What does a building permit cost?
By Mario Bailey Last checked
We read the official fee schedule of every locality we cover and recorded what it says for 1671 permit scenarios across 166 US localities. Each entry below quotes the schedule's own terms, with the verification date. Where a locality publishes no figure, or hands the permit to a state agency, we say that instead of guessing. Many localities bill by project valuation, so a single flat number often does not exist; the notes keep that honesty.
Median fees measured from real permit records
For jurisdictions whose open-data portals publish issued permits, we compute the median fee from the records themselves. These are actual amounts charged, not schedule text.
| Jurisdiction | Median fee | Records |
|---|---|---|
| Chicago, Illinois | $1,142 | 5,329 |
| Mesa, Arizona | $520 | 5,364 |
| Boston, Massachusetts | $90 | 19,468 |
Medians, not averages, so a few large projects cannot skew the figure. Full context in the turnaround study.
Bathroom Remodel permit fees
Verified in 45 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states. Mechanical or Plumbing Permit (Chapter 6 Schedule of Permit and Review Fees, as amended through January 1, 2026): $5.25 for the first $1,000 valuation or any part thereof, $5.25 for each additional $1,000 or part thereof, minimum fee $65.00.
Verified · Official fee schedule
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule. Plumbing and electrical permits are separate, with fees by valuation.
Verified · Official fee schedule
-
Trade-only remodels: AMC 23.10.109 Table 3-A item 3.A, "Trade Permits (Plumbing, mechanical, or electrical work but no structural or alteration work)": $175, 2 inspections; or a retrofit permit under Table 3-E at $175 with 2 inspections (for example "Electrical, plumbing or mechanical alterations to a residential building containing 4 or fewer dwelling units"); a Table 3-A item 3 trade permit also carries the nonrefundable $15 digital maintenance fee for "Miscellaneous Building Permits (per item 3)" (Table 3-A item 4). Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026). Remodels with structural or alteration work: Table 3-A item 2, "Up to $50,000 (Repairs, decks, and minor alterations only)" $350 with 4 inspections, otherwise $0.009 * (Valuation), minimum $450, plus Table 3-B plan review.
Verified · Official fee schedule
-
Greenville County, South Carolina
Priced as an alteration on the valuation table at actual project cost (the schedule's note reads "*** Renovations, alterations, and swimming pools to be used in the above table will be based on the actual cost of the project."), plus trade fees: plumbing minimum fee per permit $72.00 and Fixtures $6.00 each; electrical minimum fee per permit $72.00. Building work is priced on the Residential Permit Fees schedule by total valuation: "$1,000 and less" is "$36.00 minimum permit fee", and "$1,000 to $50,000" is "$22.50 for the first $1,000 plus $7.50 for each additional thousand or fraction thereof, to and including $50,000". The schedule PDF carries no effective date or resolution number; the department's notice says "Starting July 1, 2025, Residential and Commercial building permit fees will increase by 20 percent."
Verified · Official fee schedule
-
2026 Building Permit Valuation/Fee Schedule (City of Sioux Falls, fee schedule dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule": "$1-4,000" $40.00; "$4,001-25,000" "$32.50 for the first $2,000 plus $6.00 for each additional $1,000 or fraction thereof, to and including $25,000"; "$25,001-50,000" "$170.50 for the first $25,000 plus $4.50 for each additional $1,000 or fraction thereof". Residential projects have no plan review fee (Residential Plan Review page). Plumbing and electrical permits are separate, on the MEP valuation schedule ($40 up to $5,000 of trade valuation).
Verified · Official fee schedule
-
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
Verified · Official fee schedule
-
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Verified · Official fee schedule
-
Building permit if walls or layout change (building permit fee from the valuation table in the Salt Lake City Consolidated Fee Schedule (FY2027, "Amended 06/16/2026 by Ord. 2026 - 29"), for example "$0.01 - $500.00" $55.97 and "$2,000.01 - $25,000.00" "$115.97 for the first $2,000 plus $20 for each additional $1,000 or fraction thereof, to and including $25,000", plus a plan review fee of "65% of building permit fee" (18.20.020.B)); plumbing permit "Base fee" $59 plus $8 per fixture (18.56.040); electrical "Minor remodel and additional circuits" $40 plus the $59 base fee, or "Homeowner electrical remodel permit" $48 (18.36.100), all from the Salt Lake City Consolidated Fee Schedule (FY2027, "Amended 06/16/2026 by Ord. 2026 - 29").
Verified · Official fee schedule
-
Valuation-based under Table 1A-A Building Permit Fees (July 2026) with separate electrical (Table 1A-E) and plumbing (Table 1A-C, "CATEGORY 1P" includes "a single kitchen or bathroom remodel", $290) permits. DBI's page: "Minimum valuations are $24,663 per kitchen and $20,552 per bathroom, according to DBI's cost schedule."
Verified · Official fee schedule
-
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
Verified · Official fee schedule
Plus 33 more localities with a verified note, each on its own permit page. Browse every bathroom remodel page
Deck permit fees
Verified in 157 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states.
Verified · Official fee schedule
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
A deck over the exemption is a building permit priced from the one- and two-family valuation table in Sec. 18-20(b)(2): $52.00 up to $1,000.00 of valuation, $58.00 from $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 per additional $1,000.00 or fraction thereof to $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. One- and two-family work carries no separate construction document review fee. A reinspection is $75.00 under Sec. 18-20(h)(6), and building without the permit first triples the permit fee under Sec. 18-20(e)(2).
Verified · Official fee schedule
-
Newark municipal code Chapter 7:2-3.1c prices deck work as 'Building Renovation and Alteration', 'Fees based on estimated cost of construction for all building types': $28 per $1,000 between $0 and $50,000, $21 per $1,000 from $50,001 to $100,000, and $17 per $1,000 over $100,000, plus a DCA administrative surcharge of $0.80 per $1,000. 'Minimum Building Permit: $58.' (Ord. 6 S+FD, 9-5-2007; code current through 12-20-2023.)
