What does a building permit cost?
By Mario Bailey Last checked 2026-07-19
We read the official fee schedule of every locality we cover and recorded what it says for 610 permit scenarios across 61 US localities. Each entry below quotes the schedule's own terms, with the verification date. Where a locality publishes no figure, or hands the permit to a state agency, we say that instead of guessing. Many localities bill by project valuation, so a single flat number often does not exist; the notes keep that honesty.
Median fees measured from real permit records
For jurisdictions whose open-data portals publish issued permits, we compute the median fee from the records themselves. These are actual amounts charged, not schedule text.
| Jurisdiction | Median fee | Records |
|---|---|---|
| Chicago, Illinois | $1,142 | 5,329 |
| Mesa, Arizona | $520 | 5,364 |
| Boston, Massachusetts | $90 | 19,468 |
Medians, not averages, so a few large projects cannot skew the figure. Full context in the turnaround study.
Bathroom Remodel permit fees
Verified in 15 localities. Dollar figures appearing in those schedules run from $0.10 to $5,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Falls under the existing-dwelling building permit formula of $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy, capped at $680 plus levy ($693.60 total), with plumbing or electrical trade permits added for new fixtures, per the county fee page
Verified 2026-07-12 · Official fee schedule
-
Non-structural bathroom work uses the Short-Form building permit at $20 primary plus $10 per $1,000 of estimated cost; moving walls needs Long-Form at $50 primary plus $10 per $1,000, with plumbing and electrical trade permits on top, per the ISD fee schedule effective 5/15/2023
Verified 2026-07-12 · Official fee schedule
-
Building subcode charges $15 per $1,000 of estimated renovation cost with a $50 minimum short-permit fee or $100 minimum plan-review fee, plus $10 per plumbing fixture added or replaced, per city ordinance Ch. 160-1
Verified 2026-07-12
-
Filed as a residential Alteration Building Permit at $0.78 per sq ft of altered area with a filing fee of 50% of the permit fee or $329.59 whichever is greater, per DPS-Fees-ResConst-FY27.pdf effective 2026-07-01; plumbing fixture work needs a separate WSSC plumbing permit outside county DPS
Verified 2026-07-12 · Official fee schedule
-
Nonstructural interior remodel up to 500 sq ft with no occupancy or load-bearing change is a flat $250 stand-alone fee per Table 14A-12-1204.2; larger remodels take higher brackets or the calculated permit formula
Verified 2026-07-12 · Official fee schedule
-
Interior renovation building fee runs $0.34 per square foot with a $180 minimum, plus a 2% surcharge and $65 processing fee ($248.60 total on a typical under-500 sq ft remodel), per the county interior renovation packet under the 7/1/2025 Unified Fee Schedule
Verified 2026-07-12 · Official fee schedule
-
Falls under renovation, alteration or conversion: $114 if square footage does not change, $171 with a change of use or added square footage, plus separate electrical or plumbing permits for rough-in work and the 2% state levy, per the residential fee schedule effective 7/1/2025
Verified 2026-07-12 · Official fee schedule
-
Bills as the residential Alteration category at $0.25 per square foot with a $150 minimum, plus separate Trades permits at $0.15 per square foot ($100 minimum) for plumbing or electrical work, plus Virginia's 2% state surcharge, per the FY27 Tax and Fee Schedule
Verified 2026-07-12 · Official fee schedule
-
No single line item; as an interior alteration it falls to the schedule's $141.75 base fee minimum, plus plumbing (base fee for 1 to 7 fixtures, rising by level) and electrical (base fee for 1 to 100 fixtures or circuits) trade fees when fixtures or wiring change, per Appendix Q effective 2026-07-01
Verified 2026-07-12 · Official fee schedule
-
Billed as a residential alteration: building permit fee is 1% of construction cost plus a $130 plan review fee, with separate electrical or plumbing trade permits if fixtures are relocated, per the county's Residential Additions and Alterations page
Verified 2026-07-12 · Official fee schedule
-
Prince William County, Virginia
No dedicated line item; billed as Residential Repairs and Alterations building permit $88.44 base ($110.65 with surcharges) plus a Plumbing Additions/Remodeling permit $88.44 base ($110.65) plus $7.36 per fixture ($9.20), and an Electrical Existing Dwellings permit $44.23 base ($55.35) with per-item charges, only for the trades actually altered, per the FY27 BDD Fee Schedule
Verified 2026-07-12 · Official fee schedule
-
Interior alterations to a single family home need a $25 filing fee plus $50 for an area of 200 sq ft or less or $100 over 200 sq ft, plus a 10% technology fee on all permits, per the FY27 Building Permit Fee Schedule effective 7/1/2026
Verified 2026-07-12 · Official fee schedule
Plus 3 more localities with a verified note, each on its own permit page. Browse every bathroom remodel page
Deck permit fees
Verified in 58 localities. Dollar figures appearing in those schedules run from $0.07 to $50,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Deck permits follow the county's general building permit valuation table: no fee for construction valued at $1,000 or less unless an inspection is required ($15.00 per inspection); $15.00 for the first $1,000 plus $5.00 for each additional thousand or fraction thereof, up to $50,000 (Schedule of Building Permit Fees).
Verified 2026-07-06 · Official fee schedule
-
Building permit fee by valuation per Construction Fees Resolution 17-025; residential fee starts at $85.00 for work valued up to $12,000; fees due at permit issuance.
