, reviewable through Walk-Thru Express and Homeowner's Express Review, and pools designed on piles need full structural review.
A building permit is required for all residential pools, spas, and hot tubs in unincorporated Pinellas County; Pool/Spa Above Ground and Pool/Spa Inground are listed permit types in the Access Portal, plus electrical, plumbing, and gas sub-permits as applicable.
Santa Rosa County requires a building permit application for all residential and commercial pool and spa installations, along with an engineered lot grading plan (for lots in unincorporated areas), a site plan or city approval, a pool layout drawing, and a notarized Barrier/Alarm Acknowledgment Form documenting compliance with Chapter 515, F.S. barrier or alarm requirements.
Sarasota County's building permit application requires applicants to acknowledge that a separate permit must be secured for pools, in addition to any building permit covering pool decking or a screen enclosure.
Installing an in-ground or above-ground swimming pool in unincorporated Volusia County requires a building permit, with separate fee amounts for public pools, private in-ground pools, and private above-ground pools.
A window air conditioning unit using an existing electrical outlet, and repair of existing mechanical equipment, do not require a building permit; installing a new central/ducted system or changing out equipment does.
A permit is required for mechanical work such as installing or replacing air conditioning and heating equipment. It is not required for connecting portable heating, ventilation, cooling, or evaporative-cooling equipment; for replacing a part within a single existing piece of equipment; or for a self-contained refrigeration system with 10 pounds or less of refrigerant run by a motor of 1 horsepower or less.
Replacement and new installation of air conditioners and ductwork require a mechanical permit. Replacement of a window air conditioning unit, and portable heating or cooling appliances, do not require a permit.
Installing an A/C unit under three tons that is cord-and-plug connected to an existing electrical outlet and not connected to ductwork does not require a permit.
A new air conditioning system and an A/C change-out need a permit. Replacing an existing window unit on an existing dedicated electrical outlet, repairing an existing system, and replacing any part that does not alter the system listing or make it unsafe are listed as not requiring a permit.
Air conditioning repair of existing equipment is exempt; equipment change outs and new installations require a mechanical permit and mechanical work is excluded from the state exemption for work valued at less than $7,500.
A self-contained refrigeration system with 10 pounds or less of refrigerant, actuated by a motor of 1 horsepower or less, does not require a permit; portable heating, ventilation, and cooling equipment is also exempt.
Alachua County treats HVAC replacement as a Level 1 alteration under the Florida Building Code and issues a permit for it, backed by a dedicated HVAC Change Out Inspection Checklist and affidavit provided to applicants at permit issuance.
Brevard County requires a Residential HVAC/Mechanical permit for installing a new or replacement heating, ventilation, and air conditioning unit, with or without duct work.
Clay County calls this permit type a 'Mechanical Permit' (Section 208.4 of its fee schedule), which covers HVAC and related equipment such as boilers and gas burners.
This is a self-issuing permit available on the portal, unless any of the criteria listed below apply. If they do, the permit will follow the standard permitting and plan review process: Greater than 5 tons (single family); Located on the roof of a building; Adding concrete slab; Changing size of equipment; Moving location of equipment; Any changes to duct work; Adding a new mini-split; If owner-builder; In a trailer or manufactured home; If commercial building; If multi-family building.
Escambia County requires an Air Conditioning Permit for installing or changing an existing air conditioning or mechanical system, filed through the county's Mechanical Permit Application.
Lake County charges a Residential Trades fee covering mechanical (HVAC) work alongside electric, plumbing, and gas, and the Office of Building Services publishes a dedicated Mechanical Changeout Residential Checklist (CL10) requiring a Building Permit Application and the Mechanical System Change Outs form (BF65).
Portable HVAC equipment and replacement of any part that does not alter the equipment's approval or make it unsafe are exempt per Florida Building Code section 105.2.
Leon County requires a building permit for HVAC and mechanical work, including equipment replacements, billed either as part of the square-footage-based Mechanical plan review and inspection fee or as a standalone Mechanical trade permit.