Verified · Official fee schedule
-
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'
Verified · Official fee schedule
-
Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". "Other Building Permit Fees: Minor Renovation Projects (valued less than $75,000) | Residential Renovation Permit | $125" and "Extensive Renovation Projects (valued at $75,000 or greater) | Extensive Renovation Permit | $4 per $1,000 of construction value". The schedule also states "Building permit fees include Plan Review and Building Inspections" and prices reinspections at "First Follow-up Inspection $0", "Second Follow-up Inspection $50", "Third and each Subsequent Follow-up Inspection $100", with "Penalty for Construction Prior to Issuance of Permit 100% of the Permit Fee". Caution on figures: the department's older undated handout "Regulatory Requirements for Residential Permits" still prices this work at "$0.006 x Value of Construction" and the 2012-era step sheets at "$6 per $1,000 of estimated construction cost (minimum fee is $30)", both of which predate the July 1, 2024 schedule. Confirm the current amount with the Permits Section at 678-518-6020 before budgeting.
Verified · Official fee schedule
-
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule.
Verified · Official fee schedule
-
AMC 23.10.109 Table 3-A item 2, Residential Construction: "Up to $50,000 (Repairs, decks, and minor alterations only)" $350 with 4 inspections; plus Table 3-B residential plan review ("Regular Plan Review" 0.005 *(Valuation), minimum $75; the 50% repair-only rate "does not include minor alterations or decks"), land use plan review at 15% of the Table 3-A fee (minimum $75), and the $50 residential digital maintenance fee. Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026).
Verified · Official fee schedule
-
No deck line item appears in the Building Inspection Department Service Fee Schedule (Schedule A, effective July 1, 2024). A deck permit is priced from construction valuation using the Schedule A building permit fee table (for example, '$381.46 for the first $10,000 plus $8.88 for each additional $1,000.00 or fraction thereof, to and including $50,000'), plus building plan review at 80% of the building permit fee with a $140.00 minimum, plus a $20.00 single-permit processing fee.
Verified · Official fee schedule
-
PDS 613 (effective 07/10/2026, FY 25/26) publishes no line item named "deck." Under "PROJECT TYPES NOT LISTED IN THE TABLES ABOVE" the fee is calculated from the Schedule of Building Permit Fees Based on Valuation, which is $374.00 for the first $10,000.00 of total valuation plus $1.00 for each additional $1,000.00 or fraction thereof up to $50,000.00, with a plan review fee of 65% of the building permit fee.
Verified · Official fee schedule
-
Building permit fees are valuation-based under Table 1A-A Building Permit Fees ("July 2026", applying "to all building permits issued on and after July 12, 2026"): "The Building Permit Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to $2,000 the plan review fee is "$181 for the first $500 plus $8.60 for each additional $100 or fraction thereof" and the permit issuance fee is "$206 for the first $500 plus $4 for each additional $100 or fraction thereof"; for $2,001 to $50,000 they are "$310 for the first $2,000 plus $28.35" and "$266 for the first $2,000 plus $8.56" for each additional $1,000.
Verified · Official fee schedule
-
At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge; a $22 zoning review fee is due at issuance.
Verified
Plus 145 more localities with a verified note, each on its own permit page. Browse every deck page
Electrical permit fees
Verified in 162 localities. Dollar figures appearing in those schedules run from $0.01 to $100,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Electrical permits for one- and two-family detached dwellings are priced from the same valuation table as every other trade, Sec. 18-20(b)(2): $52.00 for total valuation of $0.00 to $1,000.00, $58.00 for $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. Sec. 18-20(h)(9) adds a distinct $54.00 electrical service reconnect fee when an owner asks for an inspection of an existing service so the utility can reconnect, creditable toward a permit fee if permitted work turns out to be needed, and waived where the service was disconnected by a fire in the previous 90 days.
Verified · Official fee schedule
-
Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". The schedule has no separate electrical trade permit line; the department's "Regulatory Requirements for Residential Permits" lists a combined "Mechanical, Electrical, Plumbing" application type at "$0.006 x Value of Construction", which predates the July 1, 2024 schedule. Standalone residential work under $75,000 falls in the "Residential Renovation Permit | $125" band. Confirm with the Permits Section at 678-518-6020.
Verified · Official fee schedule
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge.
Verified
-
Electrical permits are charged as a trade permit under the LUESA Fee Ordinance (revised July 1, 2026): $1 to $3,000 in total construction permit value is a $59.70 minimum fee per trade for projects not requiring plan review, and $3,001 to $50,000 is '$59.70 plus $12.19 per $1,000 or part over $3,000', plus a $3.00 technology charge on all permits. Where the owner serves as the contractor and total construction permit value is less than $40,000, the ordinance charges $60.00 per BEMP trade base permit fee, $45.00 per BEMP trade plan review if required and $45.00 per inspection trip. Item 29 of the same ordinance charges the original permit fee times 3.75 for work started without a permit.
Verified · Official fee schedule
-
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
Verified · Official fee schedule
-
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
Verified · Official fee schedule
-
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Verified · Official fee schedule
-
2026 Mechanical, Electrical, or Plumbing Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for "$0.01 to $5,000.00" and "$40 for the first $5,000, plus $6 for each additional $1,000 or fraction thereof, to and including $25,000"; a homeowner's permit is $25 plus that fee (Code of Ordinances Table 104.5 "Homeowner s permit" $25 for plumbing; IMC Table No. 1-A "Homeowner's permit" $25 for mechanical). Electrical homeowner's permits are available only to an owner-occupant wiring his or her own home (Code of Ordinances 150.233).
Verified · Official fee schedule
-
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
Verified · Official fee schedule
-
A stand-alone electrical permit is valuation based on the same Residential Rate Table, $220 minimum for the $0 to $8,333 bracket, plus a 4% technology improvement fee capped at $800, per the Development Services Schedule of Fees (Ord. 5524, Dec 2025)
Verified · Official fee schedule
-
2026 PLI Fee Schedule, effective 1/1/2026: "Base Permit Fee (Residential) $6.00 per $1,000 of Construction Value (Minimum: $130 - Maximum: $8,000)", 40% non-refundable at application and the remainder at issuance, plus a $4.50 State Education and Training Fund fee, a $5.00 Digital Record Retention Fee and a technology fee of $2.00 to $25.00 by base fee range. An Electrical trade license is $90.00 initial and annual renewal.
Verified · Official fee schedule
Plus 150 more localities with a verified note, each on its own permit page. Browse every electrical page
EV Charger permit fees
Verified in 44 localities. Dollar figures appearing in those schedules run from $0.01 to $50,001, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
Verified · Official fee schedule
-
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
Verified · Official fee schedule
-
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value. EV charger projects may use the expedited clean-energy process under ROH 18-5.10.
