What does a building permit cost?
We read the official fee schedule of every locality we cover and recorded what it says for 1775 permit scenarios across 175 US localities. Each entry below quotes the schedule's own terms, with the verification date. Where a locality publishes no figure, or hands the permit to a state agency, we say that instead of guessing. Many localities bill by project valuation, so a single flat number often does not exist; the notes keep that honesty.
Median fees measured from real permit records
For jurisdictions whose open-data portals publish issued permits, we compute the median fee from the records themselves. These are actual amounts charged, not schedule text.
| Jurisdiction | Median fee | Records |
|---|---|---|
| Chicago, Illinois | $1,142 | 5,329 |
| Mesa, Arizona | $520 | 5,364 |
| Boston, Massachusetts | $90 | 19,468 |
Medians, not averages, so a few large projects cannot skew the figure. Full context in the turnaround study.
Bathroom Remodel permit fees
Verified in 53 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- New Castle County, Delaware By valuation
The schedule's wording
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states. Mechanical or Plumbing Permit (Chapter 6 Schedule of Permit and Review Fees, as amended through January 1, 2026): $5.25 for the first $1,000 valuation or any part thereof, $5.25 for each additional $1,000 or part thereof, minimum fee $65.00.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Fargo, North Dakota By valuation
The schedule's wording
Residential Building Permit Fees (one- and two-family dwellings), effective January 1, 2026, by total valuation: up to and including $1,000.00, $50.00; $1,001.00 to $100,000.00, $50.00 for the first $1,000.00 plus $5.56 for each additional $1,000.00 or fraction thereof; $100,001.00 and up, $600.44 for the first $100,000.00 plus $3.06 for each additional $1,000.00. Work begun before the permit: permit fee doubled for $0 to $50,000 of valuation. Plumbing, electrical and mechanical work carry their own permits and fees.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Providence, Rhode Island By valuation
The schedule's wording
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule. Plumbing and electrical permits are separate, with fees by valuation.
- Anchorage, Alaska By valuation
The schedule's wording
Trade-only remodels: AMC 23.10.109 Table 3-A item 3.A, "Trade Permits (Plumbing, mechanical, or electrical work but no structural or alteration work)": $175, 2 inspections; or a retrofit permit under Table 3-E at $175 with 2 inspections (for example "Electrical, plumbing or mechanical alterations to a residential building containing 4 or fewer dwelling units"); a Table 3-A item 3 trade permit also carries the nonrefundable $15 digital maintenance fee for "Miscellaneous Building Permits (per item 3)" (Table 3-A item 4). Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026). Remodels with structural or alteration work: Table 3-A item 2, "Up to $50,000 (Repairs, decks, and minor alterations only)" $350 with 4 inspections, otherwise $0.009 * (Valuation), minimum $450, plus Table 3-B plan review.
- Billings, Montana By valuation
The schedule's wording
Building permit fees are set by valuation (Permit Fees by Valuation schedule, PDF dated April 23, 2026): $30.00 for $1 to $1,000; $45.00 for $1,001 to $2,000; $45.00 for the first $2,000 plus $9.00 for each additional $1,000 or fraction up to $25,000; $252.00 for the first $25,000 plus $6.00 for each additional $1,000 or fraction up to $50,000. Fees are charged on the higher of the bid price or the Building Safety Journal valuation table. Remodel valuation is the contract price or estimated value of material and labor; plumbing and electrical sub-permits are priced on their own schedules.
- Greenville County, South Carolina By valuation
The schedule's wording
Priced as an alteration on the valuation table at actual project cost (the schedule's note reads "*** Renovations, alterations, and swimming pools to be used in the above table will be based on the actual cost of the project."), plus trade fees: plumbing minimum fee per permit $72.00 and Fixtures $6.00 each; electrical minimum fee per permit $72.00. Building work is priced on the Residential Permit Fees schedule by total valuation: "$1,000 and less" is "$36.00 minimum permit fee", and "$1,000 to $50,000" is "$22.50 for the first $1,000 plus $7.50 for each additional thousand or fraction thereof, to and including $50,000". The schedule PDF carries no effective date or resolution number; the department's notice says "Starting July 1, 2025, Residential and Commercial building permit fees will increase by 20 percent."
- Cheyenne, Wyoming By valuation
The schedule's wording
Valuation-based, from the City of Cheyenne Building and Construction Permit Fees table in City Code 15.08.030 (effective January 30, 2023, Ord. No. 4485): $1.00 to $500.00 is $23.50; $501.00 to $2,000.00 is $23.50 for the first $500.00 plus $3.05 for each additional $100.00; $2,001.00 to $25,000.00 is $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00; $25,001.00 to $50,000.00 is $391.75 for the first $25,000.00 plus $10.10 for each additional $1,000.00 (higher tiers continue). Plan review, when submittal documents are required, is 65 percent of the permit fee and is in addition to it. Reinspection fee $250.00. Work begun before the permit is issued carries an investigation fee equal to the permit fee (IRC R108.6 as amended by 15.10.020(H)).
- Sioux Falls, South Dakota By valuation
The schedule's wording
2026 Building Permit Valuation/Fee Schedule (City of Sioux Falls, fee schedule dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule": "$1-4,000" $40.00; "$4,001-25,000" "$32.50 for the first $2,000 plus $6.00 for each additional $1,000 or fraction thereof, to and including $25,000"; "$25,001-50,000" "$170.50 for the first $25,000 plus $4.50 for each additional $1,000 or fraction thereof". Residential projects have no plan review fee (Residential Plan Review page). Plumbing and electrical permits are separate, on the MEP valuation schedule ($40 up to $5,000 of trade valuation).
- Martin County, Florida By valuation
The schedule's wording
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
- Honolulu, Hawaii By valuation
The schedule's wording
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Plus 41 more localities with a verified note, each on its own permit page. Browse every bathroom remodel page
Deck permit fees
Verified in 166 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- New Castle County, Delaware By valuation
The schedule's wording
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states.
- Pinellas County, Florida By valuation
The schedule's wording
No dedicated deck line; billed under Combination Permits IV-A (1 and 2 family dwellings and accessory structures, valuation up to $600,000) at $11.00 per $1,000.00 of valuation with a $100.00 minimum per inspection, per the FY27 Adopted BDRS user fees.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Fargo, North Dakota By valuation
The schedule's wording
Residential Building Permit Fees (one- and two-family dwellings), effective January 1, 2026, by total valuation: up to and including $1,000.00, $50.00; $1,001.00 to $100,000.00, $50.00 for the first $1,000.00 plus $5.56 for each additional $1,000.00 or fraction thereof; $100,001.00 and up, $600.44 for the first $100,000.00 plus $3.06 for each additional $1,000.00. Work begun before the permit: permit fee doubled for $0 to $50,000 of valuation.
- Kansas City, Missouri By valuation
The schedule's wording
A deck over the exemption is a building permit priced from the one- and two-family valuation table in Sec. 18-20(b)(2): $52.00 up to $1,000.00 of valuation, $58.00 from $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 per additional $1,000.00 or fraction thereof to $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. One- and two-family work carries no separate construction document review fee. A reinspection is $75.00 under Sec. 18-20(h)(6), and building without the permit first triples the permit fee under Sec. 18-20(e)(2).
- Newark, New Jersey By valuation
The schedule's wording
Newark municipal code Chapter 7:2-3.1c prices deck work as 'Building Renovation and Alteration', 'Fees based on estimated cost of construction for all building types': $28 per $1,000 between $0 and $50,000, $21 per $1,000 from $50,001 to $100,000, and $17 per $1,000 over $100,000, plus a DCA administrative surcharge of $0.80 per $1,000. 'Minimum Building Permit: $58.' (Ord. 6 S+FD, 9-5-2007; code current through 12-20-2023.)