A mechanical permit is required for all permanently installed HVAC and air conditioning equipment in unincorporated Orange County, including replacements.
Osceola County's Permit Information page lists 'New & replacement HVAC system' among the residential examples that require a building permit, consistent with the brief's expectation that trade permits are usually required.
A mechanical permit is required in unincorporated Pinellas County for new HVAC and air conditioning installations and replacements, including like-for-like equipment swaps; New A/C System and New Minisplit with Electric are listed Mechanical permit subtypes in the Access Portal.
Only minor mechanical repairs with no extensions or modifications are exempt; installation, alteration, replacement, extension or repair of mechanical systems, including A/C equipment change outs, requires a permit.
Santa Rosa County lists Mechanical among the permit types on its Obtain a Permit guidance page, and its Development Services Fee Schedule prices HVAC work (heating, ventilation, duct, A/C, and refrigeration, including repairs, alterations, and additions) as its own Mechanical Permits category.
Sarasota County's Building Permit Guidelines list alteration, addition, or removal of air conditioning systems as work that requires a building permit.
St. Johns County's own Building Permit Application states that a separate permit must be secured for furnaces, boilers, heaters, tanks, and air conditioners, and the county's fee schedule carries a dedicated Mechanical Permit Fees section priced by system valuation.
7 of 31 make the deck answer turn on a size or scope condition the jurisdiction publishes, and the 2 that state a number publish figures from 18 to 30 inches. 24 require a permit for deck work regardless of size.
decks are not on the county's list of exempt work; the county says a project not on that list most likely requires a permit; confirm with Development Services.
A deck built by the property owner on the owner's own personal residence is exempt from a building permit if it does not exceed 30 inches above grade and a 120-square-foot footprint.
Decks greater than 100 square feet in area, or more than 30 inches above grade on any side, require a building permit (either condition alone triggers it).
All attached decks require a building permit regardless of size. A detached deck requires a permit if it is over 30 inches high or over 120 square feet; a detached deck under 30 inches high and under 120 square feet does not require a permit.
wood decks 18 inches or less above ground do not require a permit, as long as all exempt work on the home in any 12-month period does not exceed $5,000.00; other decks need a building permit.
A permit is required to construct a raised residential deck (one with footings) and for all decks on commercial property; no permit is required for a residential deck placed directly on grade without footings, in any material.
Alachua County requires a permit to construct or enlarge any structure, and its published exemption list (minor repairs under $500, finish work, playground equipment, retractable awnings, small movable fixtures, one qualifying storage shed) does not include decks.
Brevard County has no separate 'deck' permit type; a deck that changes a home's footprint or adds height is filed under the county's Residential Addition permit category, which covers exterior additions and accessory structures.
Installing a raised or flat deck at a residential property in unincorporated Charlotte County requires a building permit, with reviews from the Building, Natural Resources, Right-of-Way, Tree, and Zoning divisions as applicable.
Collier County does not publish a standalone 'deck' application code, but its official Aluminum Structures page refers to decks as separately permitted structures, indicating a deck permit process exists independent of any screen enclosure or pool built on it.
Escambia County names deck installation, alongside swimming pools and spas, as one of its listed project types on the county's Building Guide, which routes an applicant through the standard zoning check, a site plan/Development Order where applicable, and a Building Permit at the Building Inspections Division before construction begins.
Hernando County's Development Services FAQ lists decks among the projects that require a permit, and the Building Division's fee schedule includes a specific Deck permit fee.
A deck in the City of Jacksonville's consolidated Duval County jurisdiction is permitted as an Addition or Accessory Structure type of improvement under the Building Inspection Division's New Building checklist, which requires flashing, weather-resistance barrier, structural load path, and stair or guardrail details specifically for decks as part of the plan review.
City Code Sec. 10-5 requires a permit to construct, enlarge, alter or repair any building or structure, and the City's list of work exempt from permit has no deck, platform or low-height exemption.
A Building Permit is required for residential deck construction in unincorporated Palm Beach County; 'Deck' is listed as its own priced line item (by value, $75 minimum) in the Building Division's fee schedule.