Verified 2026-07-19 · Official fee schedule
-
No separate deck line; billed as miscellaneous residential construction under the Residential Rate Table, $220 minimum for the $0 to $8,333 valuation bracket, plus a 4% technology improvement fee capped at $800, per the Development Services Schedule of Fees (Ord. 5524, Dec 2025)
Verified 2026-06-17 · Official fee schedule
-
Existing-dwelling addition or alteration permit fee applies: $100 for the first $5,000 of labor and materials cost, plus $6 per additional $1,000 or fraction thereof, plus a 2% state levy; total capped at $693.60, per Henrico's residential building permit fee schedule.
Verified 2026-07-06 · Official fee schedule
-
Mecklenburg County, North Carolina
Trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026
Verified 2026-06-18 · Official fee schedule
-
Per IB-501 Table 501C effective May 2026: Deck with pre-approved plans $1,148.29 plan check plus $264.25 inspection per building, custom plans up to 500 sq ft $1,677.99 plan check plus $264.25 inspection, over 500 sq ft $2,649.60 plan check plus $440.82 inspection
Verified 2026-06-17 · Official fee schedule
-
Building permit fee is graduated by declared project valuation per LAMC 91.113 Table 1-A, posted base $65 for total valuation $100.01 to $2,000, rising by bracket above that; no deck-specific valuation multiplier is printed in the LADBS Valuation Table
Verified 2026-06-17 · Official fee schedule
-
Building permit fee follows PCC Table 17C.10-1-B (valuation based): $69.00 for construction valued at $500 or less, plus $2.00 for each additional $100 or fraction up to $2,000, plus a plan review fee equal to 65 percent of the building permit fee (PCC Table 17C.10-1-C).
Verified 2026-07-06 · Official fee schedule
-
Deck permits have no dedicated fee line, they are valuation-based building permits under Table A, minimum $195 base fee for valuation up to $1,000 then a rising per-$1,000 rate per the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
Billed as a building permit on the county valuation fee table starting at a $55 minimum for the first $1,000 of value plus a 65% plan review fee, per the 2024 Building Code Supplements fee schedule effective 7/1/2026
Verified 2026-07-06 · Official fee schedule
-
A $12 flat Zoning Permit covers a detached deck 120 sq ft or smaller; a larger deck bills under the Accessory Structure schedule at a $26 minimum for the first $1,000 of value plus $4 per additional $1,000, with non-covered wood decks valued at $5 per sq ft, per the FY2025-26 Fee Directory
Verified 2026-06-18 · Official fee schedule
-
No dedicated deck line; billed as an accessory structure under Combination Permit schedule IV-A at $11 per $1,000 of valuation with a $100 minimum per inspection, per the BDRS fee schedule in the FY26 budget
Verified 2026-07-06 · Official fee schedule
Plus 46 more localities with a verified note, each on its own permit page. Browse every deck page
Electrical permit fees
Verified in 59 localities. Dollar figures appearing in those schedules run from $0.11 to $8,333, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
A stand-alone electrical permit is valuation based on the same Residential Rate Table, $220 minimum for the $0 to $8,333 bracket, plus a 4% technology improvement fee capped at $800, per the Development Services Schedule of Fees (Ord. 5524, Dec 2025)
Verified 2026-06-17 · Official fee schedule
-
Existing-dwelling trade permit fee applies: $100 for the first $5,000 of labor and materials cost, plus $6 per additional $1,000 or fraction thereof, plus a 2% state levy; a new-dwelling trade permit is a $100 flat fee plus $2 state levy ($102 total), per Henrico's residential trade permit fee schedule.
Verified 2026-07-06 · Official fee schedule
-
Mecklenburg County, North Carolina
Electrical trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026
Verified 2026-06-18 · Official fee schedule
-
Electrical permits have no dedicated fee line, they are valuation-based building permits under Table A, minimum $195 base fee for valuation up to $1,000 then a rising per-$1,000 rate per the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
Electrical permits not tied to an active building permit bill on the countywide valuation fee table with a $55 minimum for the first $1,000 of value, per the 2024 Building Code Supplements fee schedule effective 7/1/2026
Verified 2026-07-06 · Official fee schedule
-
Base fee $45; $10 per system component or feature; low voltage $2 per termination point; alternate method $40 for the first $1,000 of valuation plus $2 per additional $1,000 per posted fee Resolution 18-17
Verified 2026-07-19 · Official fee schedule
-
$100 filing fee (nonrefundable); permit fee $25 per $1,000 of construction cost, minimum $63
Verified 2026-06-18 · Official fee schedule
-
Fee schedule sets a flat $100 fee only for electrical service upgrades of 400 amps or less per 4.6.4(b), other electrical work is billed as a standard building permit by valuation with a $50 minimum for valuation up to $500
Verified 2026-07-06 · Official fee schedule
-
Valuation-based fee per CPD Table 1 with a $20 minimum for work valued at $500 or less; service work at 400 amps or less issues as a no-plan-review quick permit, per the Development Fees schedule and Quick Permits page
Verified 2026-06-17 · Official fee schedule
-
Electrical permit fee by valuation per Table 6 of Ordinance 6879, $79 inspection fee minimum for valuation up to $500 plus a plan review fee of 10% of the inspection fee with a $35 minimum, effective 2026-01-01
Verified 2026-06-18 · Official fee schedule
-
Greater of $315 per hour of required inspection time or an itemized fixture-based schedule, charged in addition to the base Permit Issuance Fee, per the FY2025-26 Building Division Fee Schedule
Verified 2026-06-17 · Official fee schedule
-