- Greensboro, North Carolina By valuation
The schedule's wording
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'
- Mecklenburg County, North Carolina Per unit
The schedule's wording
Building permit priced off total construction permit value: $59.70 for $1 to $3,000 on projects not requiring plan review, then $59.70 plus $12.19 per $1,000 or part over $3,000 up to $50,000. The fee is the greater of that schedule or Note a, which charges projects under $100,000 and all renovation/alteration projects $79.61 per trade plus $.12 per square foot for the building trade and $.08 per square foot for each electrical, mechanical or plumbing trade involved. A $3.00 technology charge is added to every permit, per the LUESA Fee Ordinance revised July 1, 2026.
- Gwinnett County, Georgia By valuation
The schedule's wording
Planning and Development Fee Schedule, "Building Permit Fees (Effective August 25, 2026)". The schedule has no line naming decks. Its Other Building Permit Fees are $125 for a Residential Renovation Permit on Minor Renovation Projects (valued less than $75,000) and $4 per $1,000 of construction value on Extensive Renovation Projects (valued at $75,000 or greater); it does not say whether a deck addition is priced as a renovation. The department's Deck Additions handout still states "$6 per $1,000 of estimated construction cost (minimum fee is $30), plus a $25 Certificate of Completion fee". Confirm the amount with the Permits Section at 678-518-6020.
- Providence, Rhode Island By valuation
The schedule's wording
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule.
- Anchorage, Alaska By valuation
The schedule's wording
AMC 23.10.109 Table 3-A item 2, Residential Construction: "Up to $50,000 (Repairs, decks, and minor alterations only)" $350 with 4 inspections; plus Table 3-B residential plan review ("Regular Plan Review" 0.005 *(Valuation), minimum $75; the 50% repair-only rate "does not include minor alterations or decks"), land use plan review at 15% of the Table 3-A fee (minimum $75), and the $50 residential digital maintenance fee. Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026).
- Alameda County, California By valuation
The schedule's wording
No deck line item appears in the Building Inspection Department Service Fee Schedule (Schedule A, effective July 1, 2024). A deck permit is priced from construction valuation using the Schedule A building permit fee table (for example, '$381.46 for the first $10,000 plus $8.88 for each additional $1,000.00 or fraction thereof, to and including $50,000'), plus building plan review at 80% of the building permit fee with a $140.00 minimum, plus a $20.00 single-permit processing fee.
Plus 154 more localities with a verified note, each on its own permit page. Browse every deck page
Electrical permit fees
Verified in 171 localities. Dollar figures appearing in those schedules run from $0.01 to $100,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- Kansas City, Missouri By valuation
The schedule's wording
Electrical permits for one- and two-family detached dwellings are priced from the same valuation table as every other trade, Sec. 18-20(b)(2): $52.00 for total valuation of $0.00 to $1,000.00, $58.00 for $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. Sec. 18-20(h)(9) adds a distinct $54.00 electrical service reconnect fee when an owner asks for an inspection of an existing service so the utility can reconnect, creditable toward a permit fee if permitted work turns out to be needed, and waived where the service was disconnected by a fire in the previous 90 days.
- Mecklenburg County, North Carolina Per unit
The schedule's wording
Electrical trade permit priced off total construction permit value: $59.70 for $1 to $3,000 on projects not requiring plan review, then $59.70 plus $12.19 per $1,000 or part over $3,000 up to $50,000. The fee is the greater of that schedule or Note a, which charges projects under $100,000 and all renovation/alteration projects $79.61 per trade plus $.12 per square foot for the building trade and $.08 per square foot for each electrical, mechanical or plumbing trade involved. A $3.00 technology charge is added to every permit, per the LUESA Fee Ordinance revised July 1, 2026.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Charlotte County, Florida By valuation
The schedule's wording
At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge.
- Charlotte, North Carolina By valuation
The schedule's wording
Electrical permits are charged as a trade permit under the LUESA Fee Ordinance (revised July 1, 2026): $1 to $3,000 in total construction permit value is a $59.70 minimum fee per trade for projects not requiring plan review, and $3,001 to $50,000 is '$59.70 plus $12.19 per $1,000 or part over $3,000', plus a $3.00 technology charge on all permits. Where the owner serves as the contractor and total construction permit value is less than $40,000, the ordinance charges $60.00 per BEMP trade base permit fee, $45.00 per BEMP trade plan review if required and $45.00 per inspection trip. Item 29 of the same ordinance charges the original permit fee times 3.75 for work started without a permit.
- Providence, Rhode Island By valuation
The schedule's wording
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
- Cheyenne, Wyoming By valuation
The schedule's wording
Valuation-based, from the City of Cheyenne Building and Construction Permit Fees table in City Code 15.08.030 (effective January 30, 2023, Ord. No. 4485): $1.00 to $500.00 is $23.50; $501.00 to $2,000.00 is $23.50 for the first $500.00 plus $3.05 for each additional $100.00; $2,001.00 to $25,000.00 is $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00; $25,001.00 to $50,000.00 is $391.75 for the first $25,000.00 plus $10.10 for each additional $1,000.00 (higher tiers continue). Plan review, when submittal documents are required, is 65 percent of the permit fee and is in addition to it. Reinspection fee $250.00. Work begun before the permit is issued carries an investigation fee equal to the permit fee (IRC R108.6 as amended by 15.10.020(H)).
- Martin County, Florida By valuation
The schedule's wording
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
- Honolulu, Hawaii By valuation
The schedule's wording
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
- Sioux Falls, South Dakota By valuation
The schedule's wording
2026 Mechanical, Electrical, or Plumbing Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for "$0.01 to $5,000.00" and "$40 for the first $5,000, plus $6 for each additional $1,000 or fraction thereof, to and including $25,000"; a homeowner's permit is $25 plus that fee (Code of Ordinances Table 104.5 "Homeowner s permit" $25 for plumbing; IMC Table No. 1-A "Homeowner's permit" $25 for mechanical). Electrical homeowner's permits are available only to an owner-occupant wiring his or her own home (Code of Ordinances 150.233).
- Overland Park, Kansas By valuation
The schedule's wording
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
- Phoenix, Arizona By valuation
The schedule's wording
Electrical permits have no dedicated fee line; they are valuation-based building permits under Table A: a $195 base fee for a project valuation of $1 to $1,000, then $195 on the first $1,000 plus $12 for each additional $1,000 or fraction up to $10,000, with a lower rate per $1,000 in the higher brackets, per the PDD Fee Schedule effective 1/20/2026.
Plus 159 more localities with a verified note, each on its own permit page. Browse every electrical page
EV Charger permit fees
Verified in 53 localities. Dollar figures appearing in those schedules run from $0.01 to $50,001, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Providence, Rhode Island By valuation
The schedule's wording
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
- Cheyenne, Wyoming By valuation
The schedule's wording
Valuation-based, from the City of Cheyenne Building and Construction Permit Fees table in City Code 15.08.030 (effective January 30, 2023, Ord. No. 4485): $1.00 to $500.00 is $23.50; $501.00 to $2,000.00 is $23.50 for the first $500.00 plus $3.05 for each additional $100.00; $2,001.00 to $25,000.00 is $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00; $25,001.00 to $50,000.00 is $391.75 for the first $25,000.00 plus $10.10 for each additional $1,000.00 (higher tiers continue). Plan review, when submittal documents are required, is 65 percent of the permit fee and is in addition to it. Reinspection fee $250.00. Work begun before the permit is issued carries an investigation fee equal to the permit fee (IRC R108.6 as amended by 15.10.020(H)).
- Martin County, Florida By valuation
The schedule's wording
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
- Honolulu, Hawaii By valuation
The schedule's wording
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value. EV charger projects may use the expedited clean-energy process under ROH 18-5.10.
