It depends

Sometimes, depending on the project

Before installing or replacing wiring, a meter can, or a breaker panel in unincorporated Brevard County

Confirmed on official page Verified Brevard County Planning and Development Department, Building Permits Division

By Mario Bailey, verified against official sources

Quick answer

Brevard County requires a Residential Electrical permit for installing or replacing electrical wiring, a meter can, or a breaker panel, but not for changing fixtures that do not involve moving or changing wiring. Applications are reviewed by county staff, and licensed electrical contractors can apply online through BASS; owner-builders must apply in person. This applies only to unincorporated Brevard County; incorporated cities have their own building departments.

Typical threshold: Permits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing or replacing wiring, a meter can, or a breaker panel in unincorporated Brevard County

What an electrical permit costs in Brevard County

Line item
electrical permitBy formulaBrevard's Residential Electrical Permit Application fee table lists a Building Code Review fee of $75.00 for the first $1,000 of job value plus $3.25 per $1,000 thereafter, plus a $25.00 Application Processing Fee and state surcharges of 1.5% (BCA) and 1% (FBC). No effective date is shown.

How Brevard County compares in Florida

JurisdictionPermit needed?Threshold
Alachua CountyPermit requiredNot specified
Brevard Countythis pageIt dependsPermits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring.
Broward CountyPermit requiredNot specified
Charlotte CountyPermit requiredNot specified
Clay CountyPermit requiredNot specified
Collier CountyPermit requiredPermits shall not be required for the following: ... Electrical: 1. Repair work performed by licensed electrical contractors that does not exceed $1,500.00 in value of materials and labor. 2. Repair or replace existing light fixtures and ceiling fans. 3. Repair or replace electrical wall switches and wall outlet devices of 20 amps or less and 120 volts. 4. Repair/replace low voltage (under 77 volts) devices.
Hernando CountyPermit requiredNot specified

How to apply in Brevard County

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Brevard County Planning and Development Department, Building Permits Division sets the exact checklist for Brevard County.

Where to apply in Brevard County:

Brevard County Planning and Development Department, Building Permits Division

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Brevard County permit portal or by phone at (321) 633-2187.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in Brevard County?
Brevard County requires a Residential Electrical permit for installing or replacing electrical wiring, a meter can, or a breaker panel, but not for changing fixtures that do not involve moving or changing wiring. Applications are reviewed by county staff, and licensed electrical contractors can apply online through BASS; owner-builders must apply in person. This applies only to unincorporated Brevard County; incorporated cities have their own building departments. Permits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring. Always confirm with the office before starting.
How much does an electrical permit cost in Brevard County?
Brevard's Residential Electrical Permit Application fee table lists a Building Code Review fee of $75.00 for the first $1,000 of job value plus $3.25 per $1,000 thereafter, plus a $25.00 Application Processing Fee and state surcharges of 1.5% (BCA) and 1% (FBC). No effective date is shown. Contact the office for current amounts.
Where do you apply for an electrical permit in Brevard County?
You can apply through the Brevard County permit portal or contact the Brevard County Planning and Development Department, Building Permits Division directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Brevard County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Brevard County applies this before you apply.

From the Library

What else needs a permit in Brevard County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedNot published
Fence PermitIt dependsPermit not required for repair or replacement of less than 50% of an existing fence using the same size and material in the same location.Brevard's Residential Fence Permit Application fee table lists a $25.00 Application...
HVAC PermitPermit requiredNot specifiedBrevard's Residential HVAC/Mechanical Permit Application fee table lists a Building Code...
Plumbing PermitIt dependsPermits are required for the installation or replacement of water, sewer, or gas piping and systems; this does not include changing like-for-like water heaters or fixtures such as sinks.Brevard's Residential Plumbing Permit Application fee table lists a Building Code Review...
Pool PermitIt dependsPermits are issued for in-ground pools and spas, and for above-ground pools with a depth of 24 inches or greater.Brevard's Residential Pool Permit Application fee table lists a Building Code Review fee...
Roof Replacement PermitPermit requiredNot specifiedBrevard's Residential Reroof Permit Application fee table lists a Building Code Review...
Shed PermitIt dependsA permit is required for an accessory structure (shed) over 100 square feet.Sheds are filed under the Residential Addition permit category, whose fee table lists a...
Solar PermitPermit requiredNot specifiedBrevard's Residential Solar Photovoltaic Permit Application fee table lists a Building...

Electrical Permit in other Florida localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Brevard County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Brevard County Planning and Development Department, Building Permits Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page