Elevated decks are treated as structural work, so the state exemption for work valued at less than $7,500 does not apply and a permit is required regardless of cost.
Santa Rosa County treats a deck as new construction under its general rule that building permits are required for new construction or structural changes, and its Development Services fee schedule prices decks under a dedicated Building Inspection Division line item alongside docks, seawalls, retainer walls, and boathouses.
Seminole County's building permit fee schedule names wood decks as an example of a 'structure other than a building' that falls under the county's general building permit fee category, and the county's general permitting rule requires a permit before constructing, enlarging, or altering any structure.
St. Johns County requires a permit under its general rule for constructing, enlarging, or altering a structure, and decks are also named directly in the county's floodplain management code, which requires decks in Coastal High Hazard Areas and Coastal A Zones to meet specific elevation and construction standards in addition to the Florida Building Code.
Minor replacement of existing decking (walking surface only) under $1,000 in value, for 1 and 2 family dwellings, does not require a permit; new deck construction, structural work, or higher-value decking replacement requires a permit.
The City Code requires a permit before anyone constructs a building or structure, and the City's exemption list has no exemption for decks of any size or height; the only grade-level carve-out is for sidewalks and driveways not more than 30 inches above grade.
5 of 31 make the electrical answer turn on a size or scope condition the jurisdiction publishes. 26 require a permit for electrical work regardless of size.
Permits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring.
Any alteration of electrical wiring requires a permit. Residential low voltage (wired or wireless) work does not require a permit unless its cost exceeds $5,000 within any 12-month period. Repair or replacement of a wall switch or outlet device rated 20 amps and 120 volts or less does not require a permit.
Installing, altering or replacing electrical work needs a permit. The county lists like for like light fixture replacement in an existing lighting outlet, replacing an existing outlet or switch within the existing junction box, and replacing a ceiling fan using the existing fan box and wiring as items not requiring a permit.
Replacement of existing light fixtures or switches and garage door openers on existing electrical are exempt; other electrical work requires a permit and electrical work is excluded from the state exemption for work valued at less than $7,500.
Adding new electrical service or wiring, or replacing existing service or wiring, at a residential property in unincorporated Charlotte County requires an electrical permit.
Clay County's HB 803 minor-work exemption guidance explicitly excludes 'Electrical work' from the exemption regardless of project cost, so electrical work always requires a standard building permit rather than being eligible for the new $7,500 owner-requested exemption.
Permits shall not be required for the following: ... Electrical: 1. Repair work performed by licensed electrical contractors that does not exceed $1,500.00 in value of materials and labor. 2. Repair or replace existing light fixtures and ceiling fans. 3. Repair or replace electrical wall switches and wall outlet devices of 20 amps or less and 120 volts. 4. Repair/replace low voltage (under 77 volts) devices.
Escambia County requires a permit for electrical work under two named categories: Electrical - Basic Work (changing or adding to existing circuits, adding load to the panel, or wiring new equipment or appliances) and Electrical Service Change (changing a panel from fuses to breakers or upgrading to a larger rating).
Hernando County's Development Services FAQ lists electrical work among the projects that require a permit, and the Building Division's fee schedule includes Electric, Other and Low Voltage Electric line items.
The City of Jacksonville's consolidated Duval County Building Inspection Division lists new electrical service and rewiring among the repairs that require a building permit, and separately states electrical work must be done only by contractors and craftsmen certified in that trade and requires its own permit.
Lake County charges a Residential Trades fee covering electrical work alongside plumbing, mechanical, and gas, and the Office of Building Services publishes a dedicated Electrical Residential Permit Checklist (CL6) requiring a Building Permit Application and a one-line diagram, with engineering required for scopes meeting the threshold in F.S. 471.003(h).
Leon County requires a building permit for electrical work, billed either through the square-footage-based Electrical plan review and inspection fee or as a standalone Electrical trade permit.