Itemized per Fee Subtitle Table D-15: minimum $105.12 for a standard online self-issued permit plus a $55.48 administrative fee per permit, new or altered service up to 125 amps $146, 150 to 200 amps $292, branch circuit or feeder up to 200 amps $146, all plus a 5% technology fee, per the 2026 Fee Subtitle
Verified 2026-06-18 · Official fee schedule
Plus 47 more localities with a verified note, each on its own permit page. Browse every electrical page
EV Charger permit fees
Verified in 13 localities. Dollar figures appearing in those schedules run from $0.15 to $18,975, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Charged as a standard electrical permit at $25 per $1,000 of estimated cost with a $63 minimum and $18,975 maximum; no EV-specific fee line exists, per the city's electrical permit page
Verified 2026-07-12 · Official fee schedule
-
No EV-specific fee; charger circuits operate above 50 volts so they take the standard existing-dwelling electrical permit at $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy, per the county electrical permit and fee pages
Verified 2026-07-12 · Official fee schedule
-
Billed as an electrical fixture under Residential Addition/Alteration Electrical Installation Fees at the $141.75 base fee for Level One (1 to 100 fixtures, circuits or equipment), per Appendix Q effective 2026-07-01
Verified 2026-07-12 · Official fee schedule
-
No EV-specific line; a charger circuit falls under the county's electrical permit trigger for new wiring, $114 where rough-in is required or $57 for an installation using existing wiring, plus the 2% state levy, per the residential fee schedule effective 7/1/2025
Verified 2026-07-12 · Official fee schedule
-
$62.19 for an Electrical Charging Station under Other Electrical Equipment, charged in addition to the $111.94 residential electrical permit minimum fee, per DPS-Fees-Electrical-Mechanical-FY27.pdf effective 2026-07-01
Verified 2026-07-12 · Official fee schedule
-
No EV-specific line; a home charger circuit bills under the residential Trades electric category at $0.15 per square foot with a $100 minimum, plus Virginia's 2% state surcharge, per the FY27 Tax and Fee Schedule
Verified 2026-07-12 · Official fee schedule
-
No EV-specific line; a charger circuit bills as a single electrical trade permit at $84.15 including the technology fee, per the county fee schedule effective 7/1/2025
Verified 2026-07-12 · Official fee schedule
-
No EV-specific fee line; a home charger circuit files under the standard residential Electrical Permit at $70 for fixtures, receptacles and circuits, with a service upgrade a separate $70 (0-400 amps), per the July 2022 fee schedule
Verified 2026-07-12 · Official fee schedule
-
Not separately itemized; an EV charger circuit falls under the residential All Trades electrical rate of $60 per trade per system, plus the 2 percent state levy and 2.75 percent technology fee, per the Development Services Fee Schedule effective 11/1/2024
Verified 2026-07-12 · Official fee schedule
-
Prince William County, Virginia
No permit or fee if the charger is cord-and-plug connected to an existing circuit per manufacturer instructions; hardwired installs are billed as stationary equipment on the Existing Dwellings electrical schedule, base fee $44.23 ($55.35 with surcharges) plus $11.80 per unit ($14.75 with surcharges), per the FY27 BDD Fee Schedule
Verified 2026-07-12 · Official fee schedule
-
Not itemized by name; an EV charger circuit falls under the $50 electrical permit application fee plus the $50 flat fee for residential alterations or a service heavy-up, plus a 10% technology fee, per the FY27 Electrical Permit Fee Schedule effective 7/1/2026
Verified 2026-07-12 · Official fee schedule
-
An Electrical Permit is required per Boston's EVSE installation guide, billed under the electrical fee schedule at $20 application fee plus cost-based charges, per the ISD fee schedule effective 5/15/2023
Verified 2026-07-12 · Official fee schedule
Plus 1 more localities with a verified note, each on its own permit page. Browse every ev charger page
Fence permit fees
Verified in 53 localities. Dollar figures appearing in those schedules run from $0.25 to $75,001, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; no fence-specific line item, per the 2024 Fee Schedule effective 7/1/2024
Verified 2026-07-06 · Official fee schedule
-
No fence-specific line; a fence needing a building permit bills under the Section B101 valuation table, no fee for work valued $1,000 or less unless an inspection is required ($15 per inspection), then $15 for the first $1,000 plus $5 per additional thousand up to $50,000, per the county Schedule of Building Permit Fees
Verified 2026-07-06 · Official fee schedule
-
Fences up to 7 feet that are not a pool barrier need no permit; pool-barrier fences and masonry walls over 6 feet take the building permit formula of $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy, capped at $693.60 with levy, per the county permit and fee pages
Verified 2026-07-06 · Official fee schedule
-
Fence or wall over 7 feet high is billed per 100 linear feet under IB-501 Table 501C effective May 2026: custom plans $2,031.00 plan check base plus $529.71 inspection base, a pre-approved City Standard plan runs $1,148.29 plan check and $353.13 inspection per 100 LF
Verified 2026-06-17 · Official fee schedule
-
Valuation-based building permit per LAMC 91.113 Table 1-A; the LADBS Valuation Table sets minimum declared valuation at $14 per sq ft of wall for concrete fences and $10 per sq ft for masonry, feeding the graduated brackets (posted base $65 for valuation up to $2,000)
Verified 2026-06-18 · Official fee schedule
-
Building permit fee follows PCC Table 17C.10-1-B (valuation based): $69.00 for construction valued at $500 or less, plus $2.00 for each additional $100 or fraction up to $2,000, plus a plan review fee equal to 65 percent of the building permit fee (PCC Table 17C.10-1-C).