- Sioux Falls, South Dakota By valuation
The schedule's wording
2026 Mechanical, Electrical, or Plumbing Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for "$0.01 to $5,000.00" and "$40 for the first $5,000, plus $6 for each additional $1,000 or fraction thereof, to and including $25,000"; a homeowner's permit is $25 plus that fee (Code of Ordinances Table 104.5 "Homeowner s permit" $25 for plumbing; IMC Table No. 1-A "Homeowner's permit" $25 for mechanical).
- Philadelphia, Pennsylvania By valuation
The schedule's wording
Charged as an Electrical Permit with no EV-specific line: $100 nonrefundable filing fee (counted toward the final permit fee); permit fee $25 for each $1,000 or fraction thereof of estimated electrical construction cost, minimum $63, maximum $18,975; city surcharge $3 and state surcharge $4.50 per permit, per L&I's Get an Electrical Permit page.
- Henrico County, Virginia By valuation
The schedule's wording
No EV-specific fee; an electrical permit on an existing one- or two-family dwelling is $100 for the first $5,000 of estimated cost plus $6 per additional $1,000 or fraction thereof, plus the 2% state levy, per Henrico's Electrical Permit page
- Miami, Florida By valuation
The schedule's wording
Residential (up to 3 units) building, plumbing, mechanical and electrical permits: 0.50% of estimated construction cost; "Residential less than estimated $2,500.00": $45.00; "Minimum Permit Fee": $110.00; "All Permits non-refundable application fee": $40.00; "Dry run/Up-Front per $1,000.00 of estimated construction value": $2.80 (no up-front fee on residential work under $2,500); "Solid Waste Residential Surcharge" $0.22 per $100.00 of estimated cost (minimum $26.00, maximum $600.00). State and Miami-Dade County surcharges are extra. Exhibit C Fee Schedule, Building, Chapters 10, 17, 20, adopted by Resolution R-26-0200 (Ordinance 14456), April 23, 2026.
- Birmingham, Alabama By valuation
The schedule's wording
Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2).
- Stamford, Connecticut By valuation
The schedule's wording
"Residential Electrical, plumbing, HVAC": "$13.00 per $1000 of construction value", minimum $60.00, plus $0.26 per $1,000 State Education Fund fee (City Building Permit Fees page; no effective date printed).
- Burlington, Vermont By valuation
The schedule's wording
Building permit: Burlington Code of Ordinances (BCO) Sec. 8-28(a), "$8.50 per $1,000.00" of Estimated Cost of Construction "with a minimum permit fee of thirty ($30.00) dollars" (Permit Applications and Forms page). Starting work before the permit is issued adds work-without-permit fees under BCO 8-28(f). Electrical permit fees are not published on the city site.
Plus 41 more localities with a verified note, each on its own permit page. Browse every ev charger page
Fence permit fees
Verified in 158 localities. Dollar figures appearing in those schedules run from $0.01 to $150,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Fargo, North Dakota By valuation
The schedule's wording
Residential Building Permit Fees (one- and two-family dwellings), effective January 1, 2026, by total valuation: up to and including $1,000.00, $50.00; $1,001.00 to $100,000.00, $50.00 for the first $1,000.00 plus $5.56 for each additional $1,000.00 or fraction thereof; $100,001.00 and up, $600.44 for the first $100,000.00 plus $3.06 for each additional $1,000.00. Work begun before the permit: permit fee doubled for $0 to $50,000 of valuation.
- Cobb County, Georgia By valuation
The schedule's wording
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; no fence-specific line item, per the 2024 Fee Schedule effective 7/1/2024
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Anchorage, Alaska By valuation
The schedule's wording
No fence-specific fee. A fence that needs a building permit is residential construction under AMC 23.10.109 Table 3-A item 2 ("All others" $0.009 * (Valuation), minimum $450, or $350 for work up to $50,000 limited to repairs, decks and minor alterations), plus Table 3-B plan review. Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026).
- San Francisco, California By valuation
The schedule's wording
Building permit fees are valuation-based under Table 1A-A Building Permit Fees ("July 2026", applying "to all building permits issued on and after July 12, 2026"): "The Building Permit Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to $2,000 the plan review fee is "$181 for the first $500 plus $8.60 for each additional $100 or fraction thereof" and the permit issuance fee is "$206 for the first $500 plus $4 for each additional $100 or fraction thereof"; for $2,001 to $50,000 they are "$310 for the first $2,000 plus $28.35" and "$266 for the first $2,000 plus $8.56" for each additional $1,000.
- Charlotte County, Florida By valuation
The schedule's wording
Charlotte County's Residential Fence page lists fees due at issuance: Zoning Review $30, plus a building fee of 0.004 x ICC valuation (only if valuation is $50,000 or more) and a surcharge of 0.025 x the building fee.
- St. Johns County, Florida By valuation
The schedule's wording
No fence-specific fee line item is published. Fence permits fall under the general Building Services Fees table: Permit Issuance Fee $14.00, plus Total Valuation of Building fee (minimum $19.00, or $11.00 for the first $1,000 plus $2.63 for each additional thousand or fraction thereof up to $50,000; higher tiers apply above that), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026).
- Ann Arbor, Michigan By valuation
The schedule's wording
The Planning Services Fence Guidelines handout (revised 3/3/2025) states a flat Fence Permit Fee of $75.00. The Building Permit Fees schedule (effective October 2019, revised 7/15/2025) adds the line "Fences over 7 feet tall ... building permit fee", so a fence taller than 7 feet is charged the $15 base application fee plus the estimated project cost permit fee ($100 for project cost up to $1,000; $100 plus $10 per $1,000 from $1,000 to $50,000) plus a plan examination fee of 20% of the building permit fee. Properties in a historic district also pay a $35 historic district staff review fee.
- Charleston, South Carolina By valuation
The schedule's wording
No fence line item exists. A fence is billed as a residential alteration or repair under the Building and Trade Permit Fee Schedule, approved by Ordinance Nos. 2017-131, 2019-064 and 2019-072, effective October 1, 2019: a $40.00 non-refundable application fee "required for all building and trade permits," plus a construction-cost based permit fee that is "Application Fee Only" at $1,000 or less of construction cost and "$15.00 for the first $1,000 construction valuation, plus $5.00 for each additional thousand or fraction thereof, to and including $50,000" above that. A plan review fee equal to 50% of the building permit fee applies when valuation exceeds $1,000 and plans must be reviewed. Starting without a permit doubles the money: the schedule's Penalties clause says "Where work for which a permit is required by this code is started or proceeded prior to obtaining said permit, the fees herein specified shall be doubled, but the payment of such double fee shall neither relieve any persons from fully complying with the requirements of this code in the execution of the work nor from any other penalties prescribed herein."
- Greenville County, South Carolina By valuation
The schedule's wording
No fence line item on the Residential Permit Fees schedule. A fence that needs a permit would fall under the schedule's valuation table: Building work is priced on the Residential Permit Fees schedule by total valuation: "$1,000 and less" is "$36.00 minimum permit fee", and "$1,000 to $50,000" is "$22.50 for the first $1,000 plus $7.50 for each additional thousand or fraction thereof, to and including $50,000". The schedule PDF carries no effective date or resolution number; the department's notice says "Starting July 1, 2025, Residential and Commercial building permit fees will increase by 20 percent."