Marion County requires a permit to erect, install, enlarge, alter, repair, remove, or replace any electrical system regulated by the Florida Building Code, and the county's fee schedule includes a specific Res Electrical Scope permit fee.
Martin County requires a permit to install, alter, repair or replace any electrical system regulated by the code, and lists electrical panels, circuits, and ceiling fans or lights on a new circuit among projects that require a permit.
An electrical permit is required in unincorporated Orange County for all electrical construction including new wiring, panel upgrades, and new or relocated outlets.
Osceola County's Permit Information page lists 'New electrical services: Adding fixtures, meters, upgrading, or repairing existing service' among the residential examples that require a building permit.
An electrical permit is required in unincorporated Pinellas County for new wiring, service-panel upgrades, generators, and other electrical work, listed as its own Electrical permit category with multiple subtypes in the county's Access Portal.
Only minor electrical repairs with no extensions or modifications are exempt; all installation, alteration, replacement or extension work, service changes and added outlets or circuits require a permit.
Santa Rosa County's Forms & Documents page describes its Electrical Permit Application as covering all new and existing wiring work, and the county lists Electrical among the permit types required for construction work generally.
Sarasota County's Building Permit Guidelines list alteration, addition, or removal of electrical systems as work that requires a building permit, and the county's building permit application separately confirms electrical work needs its own permit.
Seminole County's Building Permitting page lists electrical repairs among the work that typically requires a building permit, backed by the fee schedule's dedicated electrical permit fee.
St. Johns County's general permitting rule explicitly names electrical systems among the work requiring a permit before installation, alteration, or repair, backed by a dedicated Electrical Permit Fees section in the county's fee schedule.
Electrical work in unincorporated St. Lucie County requires a permit pulled by a licensed electrical contractor or by an owner acting as their own contractor.
Electrical work in the City of Tampa needs a permit; the only exemptions are minor repairs such as replacing lamps or plugging approved portable equipment into existing receptacles, temporary testing systems, and utility-owned equipment.
Adding electrical receptacles or lighting, upgrading an electrical service, or otherwise altering wiring in unincorporated Volusia County requires an electrical permit.
5 of 31 make the plumbing answer turn on a size or scope condition the jurisdiction publishes. 26 require a permit for plumbing work regardless of size.
Permits are required for the installation or replacement of water, sewer, or gas piping and systems; this does not include changing like-for-like water heaters or fixtures such as sinks.
A permit is required for plumbing work such as fixture installation, water heater replacement, and sewer or water-service connections. It is not required for replacing plumbing fixtures after the stop (excluding water heaters), stopping leaks, or clearing drain stoppages, provided the repair does not involve or require replacing or rearranging valves, pipes, or fixtures.
New plumbing work such as re-piping, a new water service, a new or replacement sewer, and most water heater replacements require a permit. An electric to electric water heater changeout of the same size in the same location, and replacement of a plumbing fixture such as a toilet or faucet where no rough plumbing is changed, do not require a permit.
Replacement of existing faucets, sinks, or toilets and French drains not tied into public sewer are exempt; other plumbing work requires a permit and plumbing work is excluded from the state exemption for work valued at less than $7,500.
Alachua County's general permit rule covers erecting, installing, enlarging, altering, repairing, removing, converting, or replacing any plumbing system, and the E-Permitting system lists plumbing repair (re-piping), water heater replacement, central water/sewer hookup, and solar water heaters as plumbing permit categories available online.
Installing new plumbing or replacing existing plumbing elements at a residential property in unincorporated Charlotte County requires a plumbing permit.
Clay County's HB 803 minor-work exemption guidance explicitly excludes 'Plumbing work' from the exemption regardless of project cost, so plumbing work always requires a standard building permit rather than being eligible for the new $7,500 owner-requested exemption.
Permits shall not be required for the following: ... Plumbing: 1. Repair work performed by licensed plumbing contractors that does not exceed $1,500.00 in value of materials and labor. [Followed by 16 specific exempted repairs/replacements, e.g. faucets, water closets, sinks, garbage disposals, dishwashers, and like-for-like electric water heaters up to 52-gallon capacity.].