Verified 2026-07-06 · Official fee schedule
-
Residential fences carry a $98 minimum permit fee for project valuations of $1 to $1,000, covering up to two inspections, per Table A of the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
Zoning permit $50-$632 by lot size; building permit $69 (residential) per fence; city surcharge $3 and state surcharge $4.50 per building permit
Verified 2026-06-18 · Official fee schedule
-
Zoning construction permit fee with a $10 minimum for fences valued at $500 or less; fences over 4 ft need the zoning permit and fences over 8 ft also need a Table 1 building permit, per the Development Fees schedule and Fences and Walls page
Verified 2026-06-18 · Official fee schedule
-
Only fences over 7 feet or masonry walls over 4 feet need a building permit, priced from $55 for the first $500 of valuation plus $32 per $100 over $500, per the PDS Fee Schedule effective 1/1/2025
Verified 2026-06-18 · Official fee schedule
-
Flat $300 fee with 2 inspections, applying only to fences over 6 feet since shorter fences need no building permit, per the 2026 fee schedule effective 1/22/2026
Verified 2026-06-18 · Official fee schedule
-
$294 for the first 100 linear feet of a non-masonry fence or freestanding wall of any height plus $18 per additional 100 linear feet, masonry priced separately, per the DSC Schedule of Fees effective 10/01/2025
Verified 2026-07-06 · Official fee schedule
Plus 41 more localities with a verified note, each on its own permit page. Browse every fence page
HVAC permit fees
Verified in 59 localities. Dollar figures appearing in those schedules run from $0.03 to $8,333, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Stand-alone mechanical work is valuation based via the Residential Rate Table, $220 minimum for the $0 to $8,333 bracket plus a 4% technology fee capped at $800; a straight AC replacement with the same or less electrical load needs no permit per the Residential Construction Homeowners Guide
Verified 2026-06-17 · Official fee schedule
-
Existing-dwelling trade permit fee applies: $100 for the first $5,000 of labor and materials cost, plus $6 per additional $1,000 or fraction thereof, plus a 2% state levy; a new-dwelling trade permit is a $100 flat fee plus $2 state levy ($102 total), per Henrico's residential trade permit fee schedule.
Verified 2026-07-06 · Official fee schedule
-
Mecklenburg County, North Carolina
Mechanical trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026
Verified 2026-06-18 · Official fee schedule
-
HVAC (mechanical) permits have no dedicated fee line, they are valuation-based building permits under Table A, minimum $195 base fee for valuation up to $1,000 then a rising per-$1,000 rate per the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
Mechanical permits not tied to an active building permit bill on the countywide valuation fee table with a $55 minimum for the first $1,000 of value, per the 2024 Building Code Supplements fee schedule effective 7/1/2026
Verified 2026-07-06 · Official fee schedule
-
Base fee $45; $10 per residential system component or feature; $0.04 per square foot of conditioned or ventilated area for new construction or renovation; alternate method $40 for the first $1,000 of valuation plus $2 per additional $1,000 per posted fee Resolution 18-17
Verified 2026-07-19 · Official fee schedule
-
Mechanical Permit Fee Schedule: $10.00 permit fee plus $10.00 for the first $1,000 of valuation and $2.00 for each additional $1,000; repair, replacement, or addition permits are $5.00 plus $2.00 for each additional $1,000 of valuation (Schedule of Building Permit Fees).
Verified 2026-07-06 · Official fee schedule
-
Direct replacement of HVAC equipment is a household appliance permit, $78.75 for one appliance; new HVAC installation is a mechanical permit priced by zone count from the $141.75 base fee for one zone to $693.00 for 5 or more zones, per Appendix Q effective 2026-07-01
Verified 2026-06-18 · Official fee schedule
-
No HVAC or mechanical-specific fee line, mechanical permits are billed as a standard building permit by valuation with a $50 minimum for valuation up to $500 plus 65% plan review fee per Fee Schedule 4.6.1-4.6.2
Verified 2026-07-06 · Official fee schedule
-
$360 to install or relocate a furnace up to 100,000 BTU/hr including ducts, $227 per additional 100,000 BTU/hr, other mechanical work billed by item, per the DSC Schedule of Fees effective 10/01/2025
Verified 2026-07-06 · Official fee schedule
-
Billed as a Mechanical Permit: greater of $315 per hour of actual inspection time or an itemized schedule, charged in addition to the base Permit Issuance Fee, per the FY2025-26 Building Division Fee Schedule
Verified 2026-06-17 · Official fee schedule
-
Ducted HVAC systems are priced by project valuation with a $292 minimum; equipment installed without plans is a flat per-unit fee under Table D-8, for example $60.35 per unit for a furnace, heat pump, or wall heater and $75.50 per unit for a new gas or oil burner, plus a 5% technology fee, per the 2026 Fee Subtitle
Verified 2026-06-18 · Official fee schedule
Plus 47 more localities with a verified note, each on its own permit page. Browse every hvac page
Patio permit fees
Verified in 47 localities. Dollar figures appearing in those schedules run from $0.54 to $75,001, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; no patio-specific line item, per the 2024 Fee Schedule effective 7/1/2024
Verified 2026-07-06 · Official fee schedule
-
No patio-specific line; billed under the Section B101 valuation table, $15 for the first $1,000 plus $5 per additional thousand up to $50,000, plus a plan-check fee of half the permit fee above $1,000, per the county Schedule of Building Permit Fees
Verified 2026-07-06 · Official fee schedule
-
Building permit fee by valuation per Construction Fees Resolution 17-025; residential fee starts at $85.00 for work valued up to $12,000; fees due at permit issuance.