- Williamson County, Tennessee Not priced
The schedule's wording
No fence-specific line; a fence needing a building permit bills under the Section B101 valuation table, no fee for work valued $1,000 or less unless an inspection is required ($15 per inspection), then $15 for the first $1,000 plus $5 per additional thousand up to $50,000, per the county Schedule of Building Permit Fees
Plus 146 more localities with a verified note, each on its own permit page. Browse every fence page
HVAC permit fees
Verified in 171 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- Memphis, Tennessee Per unit
The schedule's wording
M-0 fee issuance cost per permit $20.00, M-3.1 fee for the first $1,000 valuation $15.00 then $8.00 for each additional $1,000 under $1,000,000, M-4 minimum permit fee $15.00, and M-3.2.1 SINGLE FAMILY RESIDENTS ONLY, mechanical permit fees shall be based on total valuation (contract price) based on a minimum $1,000.00 per ton, per the 2022 Fee Schedule, Mechanical Permit and Inspection Fees Schedule. Work commencing before permit issuance is charged double fee. All fees exclude an administrative charge of $4.00 and a residential surcharge of $1.00, so $5.00 is added to the residential total, per the 2022 Fee Schedule.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Mecklenburg County, North Carolina Per unit
The schedule's wording
Mechanical trade permit priced off total construction permit value: $59.70 for $1 to $3,000 on projects not requiring plan review, then $59.70 plus $12.19 per $1,000 or part over $3,000 up to $50,000. The fee is the greater of that schedule or Note a, which charges projects under $100,000 and all renovation/alteration projects $79.61 per trade plus $.12 per square foot for the building trade and $.08 per square foot for each electrical, mechanical or plumbing trade involved. A $3.00 technology charge is added to every permit, per the LUESA Fee Ordinance revised July 1, 2026.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Little Rock, Arkansas Not priced
The schedule's wording
Heating/air mechanical permit for replacements, repairs, alterations and additions by total valuation: "$500.00 and less" no fee unless an inspection is required ($25.75 per inspection); "$100.01 to $50,000.00" "Fifty-One 50/100 Dollars ($51.50) for the first two thousand dollars ($2,000.00) plus Six and 18/100 Dollars ($6.18) for each additional one thousand dollars ($1,000.00) or fraction thereof"; minimum fee for any heating/air or mechanical permit $50.00; new one- and two-family dwellings $0.11 per square foot. Little Rock Code Sec. 8-31(c), as amended through Ord. No. 22,703 (December 16, 2025), read on Municode.
- Charlotte County, Florida By valuation
The schedule's wording
At application: $90 flat building fee unless valuation is $50,000 or more (then 0.004 x ICC valuation), plus a 0.025 x building-fee surcharge.
- Providence, Rhode Island By valuation
The schedule's wording
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
- Cheyenne, Wyoming By valuation
The schedule's wording
Valuation-based, from the City of Cheyenne Building and Construction Permit Fees table in City Code 15.08.030 (effective January 30, 2023, Ord. No. 4485): $1.00 to $500.00 is $23.50; $501.00 to $2,000.00 is $23.50 for the first $500.00 plus $3.05 for each additional $100.00; $2,001.00 to $25,000.00 is $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00; $25,001.00 to $50,000.00 is $391.75 for the first $25,000.00 plus $10.10 for each additional $1,000.00 (higher tiers continue). Plan review, when submittal documents are required, is 65 percent of the permit fee and is in addition to it. Reinspection fee $250.00. Work begun before the permit is issued carries an investigation fee equal to the permit fee (IRC R108.6 as amended by 15.10.020(H)).
- Contra Costa County, California By valuation
The schedule's wording
Land Development Fee Schedule S-002 D.6, "Mechanical Permit (Other) $75.00 minimum." Fees for mechanical work not covered by the new dwelling, addition or alteration, new commercial, shell, or tenant improvement tiers are calculated from the S-002 A.1 Building Permit valuation table, which starts at $75.00 for improvement value up to $2,000 plus $13.75 for each additional $1,000. Mechanical fees for an addition or alteration to a dwelling unit start at $75.00 for improvement value up to $25,000. Fee schedule adopted May 24, 2022, effective August 10, 2022.
- Martin County, Florida By valuation
The schedule's wording
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
- Honolulu, Hawaii By valuation
The schedule's wording
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
- Sioux Falls, South Dakota By valuation
The schedule's wording
2026 Mechanical, Electrical, or Plumbing Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for "$0.01 to $5,000.00" and "$40 for the first $5,000, plus $6 for each additional $1,000 or fraction thereof, to and including $25,000"; a homeowner's permit is $25 plus that fee (Code of Ordinances Table 104.5 "Homeowner s permit" $25 for plumbing; IMC Table No. 1-A "Homeowner's permit" $25 for mechanical).
Plus 159 more localities with a verified note, each on its own permit page. Browse every hvac page
Patio permit fees
Verified in 112 localities. Dollar figures appearing in those schedules run from $0.03 to $150,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Greensboro, North Carolina By valuation
The schedule's wording
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'
- Mecklenburg County, North Carolina Per unit
The schedule's wording
Building permit priced off total construction permit value: $59.70 for $1 to $3,000 on projects not requiring plan review, then $59.70 plus $12.19 per $1,000 or part over $3,000 up to $50,000. The fee is the greater of that schedule or Note a, which charges projects under $100,000 and all renovation/alteration projects $79.61 per trade plus $.12 per square foot for the building trade and $.08 per square foot for each electrical, mechanical or plumbing trade involved. A $3.00 technology charge is added to every permit, per the LUESA Fee Ordinance revised July 1, 2026.
- Cobb County, Georgia By valuation
The schedule's wording
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; no patio-specific line item, per the 2024 Fee Schedule effective 7/1/2024
- St. Johns County, Florida By valuation
The schedule's wording
No patio-specific fee line item is published. Patio permits fall under the general Building Services Fees table: Permit Issuance Fee $14.00, plus Total Valuation of Building fee (minimum $19.00, or $11.00 for the first $1,000 plus $2.63 for each additional thousand up to $50,000; higher tiers apply above that), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026).
- Newark, New Jersey By valuation
The schedule's wording
No patio line in Newark municipal code Chapter 7:2-3.1. A roofed patio cover is priced either as an addition ($0.03 per cubic foot for residential buildings) or as renovation and alteration ($28 per $1,000 of estimated cost between $0 and $50,000), subject to the 'Minimum Building Permit: $58.' (Ord. 6 S+FD, 9-5-2007.)
- Williamson County, Tennessee By valuation
The schedule's wording
No patio-specific line; billed under the Section B101 valuation table, $15.00 for the first $1,000 plus $5.00 per additional thousand up to $50,000. When valuation exceeds $1,000.00 and a plan is required, a plan-checking fee of one-half of the building permit fee is added, per the county Schedule of Permit Fees.
- Burlington, Vermont By valuation
The schedule's wording
Zoning permit, FY2027 Fee Schedule (effective July 1, 2026): "Basic Zoning Permit (non-design control RL)", "Fence Permit" and "Certificate of Appropriateness Level I (COA I)" (projects under $29,000 estimated construction cost) are "$15 filing fee +" "$107"; COA Level II (estimated construction cost of $29,000 or more) is $15 filing fee + $140 + $2.20 per $1,000 of ECC, plus a Development Review Fee of $4.50 per $1,000 of ECC. A building permit may also apply under the all-work rule: Building permit: Burlington Code of Ordinances (BCO) Sec. 8-28(a), "$8.50 per $1,000.00" of Estimated Cost of Construction "with a minimum permit fee of thirty ($30.00) dollars" (Permit Applications and Forms page). Starting work before the permit is issued adds work-without-permit fees under BCO 8-28(f).
- Los Angeles County, California By valuation
The schedule's wording
No patio line item is published. A patio cover or patio enclosure is priced from the valuation-based Table 1-A Building Permit Fees ($65.36 for a total valuation of $0 to and including $700; $98.09 for more than $700 to and including $25,000 plus $25.27 for each additional $1,000 or fraction thereof in excess of $1,000), plus the $41.35 permit issuance fee. Building Code Fee Schedule (Title 26, Ord. No. 2013-0048), effective July 1, 2026.
