Electrical Permit in St. Johns County, Florida
Permit required
Yes, a permit is required
Before installing, altering, or replacing an electrical system in unincorporated St. Johns County
Issued byBuilding Services Division, Growth Management Department
By Mario Bailey, verified against official sources
Quick answer
St. Johns County's general permitting rule explicitly names electrical systems among the work requiring a permit before installation, alteration, or repair, backed by a dedicated Electrical Permit Fees section in the county's fee schedule. This applies to unincorporated St. Johns County; St. Augustine and St. Augustine Beach have their own building departments and separate electrical permitting.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before installing, altering, or replacing an electrical system in unincorporated St. Johns County
What an electrical permit costs in St. Johns County
How St. Johns County compares in Florida
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Alachua County | Permit required | Any size |
| Brevard County | It depends | Permits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring. |
| Broward County | Permit required | Any size |
| Charlotte County | Permit required | Any size |
| Clay County | Permit required | Any size |
| Collier County | Permit required | Permits shall not be required for the following: ... Electrical: 1. Repair work performed by licensed electrical contractors that does not exceed $1,500.00 in value of materials and labor. 2. Repair or replace existing light fixtures and ceiling fans. 3. Repair or replace electrical wall switches and wall outlet devices of 20 amps or less and 120 volts. 4. Repair/replace low voltage (under 77 volts) devices. |
| St. Johns Countythis page | Permit required | Any size |
How to apply in St. Johns County
In St. Johns County, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- For St. Johns County, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- For St. Johns County, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Building Services Division, Growth Management Department sets the exact checklist for St. Johns County.
Where to apply in St. Johns County:
Building Services Division, Growth Management Department
- 4040 Lewis Speedway, St. Augustine, FL 32084
- Phone: 904-827-6800
- Email: bldcodes@sjcfl.us
Electrical Permit in St. Johns County compared with nearby Florida localities
| Locality | Permit needed? | Threshold | What each Florida schedule says | Verified |
|---|---|---|---|---|
| St. Johns County | Permit required | Any size | Electrical Permit Fees (F.S. 553-80): Permit Issuance Fee $11.00, plus itemized charges... | |
| Alachua County | Permit required | Any size | No electrical-specific flat fee is published | |
| Brevard County | It depends | Permits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring. | ...Electrical Permit Application fee table lists a Building Code Review fee of $75.00... | |
| Broward County | Permit required | Any size | Electrical permit is the greater of a $125 minimum base fee or 3.0% of job value, per... | |
| Charlotte County | Permit required | Any size | At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation... |
Inspections and closing out your permit
In St. Johns County, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- In St. Johns County: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- In St. Johns County: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- In St. Johns County: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- In St. Johns County: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- In St. Johns County: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- In St. Johns County: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- In St. Johns County: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the St. Johns County permit portal or by phone at 904-827-6800.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for St. Johns County
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing, altering, or replacing an electrical system in unincorporated St. Johns County.
- Budget the fee. Electrical Permit Fees (F.S. 553-80): Permit Issuance Fee $11.00, plus itemized charges such as Simple Permanent Service or Feeder Panel $24.00, Construction Temporary Service $24.00, and Service Change/Increase Amps $19.00 (plus $42.00 if over 800 amps), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026). Official fee schedule.
- Apply. In St. Johns County, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the St. Johns County permit portal.
- Keep the office details handy. Building Services Division, Growth Management Department. Phone: 904-827-6800. Address: 4040 Lewis Speedway, St. Augustine, FL 32084.
- Plan for inspections. In St. Johns County, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an electrical permit in St. Johns County?
- St. Johns County's general permitting rule explicitly names electrical systems among the work requiring a permit before installation, alteration, or repair, backed by a dedicated Electrical Permit Fees section in the county's fee schedule. This applies to unincorporated St. Johns County; St. Augustine and St. Augustine Beach have their own building departments and separate electrical permitting. Always confirm with the Building Services Division, Growth Management Department before starting.
- How much does an electrical permit cost in St. Johns County?
- Electrical Permit Fees (F.S. 553-80): Permit Issuance Fee $11.00, plus itemized charges such as Simple Permanent Service or Feeder Panel $24.00, Construction Temporary Service $24.00, and Service Change/Increase Amps $19.00 (plus $42.00 if over 800 amps), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026). See the official fee schedule for current amounts.
- Where do you apply for an electrical permit in St. Johns County?
- You can apply through the St. Johns County permit portal or contact the Building Services Division, Growth Management Department directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in St. Johns County?
- Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how St. Johns County applies this before you apply.
From the Library
What else needs a permit in St. Johns County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Any size | ...fall under the general Building Services Fees table: Permit Issuance Fee $14.00... |
| Fence Permit | Permit required | Any size | ...fall under the general Building Services Fees table: Permit Issuance Fee $14.00... |
| HVAC Permit | Permit required | Any size | Mechanical Permit Fees (F.S. 553.80): Permit Issuance $11.00 with a minimum permit fee... |
| Patio Permit | Permit required | Any size | ...fall under the general Building Services Fees table: Permit Issuance Fee $14.00... |
| Plumbing Permit | Permit required | Any size | Plumbing Permit Fees (F.S. 553-80): Permit Issuance Fee $11.00 with a minimum permit fee... |
| Pool Permit | Permit required | pool surface area per the LDC regulated-pool definition, which also uses a 2 foot depth test | Swimming Pool Fees (F.S. 553-80): Permit Issuance $11.00 |
| Roof Replacement Permit | Permit required | Any size | ...fall under the general Building Services Fees table: Permit Issuance Fee $14.00... |
| Shed Permit | Permit required | Any size | ...fall under the general Building Services Fees table: Permit Issuance Fee $14.00... |
| Solar Permit | Permit required | Any size | Solar Permit Fees (F.S. 553.80): Permit Issuance $11.00 with a minimum permit fee of... |
Electrical Permit in other Florida localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not St. Johns County documents; the office above sets the local rules.
How this electrical permit page for St. Johns County was verified. 2 official sources: sjcfl.us, sjcfl.us; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Building Services Division, Growth Management Department. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Electrical Permit requirements across Florida localities