Verified · Official fee schedule
-
2026 Mechanical, Electrical, or Plumbing Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for "$0.01 to $5,000.00" and "$40 for the first $5,000, plus $6 for each additional $1,000 or fraction thereof, to and including $25,000"; a homeowner's permit is $25 plus that fee (Code of Ordinances Table 104.5 "Homeowner s permit" $25 for plumbing; IMC Table No. 1-A "Homeowner's permit" $25 for mechanical).
Verified · Official fee schedule
-
Charged as a standard electrical permit at $25 per $1,000 of estimated cost with a $63 minimum and $18,975 maximum; no EV-specific fee line exists, per the city's electrical permit page
Verified · Official fee schedule
-
No EV-specific fee; charger circuits operate above 50 volts so they take the standard existing-dwelling electrical permit at $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy, per the county electrical permit and fee pages
Verified · Official fee schedule
-
Residential (up to 3 units) building, plumbing, mechanical and electrical permits: 0.50% of estimated construction cost; "Residential less than estimated $2,500.00": $45.00; "Minimum Permit Fee": $110.00; "All Permits non-refundable application fee": $40.00; "Dry run/Up-Front per $1,000.00 of estimated construction value": $2.80 (no up-front fee on residential work under $2,500); "Solid Waste Residential Surcharge" $0.22 per $100.00 of estimated cost (minimum $26.00, maximum $600.00). State and Miami-Dade County surcharges are extra. Exhibit C Fee Schedule, Building, Chapters 10, 17, 20, adopted by Resolution R-26-0200 (Ordinance 14456), April 23, 2026.
Verified · Official fee schedule
-
Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2).
Verified · Official fee schedule
-
LMCO 150.096 (revised 2/6/2024): additional wiring in a one- or two-family residence is $75 for work costing $750 or less and $100 for work over $750.
Verified · Official fee schedule
-
Code points to Table 1A-E for "the applicable EV Charging Station fees", but the July 2026 Table 1A-E carries no EV-specific line; Category 1 residential wiring applies ("Up to 10 outlets and/or devices (1 inspection)" $305).
Verified · Official fee schedule
-
AMC 23.10.109 Table 3-A item 3.A, "Trade Permits (Plumbing, mechanical, or electrical work but no structural or alteration work)": $175, 2 inspections; or a retrofit permit under Table 3-E at $175 with 2 inspections (for example "Electrical, plumbing or mechanical alterations to a residential building containing 4 or fewer dwelling units"); a Table 3-A item 3 trade permit also carries the nonrefundable $15 digital maintenance fee for "Miscellaneous Building Permits (per item 3)" (Table 3-A item 4). Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026). A charger on "One new 20 amp circuit" fits Table 3-E item 1.A; a typical 240-volt charger circuit is an electrical alteration to a residential building under item 2.C, also $175 with 2 inspections.
Verified · Official fee schedule
Plus 32 more localities with a verified note, each on its own permit page. Browse every ev charger page
Fence permit fees
Verified in 150 localities. Dollar figures appearing in those schedules run from $0.05 to $150,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; no fence-specific line item, per the 2024 Fee Schedule effective 7/1/2024
Verified · Official fee schedule
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
No fence-specific fee. A fence that needs a building permit is residential construction under AMC 23.10.109 Table 3-A item 2 ("All others" $0.009 * (Valuation), minimum $450, or $350 for work up to $50,000 limited to repairs, decks and minor alterations), plus Table 3-B plan review. Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026).
Verified · Official fee schedule
-
Building permit fees are valuation-based under Table 1A-A Building Permit Fees ("July 2026", applying "to all building permits issued on and after July 12, 2026"): "The Building Permit Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to $2,000 the plan review fee is "$181 for the first $500 plus $8.60 for each additional $100 or fraction thereof" and the permit issuance fee is "$206 for the first $500 plus $4 for each additional $100 or fraction thereof"; for $2,001 to $50,000 they are "$310 for the first $2,000 plus $28.35" and "$266 for the first $2,000 plus $8.56" for each additional $1,000.
Verified · Official fee schedule
-
Charlotte County's Residential Fence page lists fees due at issuance: Zoning Review $30, plus a building fee of 0.004 x ICC valuation (only if valuation is $50,000 or more) and a surcharge of 0.025 x the building fee.
Verified
-
No fence-specific fee line item is published. Fence permits fall under the general Building Services Fees table: Permit Issuance Fee $14.00, plus Total Valuation of Building fee (minimum $19.00, or $11.00 for the first $1,000 plus $2.63 for each additional thousand or fraction thereof up to $50,000; higher tiers apply above that), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026).
Verified · Official fee schedule
-
The Planning Services Fence Guidelines handout (revised 3/3/2025) states a flat Fence Permit Fee of $75.00. The Building Permit Fees schedule (effective October 2019, revised 7/15/2025) adds the line "Fences over 7 feet tall ... building permit fee", so a fence taller than 7 feet is charged the $15 base application fee plus the estimated project cost permit fee ($100 for project cost up to $1,000; $100 plus $10 per $1,000 from $1,000 to $50,000) plus a plan examination fee of 20% of the building permit fee. Properties in a historic district also pay a $35 historic district staff review fee.
Verified · Official fee schedule
-
No fence line item exists. A fence is billed as a residential alteration or repair under the Building and Trade Permit Fee Schedule, approved by Ordinance Nos. 2017-131, 2019-064 and 2019-072, effective October 1, 2019: a $40.00 non-refundable application fee "required for all building and trade permits," plus a construction-cost based permit fee that is "Application Fee Only" at $1,000 or less of construction cost and "$15.00 for the first $1,000 construction valuation, plus $5.00 for each additional thousand or fraction thereof, to and including $50,000" above that. A plan review fee equal to 50% of the building permit fee applies when valuation exceeds $1,000 and plans must be reviewed. Starting without a permit doubles the money: the schedule's Penalties clause says "Where work for which a permit is required by this code is started or proceeded prior to obtaining said permit, the fees herein specified shall be doubled, but the payment of such double fee shall neither relieve any persons from fully complying with the requirements of this code in the execution of the work nor from any other penalties prescribed herein."
Verified · Official fee schedule
-
Greenville County, South Carolina
No fence line item on the Residential Permit Fees schedule. A fence that needs a permit would fall under the schedule's valuation table: Building work is priced on the Residential Permit Fees schedule by total valuation: "$1,000 and less" is "$36.00 minimum permit fee", and "$1,000 to $50,000" is "$22.50 for the first $1,000 plus $7.50 for each additional thousand or fraction thereof, to and including $50,000". The schedule PDF carries no effective date or resolution number; the department's notice says "Starting July 1, 2025, Residential and Commercial building permit fees will increase by 20 percent."