- Martin County, Florida By valuation
The schedule's wording
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
- Honolulu, Hawaii By valuation
The schedule's wording
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
- Anne Arundel County, Maryland By valuation
The schedule's wording
No building permit fee for an exempt patio. A Standard Grading Plan Application may be required depending on size and disturbed area (Do I Need a Permit? guide); a raised patio that needs a building permit is valuation-based: Building permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 | $242.00 plus .010 times estimated cost above $25,000.00", plus "A non-refundable application fee of $43.00 will be added to all building permits." Minimum Building Permit Fee $86.00, effective October 1, 2024 (Permit Fees page).
Plus 100 more localities with a verified note, each on its own permit page. Browse every patio page
Plumbing permit fees
Verified in 171 localities. Dollar figures appearing in those schedules run from $0.01 to $100,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- Kansas City, Missouri By valuation
The schedule's wording
Plumbing permits for one- and two-family detached dwellings use the Sec. 18-20(b)(2) valuation table: $52.00 for total valuation of $0.00 to $1,000.00, $58.00 for $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. Water and sewer service line permits are billed separately by the Water Services Department under the KC Water Rules and Regulations for Water Service Lines (May 2022), not under Sec. 18-20; that counter is reachable at 816-513-2174.
- Mecklenburg County, North Carolina Per unit
The schedule's wording
Plumbing trade permit priced off total construction permit value: $59.70 for $1 to $3,000 on projects not requiring plan review, then $59.70 plus $12.19 per $1,000 or part over $3,000 up to $50,000. The fee is the greater of that schedule or Note a, which charges projects under $100,000 and all renovation/alteration projects $79.61 per trade plus $.12 per square foot for the building trade and $.08 per square foot for each electrical, mechanical or plumbing trade involved. A $3.00 technology charge is added to every permit, per the LUESA Fee Ordinance revised July 1, 2026.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Charlotte County, Florida By valuation
The schedule's wording
At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge.
- Charlotte, North Carolina By valuation
The schedule's wording
Plumbing is charged as a trade permit under the LUESA Fee Ordinance (revised July 1, 2026): $1 to $3,000 in total construction permit value is a $59.70 minimum fee per trade for projects not requiring plan review, and $3,001 to $50,000 is '$59.70 plus $12.19 per $1,000 or part over $3,000', plus a $3.00 technology charge on all permits. Water heater changeouts fall under item D.1, Appliance/Equipment Change Out, which covers 'hot water heaters limited to less than 50 gal. or 5500 watts input for electric and 50 gal. or 55,000 BTU for gas' and charges a total permit fee for both trade permits combined of 1.5 times the minimum permit fee when issued through Trade Internet Permitting, or 2 times the maximum permit fee when issued any other way.
- Providence, Rhode Island By valuation
The schedule's wording
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
- Cheyenne, Wyoming By valuation
The schedule's wording
Valuation-based, from the City of Cheyenne Building and Construction Permit Fees table in City Code 15.08.030 (effective January 30, 2023, Ord. No. 4485): $1.00 to $500.00 is $23.50; $501.00 to $2,000.00 is $23.50 for the first $500.00 plus $3.05 for each additional $100.00; $2,001.00 to $25,000.00 is $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00; $25,001.00 to $50,000.00 is $391.75 for the first $25,000.00 plus $10.10 for each additional $1,000.00 (higher tiers continue). Plan review, when submittal documents are required, is 65 percent of the permit fee and is in addition to it. Reinspection fee $250.00. Work begun before the permit is issued carries an investigation fee equal to the permit fee (IRC R108.6 as amended by 15.10.020(H)).
- New York City, New York By valuation
The schedule's wording
Limited Alteration Application is the usual homeowner-scale route. Table 28-112.2 item 11 sets the one-, two- or three-family LAA minimum filing fee at $130.00, and DOB's "Limited Alteration Application (LAA) Fees and Penalties, Category 1 & 2 Filing, 1, 2, 3 Family Fees" chart prices it at $130.00 for any estimated job cost up to $5,000, rising by $2.60 per $1,000 above that ($143.00 at $9,001 to $10,000; $208.00 at $34,001 to $35,000). The matching 1 and 2 family penalty for filing after the fact starts at $780.00. Full plumbing alterations are filed as work type PL, priced on construction cost with a PW3 (DOB PW3 fee-structure sheet, Rev. 04/25).
- Martin County, Florida By valuation
The schedule's wording
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
- Honolulu, Hawaii By valuation
The schedule's wording
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
- Sioux Falls, South Dakota By valuation
The schedule's wording
Table 104.5 Plumbing Permit Fees (Code of Ordinances 150.302, 2024 UPC adopted by Ord. 6-26, passed 1-20-2026): "$0.01 to $5,000.00" of plumbing valuation $40; "$5,000.01 to $25,000.00" "$40 for the first $5,000, plus $6 for each additional $1,000 or fraction thereof, to and including $25,000"; "Homeowner s permit." $25.
- Overland Park, Kansas By valuation
The schedule's wording
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
Plus 159 more localities with a verified note, each on its own permit page. Browse every plumbing page
Pool permit fees
Verified in 169 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- New Castle County, Delaware By valuation
The schedule's wording
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states. Pool heaters also need a mechanical permit for the heater and gas piping.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Fargo, North Dakota By valuation
The schedule's wording
Residential Building Permit Fees (one- and two-family dwellings), effective January 1, 2026, by total valuation: up to and including $1,000.00, $50.00; $1,001.00 to $100,000.00, $50.00 for the first $1,000.00 plus $5.56 for each additional $1,000.00 or fraction thereof; $100,001.00 and up, $600.44 for the first $100,000.00 plus $3.06 for each additional $1,000.00. Work begun before the permit: permit fee doubled for $0 to $50,000 of valuation.
- Alameda County, California By valuation
The schedule's wording
No swimming pool line item appears in the Building Inspection Department Service Fee Schedule (Schedule A, effective July 1, 2024). A pool permit is priced from construction valuation on the Schedule A table, plus building plan review at '80% of the Building Permit fees, $140.00 minimum', plus a $20.00 single-permit processing fee or $30.00 for a combo permit, plus state Strong Motion (SMIP) fees of '$10 per $100,000 valuation' for residential work and CBSC fees of '$1 per $25,000 valuation and $1 minimum'.
- Kansas City, Missouri By valuation
The schedule's wording
The pool building permit is priced from the one- and two-family valuation table in Sec. 18-20(b)(2): $52.00 up to $1,000.00 of valuation, $58.00 from $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. Information Bulletin IB119 is explicit that the valuation you declare should exclude the electrical and plumbing work, "because this type of work will require separate supplemental permits," each priced from the same table. A structural plan review may be added when the pool is 10 feet or closer to a building on the property.
- Charlotte, North Carolina By valuation
The schedule's wording
The county building permit is priced off total construction permit value under the LUESA Fee Ordinance (revised July 1, 2026): $3,001 to $50,000 is '$59.70 plus $12.19 per $1,000 or part over $3,000' and $50,001 to $100,000 is '$632.57 plus $5.49 per $1,000 or part over $50,000', plus a $3.00 technology charge on all permits. The associated electrical and any plumbing permits are separate trade permits. The City of Charlotte FY 2025 Individual Residential Lot Fee Schedule charges $50 Stormwater Services Review for 'Additions, Deck, Pool, Retaining Wall, Shed, Detached Structure' plus $70 Residential Zoning, effective for projects submitted July 1, 2024 to June 30, 2025.
- Greensboro, North Carolina By valuation
The schedule's wording
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.' Electrical Permit Fee Schedule, Document #4100 dated 7/16/24: 'Residential Swimming Pool 65.00 ea.', with 'Minimum Permit Fee 85.00' and 'Extra Inspection Fee, First Follow-up 45.00'.