Verified 2026-07-19 · Official fee schedule
-
Patio covers and enclosures are valuation based via the Residential Rate Table, $220 minimum for the $0 to $8,333 bracket plus a 4% technology fee capped at $800; light-gauge pre-manufactured metal patio covers are permit-exempt per the Residential Construction Homeowners Guide
Verified 2026-06-17 · Official fee schedule
-
Mecklenburg County, North Carolina
Trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026; a patio built level with grade needs only a zoning permit, not this building fee
Verified 2026-06-18 · Official fee schedule
-
Per IB-501 Table 501C effective May 2026: Patio Cover with pre-approved plans $1,501.42 plan check plus $353.13 inspection each, custom plans $1,412.54 plan check plus $529.71 inspection each
Verified 2026-06-17 · Official fee schedule
-
Patio permits have no dedicated fee line, they are valuation-based building permits under Table A, minimum $195 base fee for valuation up to $1,000 then a rising per-$1,000 rate per the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
A concrete patio slab is valued at $5 per sq ft then charged under the Accessory Structure schedule at a $26 minimum plus $4 per additional $1,000 of value; a patio 120 sq ft or smaller can use the $12 flat Zoning Permit, per the FY2025-26 Fee Directory
Verified 2026-06-18 · Official fee schedule
-
Open flatwork patios are permit-exempt; a covered or screened aluminum patio structure is $250 without slab or footers or $350 with, plus $1 per $1,000 of value, per Building Stand Alone Permits V-B/V-C of the FY26 BDRS schedule
Verified 2026-07-06 · Official fee schedule
-
No dedicated patio line; the building subcode alteration fee of $15 per $1,000 of estimated cost applies with a $50 minimum short-permit fee, per city ordinance Ch. 160-1
Verified 2026-07-06
-
Uses the same residential building permit rate as decks, $5 per $1,000 of valuation plus a $25 zoning examination fee and a 10% codes tech fee, per the Metro Codes fee schedule (Dec 2025)
Verified 2026-06-18 · Official fee schedule
-
No separate patio line; the deck and accessory building category (which the county states includes porches or decks of any size) applies, $772 minimum application review plus $2.46 per sq ft inspection plus the $6.50 state building code surcharge, per the 2026 single family residential fee guide
Verified 2026-07-06 · Official fee schedule
Plus 35 more localities with a verified note, each on its own permit page. Browse every patio page
Plumbing permit fees
Verified in 59 localities. Dollar figures appearing in those schedules run from $0.03 to $8,333, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
A stand-alone plumbing permit is valuation based via the Residential Rate Table, $220 minimum for the $0 to $8,333 bracket plus a 4% technology fee capped at $800, per the Development Services Schedule of Fees (Ord. 5524, Dec 2025)
Verified 2026-06-17 · Official fee schedule
-
Existing-dwelling trade permit fee applies: $100 for the first $5,000 of labor and materials cost, plus $6 per additional $1,000 or fraction thereof, plus a 2% state levy; a new-dwelling trade permit is a $100 flat fee plus $2 state levy ($102 total), per Henrico's residential trade permit fee schedule.
Verified 2026-07-06 · Official fee schedule
-
Mecklenburg County, North Carolina
Plumbing trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026
Verified 2026-06-18 · Official fee schedule
-
Plumbing permits have no dedicated fee line (water heaters get the $98 minimum tier), general plumbing work is a valuation-based building permit under Table A, minimum $195 base fee for valuation up to $1,000 per the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
Plumbing permits not tied to an active building permit bill on the countywide valuation fee table with a $55 minimum for the first $1,000 of value, per the 2024 Building Code Supplements fee schedule effective 7/1/2026
Verified 2026-07-06 · Official fee schedule
-
Base fee $45; $10 per system component or feature; alternate method $40 for the first $1,000 of valuation plus $2 per additional $1,000 per posted fee Resolution 18-17
Verified 2026-07-19 · Official fee schedule
-
Residential addition or alteration plumbing work starts at the $141.75 base fee for Level One (1 to 7 fixtures), rising by level to $350.70 for over 22 fixtures, per Appendix Q effective 2026-07-01
Verified 2026-06-18 · Official fee schedule
-
Greater of $315 per hour of actual inspection time or an itemized fixture-based schedule, charged in addition to the base Permit Issuance Fee, per the FY2025-26 Building Division Fee Schedule
Verified 2026-06-17 · Official fee schedule
-
Plumbing falls under the combined trade line, $275 standard with 2 inspections or $140 on the Approved Minor Work Permit List, per the 2026 fee schedule effective 1/22/2026
Verified 2026-06-18 · Official fee schedule
-
Billed per fixture under IB-103 Table 3B effective May 2026: water heater $122.97, backflow preventer $87.68 first plus $52.39 each additional, gas system or meter $264.25 per 5 outlets
Verified 2026-06-17 · Official fee schedule
-
$228 for a new single-family dwelling; $114 for an addition or renovation requiring new rough-in ($57 if rough-in is pre-existing); $57 for backflow prevention or water/sewer line installation or repair, per the FY2025-26 residential fee schedule
Verified 2026-07-06 · Official fee schedule
-
Single family plumbing for new construction, additions or alterations is $0.140 per square foot of the master permit floor area subject to a $227.90 minimum plumbing permit fee, per the county plumbing and gas fee sheet (rev 9/25)
Verified 2026-06-18 · Official fee schedule
Plus 47 more localities with a verified note, each on its own permit page. Browse every plumbing page
Pool permit fees
Verified in 59 localities. Dollar figures appearing in those schedules run from $0.61 to $100,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
No pool-specific line; billed under the Section B101 valuation table, for example $260 for the first $50,000 of value plus $4 per additional thousand up to $100,000, plus a plan-check fee of half the permit fee, per the county Schedule of Building Permit Fees
Verified 2026-07-06 · Official fee schedule
-
$550 base covers building, electric and plan review for a pool, spa or hot tub with deck up to $40,000 in value, plus $5.50 per $1,000 above that, per Combination Permits IV-J of the FY26 BDRS schedule
Verified 2026-07-06 · Official fee schedule
-
Existing-dwelling addition or alteration permit fee applies to swimming pools requiring a permit: $100 for the first $5,000 of labor and materials cost, plus $6 per additional $1,000 or fraction thereof, plus a 2% state levy; total capped at $693.60, per Henrico's residential building permit fee schedule.