Verified · Official fee schedule
-
No fence-specific line; a fence needing a building permit bills under the Section B101 valuation table, no fee for work valued $1,000 or less unless an inspection is required ($15 per inspection), then $15 for the first $1,000 plus $5 per additional thousand up to $50,000, per the county Schedule of Building Permit Fees
Verified · Official fee schedule
-
A fence reviewed by Zoning only pays the Department of City Planning fee, "Residential Zoning Review $1.00/$1000 of project cost (min. $50.00, max $40,000.00)", plus a technology fee of $2.00 to $25.00 based on the base fee range. If PLI review is also triggered, the 2026 PLI Fee Schedule effective 1/1/2026 adds "Base Permit Fee (Residential) $6.00 per $1,000 of Construction Value (Minimum: $130 - Maximum: $8,000)", with 40% of the base fee non-refundable and due at application and the remainder due at issuance, plus a $4.50 State Education and Training Fund fee and a $5.00 Digital Record Retention Fee per permit.
Verified · Official fee schedule
Plus 138 more localities with a verified note, each on its own permit page. Browse every fence page
HVAC permit fees
Verified in 162 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
M-0 fee issuance cost per permit $20.00, M-3.1 fee for the first $1,000 valuation $15.00 then $8.00 for each additional $1,000 under $1,000,000, M-4 minimum permit fee $15.00, and M-3.2.1 SINGLE FAMILY RESIDENTS ONLY, mechanical permit fees shall be based on total valuation (contract price) based on a minimum $1,000.00 per ton, per the 2022 Fee Schedule, Mechanical Permit and Inspection Fees Schedule. Work commencing before permit issuance is charged double fee. All fees exclude an administrative charge of $4.00 and a residential surcharge of $1.00, so $5.00 is added to the residential total, per the 2022 Fee Schedule.
Verified · Official fee schedule
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". The schedule has no separate mechanical trade permit line; the department's "Regulatory Requirements for Residential Permits" lists a combined "Mechanical, Electrical, Plumbing" application type priced at "$0.006 x Value of Construction", which predates the July 1, 2024 schedule. A standalone residential change-out under $75,000 falls in the "Residential Renovation Permit | $125" band. Confirm with the Permits Section at 678-518-6020.
Verified · Official fee schedule
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
Heating/air mechanical permit for replacements, repairs, alterations and additions by total valuation: "$500.00 and less" no fee unless an inspection is required ($25.75 per inspection); "$100.01 to $50,000.00" "Fifty-One 50/100 Dollars ($51.50) for the first two thousand dollars ($2,000.00) plus Six and 18/100 Dollars ($6.18) for each additional one thousand dollars ($1,000.00) or fraction thereof"; minimum fee for any heating/air or mechanical permit $50.00; new one- and two-family dwellings $0.11 per square foot. Little Rock Code Sec. 8-31(c), as amended through Ord. No. 22,703 (December 16, 2025), read on Municode.
Verified · Official fee schedule
-
At application: $90 flat building fee unless valuation is $50,000 or more (then 0.004 x ICC valuation), plus a 0.025 x building-fee surcharge.
Verified
-
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
Verified · Official fee schedule
-
Contra Costa County, California
Land Development Fee Schedule S-002 D.6, "Mechanical Permit (Other) $75.00 minimum." Fees for mechanical work not covered by the new dwelling, addition or alteration, new commercial, shell, or tenant improvement tiers are calculated from the S-002 A.1 Building Permit valuation table, which starts at $75.00 for improvement value up to $2,000 plus $13.75 for each additional $1,000. Mechanical fees for an addition or alteration to a dwelling unit start at $75.00 for improvement value up to $25,000. Fee schedule adopted May 24, 2022, effective August 10, 2022.
Verified · Official fee schedule
-
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
Verified · Official fee schedule
-
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Verified · Official fee schedule
-
2026 Mechanical, Electrical, or Plumbing Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for "$0.01 to $5,000.00" and "$40 for the first $5,000, plus $6 for each additional $1,000 or fraction thereof, to and including $25,000"; a homeowner's permit is $25 plus that fee (Code of Ordinances Table 104.5 "Homeowner s permit" $25 for plumbing; IMC Table No. 1-A "Homeowner's permit" $25 for mechanical).
Verified · Official fee schedule
-
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
Verified · Official fee schedule
Plus 150 more localities with a verified note, each on its own permit page. Browse every hvac page
Patio permit fees
Verified in 110 localities. Dollar figures appearing in those schedules run from $0.03 to $150,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'
Verified · Official fee schedule
-
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; no patio-specific line item, per the 2024 Fee Schedule effective 7/1/2024
Verified · Official fee schedule
-
No patio-specific fee line item is published. Patio permits fall under the general Building Services Fees table: Permit Issuance Fee $14.00, plus Total Valuation of Building fee (minimum $19.00, or $11.00 for the first $1,000 plus $2.63 for each additional thousand up to $50,000; higher tiers apply above that), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026).
Verified · Official fee schedule
-
No patio line in Newark municipal code Chapter 7:2-3.1. A roofed patio cover is priced either as an addition ($0.03 per cubic foot for residential buildings) or as renovation and alteration ($28 per $1,000 of estimated cost between $0 and $50,000), subject to the 'Minimum Building Permit: $58.' (Ord. 6 S+FD, 9-5-2007.)
Verified · Official fee schedule
-
No patio-specific line; billed under the Section B101 valuation table, $15 for the first $1,000 plus $5 per additional thousand up to $50,000, plus a plan-check fee of half the permit fee above $1,000, per the county Schedule of Building Permit Fees
Verified · Official fee schedule
-
Los Angeles County, California
No patio line item is published. A patio cover or patio enclosure is priced from the valuation-based Table 1-A Building Permit Fees ($65.36 for a total valuation of $0 to and including $700; $98.09 for more than $700 to and including $25,000 plus $25.27 for each additional $1,000 or fraction thereof in excess of $1,000), plus the $41.35 permit issuance fee. Building Code Fee Schedule (Title 26, Ord. No. 2013-0048), effective July 1, 2026.