- Mecklenburg County, North Carolina Per unit
The schedule's wording
Building permit priced off total construction permit value: $59.70 for $1 to $3,000 on projects not requiring plan review, then $59.70 plus $12.19 per $1,000 or part over $3,000 up to $50,000. The fee is the greater of that schedule or Note a, which charges projects under $100,000 and all renovation/alteration projects $79.61 per trade plus $.12 per square foot for the building trade and $.08 per square foot for each electrical, mechanical or plumbing trade involved. A $3.00 technology charge is added to every permit, per the LUESA Fee Ordinance revised July 1, 2026.
- Charleston, South Carolina By valuation
The schedule's wording
The pool guideline says the Application Fee, Plan Review Fee and Building Permit Fee all come from page 4 of the Building and Trade Permit Fee Schedule, whose construction-cost table covers "ALL SWIMMING POOLS - NEW CONSTRUCTION, ALTERATIONS & REPAIRS." That is a $40.00 non-refundable application fee, a permit fee of "$15.00 for the first $1,000 construction valuation, plus $5.00 for each additional thousand or fraction thereof, to and including $50,000" (then $260.00 plus $4.00 per additional thousand from $50,001 to $100,000), and a plan review fee equal to 50% of the permit fee. Schedule approved by Ordinance Nos. 2017-131, 2019-064 and 2019-072, effective October 1, 2019. Separate $40.00 application fees apply to the electrical and fuel gas sub-permits.
- Williamson County, Tennessee By valuation
The schedule's wording
No pool-specific line; billed under the Section B101 valuation table, for example $260.00 for the first $50,000 of value plus $4.00 per additional thousand up to $100,000. When valuation exceeds $1,000.00 and a plan is required, a plan-checking fee of one-half of the building permit fee is added, per the county Schedule of Permit Fees.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Providence, Rhode Island By valuation
The schedule's wording
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule. Electrical work for pumps, heaters and lighting needs a separate electrical permit.
Plus 157 more localities with a verified note, each on its own permit page. Browse every pool page
Roof Replacement permit fees
Verified in 162 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- New Castle County, Delaware By valuation
The schedule's wording
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states. Renovation work with no measurable area is priced on the declared value of the work.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Saint Paul, Minnesota By valuation
The schedule's wording
A reroof is a general building permit priced on valuation under Sec. 33.04(a), published as DSI's Building Permit Fee Schedule (Section 33.04 of the Saint Paul Legislative Code, Effective: 2/25/2023). Sample rows from the schedule: valuation 9,001 to 10,000 = $274, 11,001 to 12,000 = $316, 19,001 to 20,000 = $484. Above $100,000 the fee is $1,499 for the first $100,000 plus $8 for each additional $1,000. The Minnesota state surcharge is $0.50 for jobs valued $1.00 to $1,000, otherwise 0.0005 times job value. DSI notes that Contractor Express items, which include re-roof and roof repair, do not require plan review and can be issued online.
- Kansas City, Missouri By valuation
The schedule's wording
An exempt reroof costs nothing. A reroof that loses the exemption, most often because sheathing or structure is being replaced, is a building permit priced from the one- and two-family valuation table in Sec. 18-20(b)(2): $52.00 up to $1,000.00 of valuation, $58.00 from $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. Sec. 18-20(e)(2) triples the fee if the work starts before the permit issues, with a carve-out where the work is done at a one-family dwelling by the person who owns and occupies it and the permit is applied for before the end of the workday following notification.
- Greensboro, North Carolina By valuation
The schedule's wording
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'
- Mecklenburg County, North Carolina Per unit
The schedule's wording
Building permit priced off total construction permit value: $59.70 for $1 to $3,000 on projects not requiring plan review, then $59.70 plus $12.19 per $1,000 or part over $3,000 up to $50,000. The fee is the greater of that schedule or Note a, which charges projects under $100,000 and all renovation/alteration projects $79.61 per trade plus $.12 per square foot for the building trade and $.08 per square foot for each electrical, mechanical or plumbing trade involved. A $3.00 technology charge is added to every permit, per the LUESA Fee Ordinance revised July 1, 2026.
- Cobb County, Georgia By valuation
The schedule's wording
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; re-roofs have no separate residential fee line, per the 2024 Fee Schedule effective 7/1/2024
- Gwinnett County, Georgia By valuation
The schedule's wording
Planning and Development Fee Schedule, "Building Permit Fees (Effective August 25, 2026)". The schedule has no line naming roof replacement. Its Other Building Permit Fees are $125 for a Residential Renovation Permit on Minor Renovation Projects (valued less than $75,000) and $4 per $1,000 of construction value on Extensive Renovation Projects (valued at $75,000 or greater); it does not say whether a re-roof is priced as a renovation. Confirm the amount with the Permits Section at 678-518-6020.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Providence, Rhode Island By valuation
The schedule's wording
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule.
- Charlotte County, Florida By valuation
The schedule's wording
At application: building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) plus a 0.025 x building-fee surcharge; no flat fee is listed for roof permits, unlike most other residential permit types.
- St. Johns County, Florida By valuation
The schedule's wording
No re-roof-specific fee line item is published. Roof replacement permits fall under the general Building Services Fees table: Permit Issuance Fee $14.00, plus Total Valuation of Building fee (minimum $19.00, or $11.00 for the first $1,000 plus $2.63 for each additional thousand up to $50,000; higher tiers apply above that), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026).
Plus 150 more localities with a verified note, each on its own permit page. Browse every roof replacement page
Shed permit fees
Verified in 168 localities. Dollar figures appearing in those schedules run from $0.01 to $1,000,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- New Castle County, Delaware By valuation
The schedule's wording
Building permit fees per the Deck and Swimming Pool requirement sheets (rev. 11/04/2025): "Building Permit Fee: $12 per $1,000 of Valuation ($142 Minimum)", Certificate of Occupancy $60, Zoning Permit Fee 10% of Building Permit Fee ($21 minimum, $145 maximum), NCC Volunteer Fire Assistance Fund Fee 0.5% of valuation, and a $65 Floodplain/Wetland review fee where applicable. The Chapter 6 Schedule of Permit and Review Fees (as amended through January 1, 2026) sets the valuation fee at $12.00 per $1,000 up to $1,000,000 with a $60.00 minimum; the $142 figure is the combined minimum the Estimated Building Permit Fee Form states.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Fargo, North Dakota By valuation
The schedule's wording
Residential Building Permit Fees (one- and two-family dwellings), effective January 1, 2026, by total valuation: up to and including $1,000.00, $50.00; $1,001.00 to $100,000.00, $50.00 for the first $1,000.00 plus $5.56 for each additional $1,000.00 or fraction thereof; $100,001.00 and up, $600.44 for the first $100,000.00 plus $3.06 for each additional $1,000.00. Work begun before the permit: permit fee doubled for $0 to $50,000 of valuation.
- Kansas City, Missouri By valuation
The schedule's wording
A shed that needs a permit is a general building permit priced from the one- and two-family valuation table in Sec. 18-20(b)(2) of the Code of Ordinances: $52.00 for total valuation of $0.00 to $1,000.00, $58.00 for $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00, and above $100,000.00 $483.00 for the first $100,000.00 plus $1.41 for each additional $1,000.00. Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22. There is no separate construction document review fee on one- and two-family work: Sec. 18-20(c)(1) charges that only "For other than one- and two-family dwellings." Optional add-ons are a $80.00 fast track permit fee under Sec. 18-20(b)(8) and a $30.00 scheduled express review fee for one- and two-family dwellings under Sec. 18-20(c)(4). Starting work before the permit is issued triples the fee under Sec. 18-20(e)(2).