Verified 2026-07-06 · Official fee schedule
-
Mecklenburg County, North Carolina
Trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026, with separate electrical or plumbing trade permits billed the same way when power or drainage is added
Verified 2026-06-18 · Official fee schedule
-
Per IB-501 Table 501C effective May 2026: Pool/Spa per master plan for a single dwelling $971.73 plan check plus $529.71 inspection, private custom pool $2,649.60 plan check plus $529.71 inspection each
Verified 2026-06-17 · Official fee schedule
-
An unenclosed pool accessory to a single-family or duplex home is a flat fee of four times the $292 SDCI base fee, $1,168, plus a 5% technology fee, per Fee Subtitle Table D-2 item 17a; a pool inside an enclosed building on the building plans carries no separate fee
Verified 2026-06-18 · Official fee schedule
-
The pool shell bills under the Accessory Structure schedule using the Fee Directory's $41 per sq ft pool valuation ($26 minimum plus $4 per additional $1,000), plus flat fees of $64 for the plumbing Swimming Pool Permit and $59 for Pool Wiring, per the FY2025-26 Fee Directory
Verified 2026-06-18 · Official fee schedule
-
Billed as a residential building permit at $5 per $1,000 of valuation plus a $25 zoning fee and 10% codes tech fee, with a separate plumbing permit ($75 minimum plus $11 per fixture) since pools are listed as a plumbing fixture classification, per the Metro Codes fee schedule (Dec 2025)
Verified 2026-06-18 · Official fee schedule
-
Flat all-inclusive fee of $330 for a residential in-ground swimming pool or spa, plus a 4% technology improvement fee capped at $800, per the Development Services Schedule of Fees (Ord. 5524, Dec 2025)
Verified 2026-06-17 · Official fee schedule
-
$712 for a residential pool/spa combination plus $772 standard pool plan check; a prefabricated pool, spa, or hot tub is $294, per the DSC Schedule of Fees effective 10/01/2025
Verified 2026-07-06 · Official fee schedule
-
Base permit issuance $227 plus base plan review $325 plus base inspection $367, rising to $682 total inspection when a plumbing or electrical permit for pool equipment is also required, per the FY2025-26 Building Division Fee Schedule
Verified 2026-06-17 · Official fee schedule
-
Installation of a residential swimming pool or spa carries a flat $640 building permit fee with separate electrical and plumbing sub-permits required, per Implementing Order 4-63 effective 6/30/2025
Verified 2026-06-18 · Official fee schedule
Plus 47 more localities with a verified note, each on its own permit page. Browse every pool page
Roof Replacement permit fees
Verified in 57 localities. Dollar figures appearing in those schedules run from $0.04 to $75,001, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; re-roofs have no separate residential fee line, per the 2024 Fee Schedule effective 7/1/2024
Verified 2026-07-06 · Official fee schedule
-
Residential re-roof is listed in Construction Fees Resolution 17-025; building permit fee by valuation, residential fee starts at $85.00 for work valued up to $12,000; fees due at permit issuance.
Verified 2026-07-19 · Official fee schedule
-
Roof covering replacement is exempt in unlimited amounts so typical reroofing needs no permit; replacing more than 256 sq ft of roof sheathing triggers the building permit formula of $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy, per the county permit and fee pages
Verified 2026-07-06 · Official fee schedule
-
Mecklenburg County, North Carolina
Trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026; many like-for-like reroofs fall under the county no-permit threshold and incur no fee
Verified 2026-07-06 · Official fee schedule
-
Building permit fee follows PCC Table 17C.10-1-B (valuation based): $69.00 for construction valued at $500 or less, plus $2.00 for each additional $100 or fraction up to $2,000, plus a plan review fee equal to 65 percent of the building permit fee (PCC Table 17C.10-1-C).