Verified · Official fee schedule
-
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
Verified · Official fee schedule
-
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Verified · Official fee schedule
-
No building permit fee for an exempt patio. A Standard Grading Plan Application may be required depending on size and disturbed area (Do I Need a Permit? guide); a raised patio that needs a building permit is valuation-based: Building permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 | $242.00 plus .010 times estimated cost above $25,000.00", plus "A non-refundable application fee of $43.00 will be added to all building permits." Minimum Building Permit Fee $86.00 (Permit Fees page, effective October 1, 2024).
Verified · Official fee schedule
-
Building permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to $500.00": $23.50; "$2,001.00 to $25,000.00": "$69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00 or fraction thereof"), multiplied by the Albuquerque Regional Modifier of (.50) for one- and two-family dwellings, minimum fee $23.50; plan review fee is 65 percent of the building permit fee, paid at submittal. City of Albuquerque 2024 Uniform Administrative Code (UAC), Section 112 and Tables 112-A through 112-G, cover date effective January 1, 2025.
Verified · Official fee schedule
-
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
Verified · Official fee schedule
Plus 98 more localities with a verified note, each on its own permit page. Browse every patio page
Plumbing permit fees
Verified in 162 localities. Dollar figures appearing in those schedules run from $0.01 to $100,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Plumbing permits for one- and two-family detached dwellings use the Sec. 18-20(b)(2) valuation table: $52.00 for total valuation of $0.00 to $1,000.00, $58.00 for $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. Water and sewer service line permits are billed separately by the Water Services Department under the KC Water Rules and Regulations for Water Service Lines (May 2022), not under Sec. 18-20; that counter is reachable at 816-513-2174.
Verified · Official fee schedule
-
Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". The schedule has no separate plumbing trade permit line; the department's "Regulatory Requirements for Residential Permits" lists a combined "Mechanical, Electrical, Plumbing" application type at "$0.006 x Value of Construction", which predates the July 1, 2024 schedule. Standalone residential work under $75,000 falls in the "Residential Renovation Permit | $125" band. Confirm with the Permits Section at 678-518-6020.
Verified · Official fee schedule
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge.
Verified
-
Plumbing is charged as a trade permit under the LUESA Fee Ordinance (revised July 1, 2026): $1 to $3,000 in total construction permit value is a $59.70 minimum fee per trade for projects not requiring plan review, and $3,001 to $50,000 is '$59.70 plus $12.19 per $1,000 or part over $3,000', plus a $3.00 technology charge on all permits. Water heater changeouts fall under item D.1, Appliance/Equipment Change Out, which covers 'hot water heaters limited to less than 50 gal. or 5500 watts input for electric and 50 gal. or 55,000 BTU for gas' and charges a total permit fee for both trade permits combined of 1.5 times the minimum permit fee when issued through Trade Internet Permitting, or 2 times the maximum permit fee when issued any other way.
Verified · Official fee schedule
-
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
Verified · Official fee schedule
-
Limited Alteration Application is the usual homeowner-scale route. Table 28-112.2 item 11 sets the one-, two- or three-family LAA minimum filing fee at $130.00, and DOB's "Limited Alteration Application (LAA) Fees and Penalties, Category 1 & 2 Filing, 1, 2, 3 Family Fees" chart prices it at $130.00 for any estimated job cost up to $5,000, rising by $2.60 per $1,000 above that ($143.00 at $9,001 to $10,000; $208.00 at $34,001 to $35,000). The matching 1 and 2 family penalty for filing after the fact starts at $780.00. Full plumbing alterations are filed as work type PL, priced on construction cost with a PW3 (DOB PW3 fee-structure sheet, Rev. 04/25).
Verified · Official fee schedule
-
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
Verified · Official fee schedule
-
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Verified · Official fee schedule
-
Table 104.5 Plumbing Permit Fees (Code of Ordinances 150.302, 2024 UPC adopted by Ord. 6-26, passed 1-20-2026): "$0.01 to $5,000.00" of plumbing valuation $40; "$5,000.01 to $25,000.00" "$40 for the first $5,000, plus $6 for each additional $1,000 or fraction thereof, to and including $25,000"; "Homeowner s permit." $25.
Verified · Official fee schedule
-
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
Verified · Official fee schedule
-
Plumbing permit fees are established by City Ordinance 71644. The application fee for all plumbing permits is $30.00. Fixtures (floor drain, sump, water heater, reduced pressure backflow device or double gate/double check valve, roof drain or trapped outlet) are $10.00 each; a tap, water connection or extension is $25.00 each; a sewer extension, connection or repair is $25.00 each; irrigation system zones are $25.00 each; rough inspection $25.00; finish inspection $25.00; re-inspection $30.00. Starting work before the permit issues triggers a surcharge that scales with the permit fee, from $35.00 on a $0 to $50.00 permit up to $1,005.00 over $10,000.00.
Verified · Official fee schedule
Plus 150 more localities with a verified note, each on its own permit page. Browse every plumbing page
Pool permit fees
Verified in 161 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states. Pool heaters also need a mechanical permit for the heater and gas piping.
Verified · Official fee schedule
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
No swimming pool line item appears in the Building Inspection Department Service Fee Schedule (Schedule A, effective July 1, 2024). A pool permit is priced from construction valuation on the Schedule A table, plus building plan review at '80% of the Building Permit fees, $140.00 minimum', plus a $20.00 single-permit processing fee or $30.00 for a combo permit, plus state Strong Motion (SMIP) fees of '$10 per $100,000 valuation' for residential work and CBSC fees of '$1 per $25,000 valuation and $1 minimum'.
Verified · Official fee schedule
-
The pool building permit is priced from the one- and two-family valuation table in Sec. 18-20(b)(2): $52.00 up to $1,000.00 of valuation, $58.00 from $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. Information Bulletin IB119 is explicit that the valuation you declare should exclude the electrical and plumbing work, "because this type of work will require separate supplemental permits," each priced from the same table. A structural plan review may be added when the pool is 10 feet or closer to a building on the property.
Verified · Official fee schedule
-
The county building permit is priced off total construction permit value under the LUESA Fee Ordinance (revised July 1, 2026): $3,001 to $50,000 is '$59.70 plus $12.19 per $1,000 or part over $3,000' and $50,001 to $100,000 is '$632.57 plus $5.49 per $1,000 or part over $50,000', plus a $3.00 technology charge on all permits. The associated electrical and any plumbing permits are separate trade permits. The City of Charlotte FY 2025 Individual Residential Lot Fee Schedule charges $50 Stormwater Services Review for 'Additions, Deck, Pool, Retaining Wall, Shed, Detached Structure' plus $70 Residential Zoning, effective for projects submitted July 1, 2024 to June 30, 2025.