Escambia County requires a plumbing permit for relocating a fixture, replacing a bathtub with a shower or a whirlpool tub or shower pan, replacing any water heater, replacing a water service line, and connecting an existing septic tank to sewer service.
Hernando County's Development Services FAQ lists plumbing work among the projects that require a permit, and the Building Division's fee schedule includes a Plumbing, Other (Res) line item.
Lake County charges a Residential Trades fee covering plumbing work alongside electric, mechanical, and gas, and the Office of Building Services publishes a dedicated Plumbing Residential Permit Checklist (CL14) requiring a Building Permit Application and a one-line diagram, with engineering required for scopes meeting the threshold in F.S. 471.003(h).
Leon County requires a building permit for plumbing work, billed either through the square-footage-based Plumbing plan review and inspection fee or as a standalone Plumbing trade permit.
Marion County requires a permit to erect, install, enlarge, alter, repair, remove, or replace any plumbing system regulated by the Florida Building Code, and the county's fee schedule includes a specific Res Plumbing Scope permit fee.
when done by a licensed plumbing contractor, replacement of an electric water heater up to 50-gallon capacity and repair or replacement of faucets, toilets and sinks are exempt.
Osceola County's Permit Information page lists 'Plumbing: New & replacement fixtures, water heaters, re-piping' among the residential examples that require a building permit.
A plumbing permit is required in unincorporated Palm Beach County for new water and sewer service connections, site work, and other plumbing installations and modifications. 'Water Service Connection' and 'Sewer Connection' are listed as their own Type 1 Building Permits for 1 and 2 unit residences in the county's Permit Application Types guide.
A plumbing permit is required in unincorporated Pinellas County for new water and sewer service, site work, and other plumbing installations, listed as its own Plumbing permit category with multiple subtypes in the county's Access Portal.
Only minor plumbing repairs with no extensions or modifications are exempt; installation, alteration, replacement, extension or repair of plumbing, including re-pipes and water heater change outs, requires a permit.
Santa Rosa County's Forms & Documents page describes its Plumbing Permit Application as covering all new and existing plumbing-related work, and the county lists Plumbing among the permit types required for construction work generally.
Sarasota County's Building Permit Guidelines list alteration, addition, or removal of plumbing systems as work that requires a building permit, and the county's building permit application separately confirms plumbing work needs its own permit.
Seminole County's Building Permitting page lists replacement of a water heater among the work that typically requires a building permit, backed by the fee schedule's dedicated plumbing permit fee.
St. Johns County's general permitting rule explicitly names plumbing systems among the work requiring a permit before installation, alteration, or repair, backed by a dedicated Plumbing Permit Fees section in the county's fee schedule that charges per fixture, floor drain, trap, water heater, and similar item.
Plumbing changes in unincorporated St. Lucie County require a permit pulled by a licensed plumbing contractor or by an owner acting as their own contractor.
Building without a required permit is illegal under Florida state law: section 553.79(1)(a), Florida Statutes, makes it unlawful to construct, erect, alter, modify, repair, or demolish any building without first obtaining a permit, and section 489.127(1)(h) separately prohibits any person from starting permit-required work before the permit is in effect. For an unlicensed person, and a homeowner doing the work personally is unlicensed under chapter 489, violating that prohibition is a first degree misdemeanor under section 489.127(2)(a), punishable by up to 1 year in jail and a fine of up to $1,000 under sections 775.082(4)(a) and 775.083(1)(d).
12 of the 319 rules we hold for Florida are unresolved because the jurisdiction publishes
no answer; they are counted nowhere above.
The 307 answered rules come from 210 official sources, each linked from the permit page
behind every jurisdiction name. See the full picture for the state on the
Florida permit requirements page.
This page compiles what each Florida jurisdiction publishes, with a last checked date. It is not legal
advice, and a project that is exempt from a building permit can still need zoning approval or a trade
permit. Confirm with the office linked from the jurisdiction's page before you build.