Verified 2026-07-06 · Official fee schedule
-
Per IB-501 Table 501C effective May 2026, cross-referenced from IB-123: roof re-sheathing on a single dwelling is billed hourly for plan check when plans are required plus $264.25 inspection per building, full roof structure replacement per 2,000 sq ft is $1,942.13 plan check base plus $264.25 inspection base
Verified 2026-06-17 · Official fee schedule
-
Roof replacement permits have no dedicated fee line, they are valuation-based building permits under Table A, minimum $195 base fee for valuation up to $1,000 then a rising per-$1,000 rate per the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
Residential re-roof permit fee is a $26 minimum for the first $1,000 of value plus $5 per additional $1,000, per the FY2025-26 Fee Directory's Residential Fees table
Verified 2026-07-06 · Official fee schedule
-
Roof replacement with no structural change uses the Short-Form building permit at $20 primary plus $10 per $1,000 of estimated cost, per the ISD fee schedule effective 5/15/2023
Verified 2026-06-18 · Official fee schedule
-
No dedicated roofing line; the building subcode repair fee of $15 per $1,000 of estimated cost applies with a $50 minimum short-permit fee, per city ordinance Ch. 160-1
Verified 2026-07-06
-
Roof work beyond normal maintenance (repairs over 33 percent of roof area) is billed as a residential building permit at $5 per $1,000 of valuation plus a $25 zoning fee and 10% codes tech fee, per the Metro Codes fee schedule (Dec 2025)
Verified 2026-06-18 · Official fee schedule
-
$50 plus $5 per $1,000 of construction value, plus a 2% state levy and a $10 technology fee (city Roofing and Siding Permit Fees, rev Jul-2025)
Verified 2026-07-19
Plus 45 more localities with a verified note, each on its own permit page. Browse every roof replacement page
Shed permit fees
Verified in 57 localities. Dollar figures appearing in those schedules run from $0.02 to $50,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
No shed-specific line; an accessory structure needing a permit bills under the Section B101 valuation table, no fee at $1,000 or less unless inspected, then $15 for the first $1,000 plus $5 per additional thousand up to $50,000, per the county Schedule of Building Permit Fees
Verified 2026-07-06 · Official fee schedule
-
Building permit fee by valuation per Construction Fees Resolution 17-025; residential fee starts at $85.00 for work valued up to $12,000; all construction permit fees due at time of permit issuance.
Verified 2026-07-19 · Official fee schedule
-
Sheds under 200 sq ft with no utility connections need no permit per the Residential Construction Homeowners Guide; a larger or utility-connected shed is valuation based via the Residential Rate Table, $220 minimum for the $0 to $8,333 bracket
Verified 2026-06-17 · Official fee schedule
-
Sheds of 256 sq ft or less and one story need no permit; larger or taller sheds take the building permit formula of $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy, capped at $693.60 with levy, per the county permit and fee pages
Verified 2026-07-06 · Official fee schedule
-
Mecklenburg County, North Carolina
Trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026; sheds at or under 12 feet in every dimension need only a zoning permit
Verified 2026-06-18 · Official fee schedule
-
No shed-specific valuation multiplier printed; a shed requiring a permit takes the valuation-based building permit fee per LAMC 91.113 Table 1-A off declared project valuation, posted base $65 for valuation $100.01 to $2,000
Verified 2026-06-17 · Official fee schedule
-
Building permit fee follows PCC Table 17C.10-1-B (valuation based): $69.00 for construction valued at $500 or less, plus $2.00 for each additional $100 or fraction up to $2,000, plus a plan review fee equal to 65 percent of the building permit fee (PCC Table 17C.10-1-C).
Verified 2026-07-06 · Official fee schedule
-
No dedicated shed line in the fee schedule; the closest official category in IB-501 Table 501C effective May 2026 is Garage/Storage for a single dwelling at $1,501.42 plan check per structure with inspection billed hourly
Verified 2026-06-17 · Official fee schedule
-
Valuation-based building permit fee, minimum $50 for work valued up to $1,100; building plan review fee is 65 percent of the calculated permit fee.
Verified 2026-07-19 · Official fee schedule
-
Shed permits have no dedicated fee line, they are valuation-based building permits under Table A, minimum $195 base fee for valuation up to $1,000 then a rising per-$1,000 rate per the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
A $12 flat Zoning Permit covers a tool or storage shed 120 sq ft or smaller; a larger shed bills under the Accessory Structure schedule at a $26 minimum plus $4 per additional $1,000 of value, per the FY2025-26 Fee Directory
Verified 2026-06-18 · Official fee schedule
-
Sheds of 100 sq ft or more are billed as a residential building permit at $5 per $1,000 of valuation plus a $25 zoning fee and 10% codes tech fee, per the Metro Codes fee schedule (Dec 2025)
Verified 2026-06-18 · Official fee schedule
Plus 45 more localities with a verified note, each on its own permit page. Browse every shed page
Solar permit fees
Verified in 59 localities. Dollar figures appearing in those schedules run from $0.10 to $75,001, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; the solar application requires a cost estimate and no separate solar fee line exists, per the 2024 Fee Schedule effective 7/1/2024
Verified 2026-07-06 · Official fee schedule
-
Solar voltaic (residential and commercial) is charged per the building permit fee table in Construction Fees Resolution 17-025; residential table starts at $85.00 for work valued up to $12,000.