Verified · Official fee schedule
-
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.' Electrical Permit Fee Schedule, Document #4100 dated 7/16/24: 'Residential Swimming Pool 65.00 ea.', with 'Minimum Permit Fee 85.00' and 'Extra Inspection Fee, First Follow-up 45.00'.
Verified · Official fee schedule
-
The pool guideline says the Application Fee, Plan Review Fee and Building Permit Fee all come from page 4 of the Building and Trade Permit Fee Schedule, whose construction-cost table covers "ALL SWIMMING POOLS - NEW CONSTRUCTION, ALTERATIONS & REPAIRS." That is a $40.00 non-refundable application fee, a permit fee of "$15.00 for the first $1,000 construction valuation, plus $5.00 for each additional thousand or fraction thereof, to and including $50,000" (then $260.00 plus $4.00 per additional thousand from $50,001 to $100,000), and a plan review fee equal to 50% of the permit fee. Schedule approved by Ordinance Nos. 2017-131, 2019-064 and 2019-072, effective October 1, 2019. Separate $40.00 application fees apply to the electrical and fuel gas sub-permits.
Verified · Official fee schedule
-
No pool-specific line; billed under the Section B101 valuation table, for example $260 for the first $50,000 of value plus $4 per additional thousand up to $100,000, plus a plan-check fee of half the permit fee, per the county Schedule of Building Permit Fees
Verified · Official fee schedule
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule. Electrical work for pumps, heaters and lighting needs a separate electrical permit.
Verified · Official fee schedule
-
No item-specific fee. Residential work is priced under AMC 23.10.109 Table 3-A item 2, "Residential Construction (new construction, additions, alterations, and repairs)": "Up to $50,000 (Repairs, decks, and minor alterations only)" $350 with 4 inspections, "All others" $0.009 * (Valuation), minimum $450; plus Table 3-B residential plan review ("Regular Plan Review" 0.005 *(Valuation), minimum $75; land use plan review 15% of the Table 3-A fee, minimum $75) and a $50 digital maintenance fee (Table 3-A item 4.B). Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026). Pool wiring takes an electrical permit (Table 3-A item 3.A trade permit, $175, 2 inspections).
Verified · Official fee schedule
-
Building permit fees are valuation-based under Table 1A-A Building Permit Fees ("July 2026", applying "to all building permits issued on and after July 12, 2026"): "The Building Permit Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to $2,000 the plan review fee is "$181 for the first $500 plus $8.60 for each additional $100 or fraction thereof" and the permit issuance fee is "$206 for the first $500 plus $4 for each additional $100 or fraction thereof"; for $2,001 to $50,000 they are "$310 for the first $2,000 plus $28.35" and "$266 for the first $2,000 plus $8.56" for each additional $1,000.
Verified · Official fee schedule
Plus 149 more localities with a verified note, each on its own permit page. Browse every pool page
Roof Replacement permit fees
Verified in 155 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states. Renovation work with no measurable area is priced on the declared value of the work.
Verified · Official fee schedule
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
A reroof is a general building permit priced on valuation under Sec. 33.04(a), published as DSI's Building Permit Fee Schedule (Section 33.04 of the Saint Paul Legislative Code, Effective: 2/25/2023). Sample rows from the schedule: valuation 9,001 to 10,000 = $274, 11,001 to 12,000 = $316, 19,001 to 20,000 = $484. Above $100,000 the fee is $1,499 for the first $100,000 plus $8 for each additional $1,000. The Minnesota state surcharge is $0.50 for jobs valued $1.00 to $1,000, otherwise 0.0005 times job value. DSI notes that Contractor Express items, which include re-roof and roof repair, do not require plan review and can be issued online.
Verified · Official fee schedule
-
An exempt reroof costs nothing. A reroof that loses the exemption, most often because sheathing or structure is being replaced, is a building permit priced from the one- and two-family valuation table in Sec. 18-20(b)(2): $52.00 up to $1,000.00 of valuation, $58.00 from $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. Sec. 18-20(e)(2) triples the fee if the work starts before the permit issues, with a carve-out where the work is done at a one-family dwelling by the person who owns and occupies it and the permit is applied for before the end of the workday following notification.
Verified · Official fee schedule
-
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'
Verified · Official fee schedule
-
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; re-roofs have no separate residential fee line, per the 2024 Fee Schedule effective 7/1/2024
Verified · Official fee schedule
-
Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". "Other Building Permit Fees: Minor Renovation Projects (valued less than $75,000) | Residential Renovation Permit | $125" and "Extensive Renovation Projects (valued at $75,000 or greater) | Extensive Renovation Permit | $4 per $1,000 of construction value". The schedule also states "Building permit fees include Plan Review and Building Inspections" and prices reinspections at "First Follow-up Inspection $0", "Second Follow-up Inspection $50", "Third and each Subsequent Follow-up Inspection $100", with "Penalty for Construction Prior to Issuance of Permit 100% of the Permit Fee". A residential re-roof valued under $75,000 therefore falls in the $125 Residential Renovation Permit band. Caution on figures: the department's older undated handout "Regulatory Requirements for Residential Permits" still prices this work at "$0.006 x Value of Construction" and the 2012-era step sheets at "$6 per $1,000 of estimated construction cost (minimum fee is $30)", both of which predate the July 1, 2024 schedule. Confirm the current amount with the Permits Section at 678-518-6020 before budgeting.
Verified · Official fee schedule
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule.
Verified · Official fee schedule
-
At application: building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) plus a 0.025 x building-fee surcharge; no flat fee is listed for roof permits, unlike most other residential permit types.
Verified
-
No re-roof-specific fee line item is published. Roof replacement permits fall under the general Building Services Fees table: Permit Issuance Fee $14.00, plus Total Valuation of Building fee (minimum $19.00, or $11.00 for the first $1,000 plus $2.63 for each additional thousand up to $50,000; higher tiers apply above that), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026).
Verified · Official fee schedule
-
No roofing line item is published. A flat roof reroof or recover pays the $15 base application fee plus the estimated project cost permit fee ($100 for cost up to $1,000; $100 plus $10 per $1,000 from $1,000 to $50,000) plus a plan examination fee of 20% of the building permit fee, under the Building Permit Fees schedule effective October 2019 and revised 7/15/2025. Expedited plan review adds a $15 expedited plan review fee. Properties in a historic district also pay $35 for historic district staff review.