- Newark, New Jersey By valuation
The schedule's wording
No shed-specific line in Newark municipal code Chapter 7:2-3.1 (Ord. 6 S+FD, 9-5-2007). Where a permit is required, building work is priced as 'Building Renovation and Alteration' at $28 per $1,000 of estimated cost of construction between $0 and $50,000 (then $21 per $1,000 to $100,000, $17 per $1,000 above that), or at $0.03 per cubic foot for a new residential structure, subject to the 'Minimum Building Permit: $58.' The $58 non-refundable processing fee is credited against the total.
- Greensboro, North Carolina By valuation
The schedule's wording
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'
- Rochester, New York By valuation
The schedule's wording
Building Permit Fees are based on the actual cost of work: $75.00 for $0 to $2,000, $110.00 for $2,001 to $4,000, $145.00 for $4,001 to $6,000, rising in steps to $985.00 for $58,001 to $60,000. The fee page carries the notice "Fees for licenses, building, electrical, and plumbing permits, as well as for certificates of occupancy, will change effective July 1, 2026." No separate shed line item is published.
- Providence, Rhode Island By valuation
The schedule's wording
Zoning certificate for compliance: $25.00 (Zoning Ordinance: "The fee for a zoning certificate and for a zoning certificate for compliance is $25.00."). Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule.
- Anchorage, Alaska By valuation
The schedule's wording
No item-specific fee. Residential work is priced under AMC 23.10.109 Table 3-A item 2, "Residential Construction (new construction, additions, alterations, and repairs)": "Up to $50,000 (Repairs, decks, and minor alterations only)" $350 with 4 inspections, "All others" $0.009 * (Valuation), minimum $450; plus Table 3-B residential plan review ("Regular Plan Review" 0.005 *(Valuation), minimum $75; land use plan review 15% of the Table 3-A fee, minimum $75) and a $50 digital maintenance fee (Table 3-A item 4.B). Anchorage Municipal Code (AMC) Title 23 as repealed and re-enacted by AO No. 2026-33, As Amended (approved April 14, 2026; the Codes page lists an effective date of 05/18/2026).
- San Francisco, California By valuation
The schedule's wording
Building permit fees are valuation-based under Table 1A-A Building Permit Fees ("July 2026", applying "to all building permits issued on and after July 12, 2026"): "The Building Permit Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to $2,000 the plan review fee is "$181 for the first $500 plus $8.60 for each additional $100 or fraction thereof" and the permit issuance fee is "$206 for the first $500 plus $4 for each additional $100 or fraction thereof"; for $2,001 to $50,000 they are "$310 for the first $2,000 plus $28.35" and "$266 for the first $2,000 plus $8.56" for each additional $1,000.
- Charlotte County, Florida By valuation
The schedule's wording
At application: flat fee $90, plus a 0.025 x building-fee surcharge and a $22 zoning flat fee; at issuance: building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a $90 Right-of-Way Review fee.
- St. Johns County, Florida By valuation
The schedule's wording
No shed or accessory-structure-specific fee line item is published. Shed permits fall under the general Building Services Fees table: Permit Issuance Fee $14.00, plus Total Valuation of Building fee (minimum $19.00, or $11.00 for the first $1,000 plus $2.63 for each additional thousand up to $50,000; higher tiers apply above that), per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 07/21/2026).
Plus 156 more localities with a verified note, each on its own permit page. Browse every shed page
Solar permit fees
Verified in 167 localities. Dollar figures appearing in those schedules run from $0.00 to $300,000, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- Osceola County, Florida By valuation
The schedule's wording
Appendix A states 'The following permit fees will apply to residential and commercial solar permits' immediately before its Valuation Table: up to $5,000.00 in valuation costs $85.00; $5,000.00 and over costs $150.00 plus $3.25 per thousand dollars (or fraction) over $5,000.00, capped at a $300,000.00 maximum permit fee. Separately, a re-roof combined with solar panel removal/replacement or solar shingles is billed at a flat $150.00 permit fee under the re-roofing fee lines. Effective October 1, 2025, per Resolution #25-036R.
- Sussex County, Delaware Per unit
The schedule's wording
Sussex County Building Permit Fee Guide: construction value (table rates such as $128.10/sq ft residential, $52.23/sq ft garage or pole building, $23.36/sq ft unfinished area such as a deck, porch or shed, or actual value if not listed); building permit fee for property outside town limits is $5.00 for the first $1,000 of construction value and $2.50 for each additional $1,000; plus a Fire District Fee of .0015 of construction value; plus a School Surcharge of $5.00 per $1,000 on permits with a construction value of $150,000 or above. Where the Building Code Office reviews and inspects, a separate plan review and inspection fee applies (schedule effective July 1, 2026): Residential Projects under 1,000 SF $120 base covering 5 inspections, $60 per inspection after the initial 5.
- Kansas City, Missouri By valuation
The schedule's wording
Each trade permit is priced from the one- and two-family valuation table in Sec. 18-20(b)(2), which covers building, mechanical, plumbing and electrical permits alike: $52.00 up to $1,000.00 of valuation, $58.00 from $1,001.00 to $2,000.00, then $58.00 for the first $2,000.00 plus $4.33 for each additional $1,000.00 or fraction thereof to and including $100,000.00, and $483.00 for the first $100,000.00 plus $1.41 per additional $1,000.00 above that. Information Bulletin IB162 requires the declared valuation to include the entire scope of the project, including the solar panels themselves. The scheduled express review option adds $30.00 for one- and two-family dwellings under Sec. 18-20(c)(4). Sec. 18-20 was last amended by Ord. No. 220612, Sec. 1, 10-27-22.
- Charlotte, North Carolina By valuation
The schedule's wording
Solar has no dedicated line item. The permit is charged off total construction permit value under the LUESA Fee Ordinance (revised July 1, 2026), where $3,001 to $50,000 is '$59.70 plus $12.19 per $1,000 or part over $3,000' and $50,001 to $100,000 is '$632.57 plus $5.49 per $1,000 or part over $50,000', plus a $3.00 technology charge on all permits. A ground-mounted or pole-mounted array that needs the City of Charlotte LDIRL pays $70 Residential Zoning under the FY 2025 Individual Residential Lot Fee Schedule, effective for projects submitted July 1, 2024 to June 30, 2025, plus any Urban Forestry tree preservation tier of $75, $225 or $375.
- Greensboro, North Carolina By valuation
The schedule's wording
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.' The Electrical Permit Fee Schedule, Document #4100 dated 7/16/24, has no solar line item; it prices the work through 'Minimum Permit Fee 85.00', 'Panel 10.00 ea.' and the amp-rated service lines ('200 Amp. Service 99.00 ea.').
- Mecklenburg County, North Carolina Per unit
The schedule's wording
No solar-specific line in the fee ordinance; permits are priced off total construction permit value: $59.70 for $1 to $3,000 on projects not requiring plan review, then $59.70 plus $12.19 per $1,000 or part over $3,000 up to $50,000. The fee is the greater of that schedule or Note a, which charges projects under $100,000 and all renovation/alteration projects $79.61 per trade plus $.12 per square foot for the building trade and $.08 per square foot for each electrical, mechanical or plumbing trade involved. A $3.00 technology charge is added to every permit, per the LUESA Fee Ordinance revised July 1, 2026.