Verified 2026-07-19 · Official fee schedule
-
Residential solar needs only an electrical permit with no separate building permit per the county's solar pathway memo, billed at $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy
Verified 2026-07-06 · Official fee schedule
-
Mecklenburg County, North Carolina
Photovoltaic installs bill as an electrical trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review plus $12.19 per $1,000 over $3,000 and a $3 technology charge per permit, per the LUESA Fee Ordinance revised July 1 2026
Verified 2026-06-18 · Official fee schedule
-
No dedicated solar line; PV installation bills under the Electrical Permit Additions and Alterations schedule at a $38 minimum for the first $1,000 of valuation plus $5 per additional $1,000, per the FY2025-26 Fee Directory
Verified 2026-06-18 · Official fee schedule
-
Systems under 20 kWh on 1-2 family homes qualify for Short-Form at $20 primary plus $10 per $1,000 of estimated cost; 20 kWh and up or 3+ family buildings need Long-Form at $50 primary plus $10 per $1,000, plus a separate Electrical Permit, per the ISD fee schedule effective 5/15/2023
Verified 2026-06-18 · Official fee schedule
-
Flat $200 building permit fee for the solar panel structure plus a separate electrical permit at $25 per $1,000 of cost, per the city's solar permit page
Verified 2026-06-18 · Official fee schedule
-
The structural mounting permit bills under the Section B101 valuation table starting at $15 for the first $1,000 plus $5 per additional thousand; the PV electrical connection is permitted separately through the state CORE system, per the county Schedule of Building Permit Fees
Verified 2026-07-06 · Official fee schedule
-
Solar PV is permitted through the electrical permit: systems below 12kW are a flat $438 online fee plus the $55.48 administrative fee, systems from 12kW to 26kW take a plan-reviewed permit at three times the $292 base fee, $876, all plus a 5% technology fee, per the 2026 Fee Subtitle Tables D-15 and D-14
Verified 2026-06-18 · Official fee schedule
-
Residential solar photovoltaic permits use fixed-fee options from $780 with plan review and 3 inspections down to $293 administrative fee with no plan review and 1 inspection, or Table A valuation for non-standard systems, per the PDD Fee Schedule effective 1/20/2026
Verified 2026-06-18 · Official fee schedule
-
$700 for a residential photovoltaic system up to 10 kW plus $176 per additional 10 kW on the same system, battery and EV receptacle add-ons priced separately, per the DSC Schedule of Fees effective 10/01/2025
Verified 2026-07-06 · Official fee schedule
-
Roof-mounted residential solar is printed at $300 ($150 inspection plus $140 plan review itemized) and ground-mounted under 6 feet at $500 ($200 plus $190 itemized) in the June 2024 Summary of the Fee Schedule; the header totals and itemized lines disagree, so confirm the current total with Permitting Services
Verified 2026-06-18 · Official fee schedule
Plus 47 more localities with a verified note, each on its own permit page. Browse every solar page
Water Heater permit fees
Verified in 15 localities. Dollar figures appearing in those schedules run from $0.15 to $5,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
-
Electric, gas and oil water heaters need a mechanical permit for new or replacement installs, billed at $100 for the first $5,000 of labor and material cost plus $6 per additional $1,000 plus a 2% state levy, per the county mechanical permit and fee pages
Verified 2026-07-12 · Official fee schedule
-
Water heater replacement is a flat $147 covering the $100 base plus 2% surcharge and $45 processing fee, per the county mechanical packet under the 7/1/2025 Unified Fee Schedule
Verified 2026-07-12 · Official fee schedule
-
Replacing an electric water heater with a new electric unit needs no permit; a gas water heater repaired or replaced with a like appliance is $57, new gas installation $114, gas piping to the appliance only $57, plus the 2% state levy, per the residential fee schedule effective 7/1/2025
Verified 2026-07-12 · Official fee schedule
-
Prince William County, Virginia
Billed under Plumbing as an appliance: base fee $88.44 ($110.65 with surcharges) plus $7.36 per appliance ($9.20) for electric or gas units; replacing an electric water heater with a same-size unit in the same location needs no permit per the Do I Need a Permit guide, per the FY27 BDD Fee Schedule
Verified 2026-07-12 · Official fee schedule
-
No water-heater line; installation or replacement bills under the residential Trades plumbing category at $0.15 per square foot with a $100 minimum, plus Virginia's 2% state surcharge, per the FY27 Tax and Fee Schedule
Verified 2026-07-12 · Official fee schedule
-
A gas water heater needs a trade permit at $84.15 including the technology fee; replacing a non-gas unit needs no permit, per the county Do I Need a Building Permit sheet and fee schedule
Verified 2026-07-12 · Official fee schedule
-
Billed as a household appliance permit, $78.75 for one appliance per Ch. 61-1-3(d)13, with an added plumbing fixture fee possible when supply or drain connections change, per Appendix Q effective 2026-07-01
Verified 2026-07-12 · Official fee schedule
-
No permit to repair or in-kind replace a water heater in a residential building up to 4 stories per chicago.gov; otherwise $75 per dwelling unit per Table 14A-12-1204.2
Verified 2026-07-12 · Official fee schedule
-
No dedicated line; install or replacement bills under the standard Plumbing Permit at $70 for 1 and 2 family dwellings, with a gas-fired unit also triggering the separate $70 Gas Permit fee, per the July 2022 fee schedule
Verified 2026-07-12 · Official fee schedule
-
Not separately itemized; a water heater replacement bills as a plumbing or mechanical trade permit under the All Trades line at $60 per trade per system, plus the 2 percent state levy and 2.75 percent technology fee, per the Development Services Fee Schedule effective 11/1/2024
Verified 2026-07-12 · Official fee schedule
-
Water heater replacement bills as the $50 plumbing filing fee plus the $25 fixture-replacement exception fee for a water heater, plus a 10% technology fee, per the FY27 Plumbing Permit Fee Schedule effective 7/1/2026
Verified 2026-07-12 · Official fee schedule
-
Flat $31 plumbing permit fee to replace a water heater in a one or two family dwelling, per the L&I construction fee schedule effective 1/1/2025
Verified 2026-07-12 · Official fee schedule
Plus 3 more localities with a verified note, each on its own permit page. Browse every water heater page
Methodology
Every fee note above was written while reading the locality's current official fee schedule and was reviewed against a quoted line of that schedule before it entered the dataset, with the date recorded. Notes repeat the schedule's own billing basis (flat fee, valuation tier, plan review percentage) rather than reducing everything to one number.
Honest gaps stay gaps: a few localities publish no usable schedule (some block archives, some publish none for certain trades), and some permits are issued by a state agency instead of the locality. Those rows say exactly that.
The measured medians come from official open-data portals and are computed from real issued permits. Sample sizes are shown; medians are used throughout. Read more about the process on how we verify.