Verified · Official fee schedule
Plus 143 more localities with a verified note, each on its own permit page. Browse every roof replacement page
Shed permit fees
Verified in 159 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states.
Verified · Official fee schedule
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
A shed that needs a permit is a general building permit priced from the one- and two-family valuation table in Sec. 18-20(b)(2) of the Code of Ordinances: $52.00 for total valuation of $0.00 to $1,000.00, $58.00 for $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00, and above $100,000.00 $483.00 for the first $100,000.00 plus $1.41 for each additional $1,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. There is no separate construction document review fee on one- and two-family work: Sec. 18-20(c)(1) charges that only "For other than one- and two-family dwellings." Optional add-ons are a $80.00 fast track permit fee under Sec. 18-20(b)(8) and a $30.00 scheduled express review fee for one- and two-family dwellings under Sec. 18-20(c)(4). Starting work before the permit is issued triples the fee under Sec. 18-20(e)(2).
Verified · Official fee schedule
-
No shed-specific line in Newark municipal code Chapter 7:2-3.1 (Ord. 6 S+FD, 9-5-2007). Where a permit is required, building work is priced as 'Building Renovation and Alteration' at $28 per $1,000 of estimated cost of construction between $0 and $50,000 (then $21 per $1,000 to $100,000, $17 per $1,000 above that), or at $0.03 per cubic foot for a new residential structure, subject to the 'Minimum Building Permit: $58.' The $58 non-refundable processing fee is credited against the total.
Verified · Official fee schedule
-
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'
Verified · Official fee schedule
-
Building Permit Fees are based on the actual cost of work: $75.00 for $0 to $2,000, $110.00 for $2,001 to $4,000, $145.00 for $4,001 to $6,000, rising in steps to $985.00 for $58,001 to $60,000. The fee page carries the notice "Fees for licenses, building, electrical, and plumbing permits, as well as for certificates of occupancy, will change effective July 1, 2026." No separate shed line item is published.
Verified · Official fee schedule
-
Zoning certificate for compliance: $25.00 (Zoning Ordinance: "The fee for a zoning certificate and for a zoning certificate for compliance is $25.00."). Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule.
Verified · Official fee schedule
-
No item-specific fee. Residential work is priced under AMC 23.10.109 Table 3-A item 2, "Residential Construction (new construction, additions, alterations, and repairs)": "Up to $50,000 (Repairs, decks, and minor alterations only)" $350 with 4 inspections, "All others" $0.009 * (Valuation), minimum $450; plus Table 3-B residential plan review ("Regular Plan Review" 0.005 *(Valuation), minimum $75; land use plan review 15% of the Table 3-A fee, minimum $75) and a $50 digital maintenance fee (Table 3-A item 4.B). Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026).
Verified · Official fee schedule
-
Building permit fees are valuation-based under Table 1A-A Building Permit Fees ("July 2026", applying "to all building permits issued on and after July 12, 2026"): "The Building Permit Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to $2,000 the plan review fee is "$181 for the first $500 plus $8.60 for each additional $100 or fraction thereof" and the permit issuance fee is "$206 for the first $500 plus $4 for each additional $100 or fraction thereof"; for $2,001 to $50,000 they are "$310 for the first $2,000 plus $28.35" and "$266 for the first $2,000 plus $8.56" for each additional $1,000.
Verified · Official fee schedule
-
At application: flat fee $90, plus a 0.025 x building-fee surcharge and a $22 zoning flat fee; at issuance: building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a $90 Right-of-Way Review fee.
Verified
-
No shed or accessory-structure-specific fee line item is published. Shed permits fall under the general Building Services Fees table: Permit Issuance Fee $14.00, plus Total Valuation of Building fee (minimum $19.00, or $11.00 for the first $1,000 plus $2.63 for each additional thousand up to $50,000; higher tiers apply above that), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026).
Verified · Official fee schedule
-
Building Permit Fees (effective October 2019, revised 7/15/2025), under the Zoning Compliance permit heading: "Sheds under 200 square feet, includes one inspection ... $75". The same schedule prices zoning compliance permits at $25 for building projects up to $10,000 and $75 for projects over $10,000. A shed larger than 200 sq ft pays the $15 base application fee plus the estimated project cost permit fee ($100 for cost up to $1,000; $100 plus $10 per $1,000 from $1,000 to $50,000) plus a plan examination fee of 20% of the building permit fee.
Verified · Official fee schedule
Plus 147 more localities with a verified note, each on its own permit page. Browse every shed page
Solar permit fees
Verified in 158 localities. Dollar figures appearing in those schedules run from $0.02 to $300,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Appendix A states 'The following permit fees will apply to residential and commercial solar permits' immediately before its Valuation Table: up to $5,000.00 in valuation costs $85.00; $5,000.00 and over costs $150.00 plus $3.25 per thousand dollars (or fraction) over $5,000.00, capped at a $300,000.00 maximum permit fee. Separately, a re-roof combined with solar panel removal/replacement or solar shingles is billed at a flat $150.00 permit fee under the re-roofing fee lines. Effective October 1, 2025, per Resolution #25-036R.
Verified · Official fee schedule
-
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
Verified · Official fee schedule
-
Each trade permit is priced from the one- and two-family valuation table in Sec. 18-20(b)(2), which covers building, mechanical, plumbing and electrical permits alike: $52.00 up to $1,000.00 of valuation, $58.00 from $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00, and $483.00 for the first $100,000.00 plus $1.41 per additional $1,000.00 above that. Information Bulletin IB162 requires the declared valuation to include the entire scope of the project, including the solar panels themselves. The scheduled express review option adds $30.00 for one- and two-family dwellings under Sec. 18-20(c)(4). Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22.
Verified · Official fee schedule
-
Solar has no dedicated line item. The permit is charged off total construction permit value under the LUESA Fee Ordinance (revised July 1, 2026), where $3,001 to $50,000 is '$59.70 plus $12.19 per $1,000 or part over $3,000' and $50,001 to $100,000 is '$632.57 plus $5.49 per $1,000 or part over $50,000', plus a $3.00 technology charge on all permits. A ground-mounted or pole-mounted array that needs the City of Charlotte LDIRL pays $70 Residential Zoning under the FY 2025 Individual Residential Lot Fee Schedule, effective for projects submitted July 1, 2024 to June 30, 2025, plus any Urban Forestry tree preservation tier of $75, $225 or $375.