- Cobb County, Georgia By valuation
The schedule's wording
Fee follows the small residential construction cost table, $80 base for cost up to $15,000 rising by tier to $450 (or $6 per $1,000 above $75,001), plus a $15 technology fee; the solar application requires a cost estimate and no separate solar fee line exists, per the 2024 Fee Schedule effective 7/1/2024
- Gwinnett County, Georgia By valuation
The schedule's wording
Planning and Development Fee Schedule, "Building Permit Fees (Effective August 25, 2026)". The schedule sets no separate solar price; it grants a discount: "There will be a 5% Building Permit Fee reduction for the installation of the following: - Solar panel installations for nonresidential and residential buildings". It does not say which building permit fee a solar installation is charged. Its Other Building Permit Fees are $125 for a Residential Renovation Permit on Minor Renovation Projects (valued less than $75,000) and $4 per $1,000 of construction value on Extensive Renovation Projects (valued at $75,000 or greater). Confirm the amount with the Permits Section at 678-518-6020.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Providence, Rhode Island By valuation
The schedule's wording
Building permit fee by project valuation, from the City of Providence schedule in the state fee rule 510-RICR-00-00-21, section 21.12(A)(28) (amendment effective 12/10/2023): "$1 to $10,000": $23.00 per $1,000; "From $10,001 to $50,000": "$230 +" $21.00 "per $1,000 exceeding $10k"; "From $50,001 to no limit": "$1070 +" $19.00 "per $1,000 exceeding $50k"; "Note: $125 minimum fee". The rule says these fees are exclusive of the state levy under R.I. Gen. Laws 23-27.3-108.2(c)(1). The City's own Permit Fee Calculator (FY19, dated 2018-07-18) uses the same rates but a $50.00 minimum and adds an ADA fee of 0.1 percent of cost; the state rule is the later and governing schedule. The checklist adds: "If the project has a construction cost exceeding $50,000.00, DIS requests 1/3 of the permit fee at the time of application, with balance due at time of issuance."
- Charlotte County, Florida By valuation
The schedule's wording
At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge.
- Ann Arbor, Michigan By valuation
The schedule's wording
For expedited residential solar the Solar Photovoltaic (PV) System Permitting Checklist shows the electric permit basic application fee WAIVED, residential solar panels $0.00, and inspection $35.00 if applicable, with no building permit. Electrical Permit Fees (effective January 2020) confirm the residential line "Solar Panels per set of 3 panels ... $0". Non expedited residential and commercial solar also pays a building permit under the Building Permit Fees schedule (revised 7/15/2025) flat solar scale: estimated cost $0 to $10,000 is a $37.50 plan examination fee plus a $150 permit fee; $10,001 to $50,000 is $75 plus $200; over $50,000 is $100 plus $400. The building plan examination fee of 20% expressly excludes solar permits.
Plus 155 more localities with a verified note, each on its own permit page. Browse every solar page
Water Heater permit fees
Verified in 54 localities. Dollar figures appearing in those schedules run from $0.01 to $50,001, and the two ends are rarely for the same thing: minimum permit fees, flat per-trade rates, plan-review percentages, and valuation tiers all appear below exactly as each schedule states them.
- Hawaii County, Hawaii By valuation
The schedule's wording
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
- Providence, Rhode Island By valuation
The schedule's wording
Trade permit fee by project valuation. The statewide fee rule (510-RICR-00-00-21) defines building permit fees by reference to R.I. Gen. Laws 23-27.3-118 and 118.1, and 118.1 names electrical and plumbing permits among them; Providence's schedule there (section 21.12(A)(28), effective 12/10/2023) is $23.00 per $1,000 up to $10,000, $230 + $21.00 per $1,000 exceeding $10k up to $50,000, $1070 + $19.00 per $1,000 exceeding $50k above that, with a $125 minimum fee, exclusive of the state levy. The City's FAQ points to one Permit Fee Calculator for "Building, Plumbing, Mechanical" permits, which applies the same rates.
- Cheyenne, Wyoming By valuation
The schedule's wording
Valuation-based, from the City of Cheyenne Building and Construction Permit Fees table in City Code 15.08.030 (effective January 30, 2023, Ord. No. 4485): $1.00 to $500.00 is $23.50; $501.00 to $2,000.00 is $23.50 for the first $500.00 plus $3.05 for each additional $100.00; $2,001.00 to $25,000.00 is $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00; $25,001.00 to $50,000.00 is $391.75 for the first $25,000.00 plus $10.10 for each additional $1,000.00 (higher tiers continue). Plan review, when submittal documents are required, is 65 percent of the permit fee and is in addition to it. Reinspection fee $250.00. Work begun before the permit is issued carries an investigation fee equal to the permit fee (IRC R108.6 as amended by 15.10.020(H)).
- Martin County, Florida By valuation
The schedule's wording
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75.
- Honolulu, Hawaii By valuation
The schedule's wording
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
- Overland Park, Kansas By valuation
The schedule's wording
Development Approval and Permit Fees, effective 08/01/2025: for a Building Permit with work value of $19,000 or less, a Flat Building Permit Fee of $30 ($1 - $5,000) or $50 ($5,001 - $19,000) plus a Flat Plan Review Fee of $30, "for a Total Plan Review and Permit Fee of $60 for work valued at $1 - $5,000 and $80 for work valued at $5,001 - $19,000"; above $19,000, Fee = Valuation x Permit Fee Multiplier (0.0050).
- Sioux Falls, South Dakota By valuation
The schedule's wording
Plumbing permit, Table 104.5 (Code of Ordinances 150.302): $40 for "$0.01 to $5,000.00" of plumbing valuation; "Homeowner s permit." $25.
- Henrico County, Virginia By valuation
The schedule's wording
No water-heater-specific fee; a mechanical or plumbing permit on an existing one- or two-family dwelling is $100 for the first $5,000 of estimated cost plus $6 per additional $1,000 or fraction thereof, plus the 2% state levy, per Henrico's Mechanical Permit and Plumbing Permit pages
- Miami, Florida By valuation
The schedule's wording
Residential (up to 3 units) building, plumbing, mechanical and electrical permits: 0.50% of estimated construction cost; "Residential less than estimated $2,500.00": $45.00; "Minimum Permit Fee": $110.00; "All Permits non-refundable application fee": $40.00; "Dry run/Up-Front per $1,000.00 of estimated construction value": $2.80 (no up-front fee on residential work under $2,500); "Solid Waste Residential Surcharge" $0.22 per $100.00 of estimated cost (minimum $26.00, maximum $600.00). State and Miami-Dade County surcharges are extra. Exhibit C Fee Schedule, Building, Chapters 10, 17, 20, adopted by Resolution R-26-0200 (Ordinance 14456), April 23, 2026.
- Birmingham, Alabama By valuation
The schedule's wording
Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "PLUMBING PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2). The Plumbing Permit Application fee worksheet lists "Hot Water Heater - Electrical" and "Hot Water Heater - Gas"; the Gas Permit Application lists "Water Heater (Gas or Electric)". Gas permit: $9.50 per $1,000.00 valuation, minimum $125.00.
- Stamford, Connecticut By valuation
The schedule's wording
"Residential Electrical, plumbing, HVAC": "$13.00 per $1000 of construction value", minimum $60.00, plus $0.26 per $1,000 State Education Fund fee (City Building Permit Fees page; no effective date printed).
- New Castle County, Delaware By valuation
The schedule's wording
Mechanical or Plumbing Permit (Chapter 6 Schedule of Permit and Review Fees, as amended through January 1, 2026): $5.25 for the first $1,000 valuation or any part thereof, $5.25 for each additional $1,000 or part thereof, minimum fee $65.00.
Plus 42 more localities with a verified note, each on its own permit page. Browse every water heater page
Methodology
Every fee note above was written while reading the locality's current official fee schedule and was reviewed against a quoted line of that schedule before it entered the dataset, with the date recorded. Notes repeat the schedule's own billing basis (flat fee, valuation tier, plan review percentage) rather than reducing everything to one number.
Honest gaps stay gaps: a few localities publish no usable schedule (some block archives, some publish none for certain trades), and some permits are issued by a state agency instead of the locality. Those rows say exactly that.
The measured medians come from official open-data portals and are computed from real issued permits. Sample sizes are shown; medians are used throughout. Read more about the process on how we verify.
What will your project need?
Answer three questions and get the verified requirements, fees, and office links for your locality.