Permit required
Yes, a permit is required
Before performing new electrical work, a service change, or a generator installation in unincorporated Collier County
By Mario Bailey, verified against official sources
Quick answer
Collier County requires a building permit for electrical work such as service changes, new circuits, low-voltage systems, and generator installations. A narrow local exemption covers minor repairs by a licensed electrical contractor under $1,500 in materials and labor for detached single-family homes, plus specific like-for-like fixture, switch, outlet, and low-voltage device repairs. This applies to unincorporated Collier County; incorporated cities operate their own building departments.
Typical threshold: Permits shall not be required for the following: ... Electrical: 1. Repair work performed by licensed electrical contractors that does not exceed $1,500.00 in value of materials and labor. 2. Repair or replace existing light fixtures and ceiling fans. 3. Repair or replace electrical wall switches and wall outlet devices of 20 amps or less and 120 volts. 4. Repair/replace low voltage (under 77 volts) devices.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before performing new electrical work, a service change, or a generator installation in unincorporated Collier County
What an electrical permit costs in Collier County
How Collier County compares in Florida
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Alachua County | Permit required | Not specified |
| Brevard County | It depends | Permits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring. |
| Broward County | Permit required | Not specified |
| Charlotte County | Permit required | Not specified |
| Clay County | Permit required | Not specified |
| Collier Countythis page | Permit required | Permits shall not be required for the following: ... Electrical: 1. Repair work performed by licensed electrical contractors that does not exceed $1,500.00 in value of materials and labor. 2. Repair or replace existing light fixtures and ceiling fans. 3. Repair or replace electrical wall switches and wall outlet devices of 20 amps or less and 120 volts. 4. Repair/replace low voltage (under 77 volts) devices. |
| Hernando County | Permit required | Not specified |
How to apply in Collier County
In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Growth Management Community Development Department (GMCD), Building Plan Review and Inspection Division (Building Division) sets the exact checklist for Collier County.
Where to apply in Collier County:
Growth Management Community Development Department (GMCD), Building Plan Review and Inspection Division (Building Division)
- North Horseshoe Campus, 2800 Horseshoe Drive North, Naples, FL 34104
- Phone: 239-252-2400
- Email: Permitting.Dept@collier.gov
Inspections and closing out your permit
Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Collier County permit portal or by phone at 239-252-2400.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for Collier County
- Confirm the requirement. Yes, a permit is required. Typical threshold: Permits shall not be required for the following: ... Electrical: 1. Repair work performed by licensed electrical contractors that does not exceed $1,500.00 in value of materials and labor. 2. Repair or replace existing light fixtures and ceiling fans. 3. Repair or replace electrical wall switches and wall outlet devices of 20 amps or less and 120 volts. 4. Repair/replace low voltage (under 77 volts) devices. Usually needed: Before performing new electrical work, a service change, or a generator installation in unincorporated Collier County.
- Budget the fee. Fee Schedule (Resolution 2025-231, effective January 1, 2026), Electrical Permit Review Fees: valuation up to $4,999.99, "$100.00 plus applicable inspection fees as required"; "The minimum for any electrical permit review fee shall be $150.00 per unit or tenant space plus applicable inspection fees as required.". Official fee schedule.
- Apply. In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the Collier County permit portal.
- Keep the office details handy. Growth Management Community Development Department (GMCD), Building Plan Review and Inspection Division (Building Division). Phone: 239-252-2400. Address: North Horseshoe Campus, 2800 Horseshoe Drive North, Naples, FL 34104.
- Plan for inspections. Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an electrical permit in Collier County?
- Collier County requires a building permit for electrical work such as service changes, new circuits, low-voltage systems, and generator installations. A narrow local exemption covers minor repairs by a licensed electrical contractor under $1,500 in materials and labor for detached single-family homes, plus specific like-for-like fixture, switch, outlet, and low-voltage device repairs. This applies to unincorporated Collier County; incorporated cities operate their own building departments. Always confirm with the Growth Management Community Development Department (GMCD), Building Plan Review and Inspection Division (Building Division) before starting.
- How much does an electrical permit cost in Collier County?
- Fee Schedule (Resolution 2025-231, effective January 1, 2026), Electrical Permit Review Fees: valuation up to $4,999.99, "$100.00 plus applicable inspection fees as required"; "The minimum for any electrical permit review fee shall be $150.00 per unit or tenant space plus applicable inspection fees as required.". See the official fee schedule for current amounts.
- Where do you apply for an electrical permit in Collier County?
- You can apply through the Collier County permit portal or contact the Growth Management Community Development Department (GMCD), Building Plan Review and Inspection Division (Building Division) directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in Collier County?
- Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Collier County applies this before you apply.
From the Library
What else needs a permit in Collier County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Not specified | Not published |
| Fence Permit | Permit required | Not specified | Fee Schedule (Resolution 2025-231, BCC approved October 28, 2025, effective January 1... |
| HVAC Permit | Permit required | This is a self-issuing permit available on the portal, unless any of the criteria listed below apply. If they do, the permit will follow the standard permitting and plan review process: Greater than 5 tons (single family); Located on the roof of a building; Adding concrete slab; Changing size of equipment; Moving location of equipment; Any changes to duct work; Adding a new mini-split; If owner-builder; In a trailer or manufactured home; If commercial building; If multi-family building. | Fee Schedule (Resolution 2025-231, effective January 1, 2026), Mechanical Permit Review... |
| Patio Permit | It depends | Permits shall not be required for the enclosure of an existing covered patio, balcony, or porch with screening only; a permit is required to build a new patio cover, screen enclosure, or other patio structure. | Not published |
| Plumbing Permit | Permit required | Permits shall not be required for the following: ... Plumbing: 1. Repair work performed by licensed plumbing contractors that does not exceed $1,500.00 in value of materials and labor. [Followed by 16 specific exempted repairs/replacements, e.g. faucets, water closets, sinks, garbage disposals, dishwashers, and like-for-like electric water heaters up to 52-gallon capacity.] | Fee Schedule (Resolution 2025-231, effective January 1, 2026), Plumbing and Gas Permit... |
| Pool Permit | Permit required | Not specified | Fee Schedule (Resolution 2025-231, effective January 1, 2026), Section U (Pool or Spa... |
| Roof Replacement Permit | Permit required | Collier County's locally adopted building code amendment exempts from permit only the repair of any roof covering not exceeding $1,500.00 in value of materials and labor, or repair work not exceeding two roofing squares (200 square feet) in extent; this exemption is for roof repair, not for roof replacement/reroofing (removing and replacing the covering), which requires a standard Reroof permit. | No roof-specific line item is published |
| Shed Permit | Permit required | Not specified | Not published |
| Solar Permit | Permit required | Not specified | Fee Schedule (Resolution 2025-231, effective January 1, 2026), Solar Permit Review Fees:... |
Electrical Permit in other Florida localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Collier County documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with Growth Management Community Development Department (GMCD), Building Plan Review and Inspection Division (Building Division). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Electrical Permit requirements across Florida localities
Permit office
Growth Management Community Development Department (GMCD), Building Plan Review and Inspection Division (Building Division)
239-252-2400Permit portalFlorida rule changes
- Broward County, FL updates building permit fee schedule (Ordinance 2025-038)
Ord. 2025-038 ·
- Florida waives permits for small single-family jobs under $7,500 (HB 803)