Verified · Official fee schedule
-
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.' The Electrical Permit Fee Schedule, Document #4100 dated 7/16/24, has no solar line item; it prices the work through 'Minimum Permit Fee 85.00', 'Panel 10.00 ea.' and the amp-rated service lines ('200 Amp. Service 99.00 ea.').
Verified · Official fee schedule
-
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; the solar application requires a cost estimate and no separate solar fee line exists, per the 2024 Fee Schedule effective 7/1/2024
Verified · Official fee schedule
-
Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". The schedule grants a discount rather than setting a separate solar price: "Green Building Credit [...] There will be a 5% Building Permit Fee reduction for the installation of the following: - Solar panel installations for nonresidential and residential buildings - EV charger unit installations for nonresidential and residential developments". The underlying permit is priced from the Other Building Permit Fees table, where "Minor Renovation Projects (valued less than $75,000) | Residential Renovation Permit | $125".
Verified · Official fee schedule
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule. The checklist adds: "If the project has a construction cost exceeding $50,000.00, DIS requests 1/3 of the permit fee at the time of application, with balance due at time of issuance."
Verified · Official fee schedule
-
At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge.
Verified
-
For expedited residential solar the Solar Photovoltaic (PV) System Permitting Checklist shows the electric permit basic application fee WAIVED, residential solar panels $0.00, and inspection $35.00 if applicable, with no building permit. Electrical Permit Fees (effective January 2020) confirm the residential line "Solar Panels per set of 3 panels ... $0". Non expedited residential and commercial solar also pays a building permit under the Building Permit Fees schedule (revised 7/15/2025) flat solar scale: estimated cost $0 to $10,000 is a $37.50 plan examination fee plus a $150 permit fee; $10,001 to $50,000 is $75 plus $200; over $50,000 is $100 plus $400. The building plan examination fee of 20% expressly excludes solar permits.
Verified · Official fee schedule
-
Two permits, two fees. The guideline charges the array as a "Residential - Alterations & Repairs permit fee per Building and Trade Permit Fee Schedule," which is a $40.00 non-refundable application fee plus "$15.00 for the first $1,000 construction valuation, plus $5.00 for each additional thousand or fraction thereof, to and including $50,000." The electrical sub-permit carries its own $40.00 application fee plus the Electrical Permit Fee Table rate of "$0.25 per ampere (amp)" for new, replacement or upgrade service. Schedule approved by Ordinance Nos. 2017-131, 2019-064 and 2019-072, effective October 1, 2019.
Verified · Official fee schedule
Plus 146 more localities with a verified note, each on its own permit page. Browse every solar page
Water Heater permit fees
Verified in 46 localities. Dollar figures appearing in those schedules run from $0.01 to $50,001, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Verified · Official fee schedule
-
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
Verified · Official fee schedule
-
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
Verified · Official fee schedule
-
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Verified · Official fee schedule
-
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
Verified · Official fee schedule
-
Plumbing permit, Table 104.5 (Code of Ordinances 150.302): $40 for "$0.01 to $5,000.00" of plumbing valuation; "Homeowner s permit." $25.
Verified · Official fee schedule
-
Electric, gas and oil water heaters need a mechanical permit for new or replacement installs, billed at $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy, per the county mechanical permit and fee pages
Verified · Official fee schedule
-
Residential (up to 3 units) building, plumbing, mechanical and electrical permits: 0.50% of estimated construction cost; "Residential less than estimated $2,500.00": $45.00; "Minimum Permit Fee": $110.00; "All Permits non-refundable application fee": $40.00; "Dry run/Up-Front per $1,000.00 of estimated construction value": $2.80 (no up-front fee on residential work under $2,500); "Solid Waste Residential Surcharge" $0.22 per $100.00 of estimated cost (minimum $26.00, maximum $600.00). State and Miami-Dade County surcharges are extra. Exhibit C Fee Schedule, Building, Chapters 10, 17, 20, adopted by Resolution R-26-0200 (Ordinance 14456), April 23, 2026.
Verified · Official fee schedule
-
Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "PLUMBING PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2). The Plumbing Permit Application fee worksheet lists "Hot Water Heater - Electrical" and "Hot Water Heater - Gas"; the Gas Permit Application lists "Water Heater (Gas or Electric)". Gas permit: $9.50 per $1,000.00 valuation, minimum $125.00.
Verified · Official fee schedule
-
Mechanical or Plumbing Permit (Chapter 6 Schedule of Permit and Review Fees, as amended through January 1, 2026): $5.25 for the first $1,000 valuation or any part thereof, $5.25 for each additional $1,000 or part thereof, minimum fee $65.00.
Verified · Official fee schedule
-
Table 1A-C Plumbing/Mechanical Issuance and Inspection Fees (July 2026) has no water-heater line; the residential single-unit plumbing category is "CATEGORY 1P" at $290 and "CATEGORY 11P/M" "Miscellaneous" is $320. Which applies is not stated.
Verified · Official fee schedule
-
The FY27 Development Fee Guide (applications submitted July 1, 2026 through June 30, 2027) enumerates water heater fees only for commercial work ("New or replacement HVAC/Water Heater/other appliance - Commercial", $224.00). FY27 Development Fee Guide (applications submitted July 1, 2026 through June 30, 2027), Building and Safety: "Minimum Trade Permit Fee" of $124.00 per trade ("Any fee not specifically listed as an individual fee will be charged at the minimum permit fee."); the guide's appendix adds the 4% technology surcharge for a total of $129.00. State law (G.S. 160D-1110(d)(1)) bars a local government from requiring more than one building permit for the complete replacement of a gas or electrical appliance by a licensed plumber or electrician, priced at no more than one trade permit.
Verified · Official fee schedule
Plus 34 more localities with a verified note, each on its own permit page. Browse every water heater page
Methodology
Every fee note above was written while reading the locality's current official fee schedule and was reviewed against a quoted line of that schedule before it entered the dataset, with the date recorded. Notes repeat the schedule's own billing basis (flat fee, valuation tier, plan review percentage) rather than reducing everything to one number.
Honest gaps stay gaps: a few localities publish no usable schedule (some block archives, some publish none for certain trades), and some permits are issued by a state agency instead of the locality. Those rows say exactly that.
The measured medians come from official open-data portals and are computed from real issued permits. Sample sizes are shown; medians are used throughout. Read more about the process on how we verify.