Georgia / Gwinnett County

Solar Permit in Gwinnett County, Georgia

Permit required

Yes, a permit is required

Before installing a rooftop or ground-mounted solar photovoltaic system at a house.

Confirmed on official page Verified Gwinnett County Department of Planning and Development, Building Division

By Mario Bailey, verified against official sources

Quick answer

A residential solar photovoltaic installation is the installation of an electrical system, so Gwinnett County Construction Code section 106.1 requires a permit before the work starts, and no solar exemption appears in the section 106.4 exempt-work list. The county's current fee schedule confirms the permit exists by discounting it, giving a 5 percent building permit fee reduction for solar panel installations on residential and nonresidential buildings. Gwinnett's weekly Building Permits Issued reports show these permits going out to solar contractors on single family houses with a type of work of "Electrical Only".

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing a rooftop or ground-mounted solar photovoltaic system at a house.

What a solar permit costs in Gwinnett County

Line item
solar permitBy formulaPlanning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". The schedule grants a discount rather than setting a separate solar price: "Green Building Credit [...] There will be a 5% Building Permit Fee reduction for the installation of the following: - Solar panel installations for nonresidential and residential buildings - EV charger unit installations for nonresidential and residential developments". The underlying permit is priced from the Other Building Permit Fees table, where "Minor Renovation Projects (valued less than $75,000) | Residential Renovation Permit | $125".
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Gwinnett County compares in Georgia

No Georgia jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
AtlantaPermit requiredNot published
Cobb CountyPermit requiredFee follows the small residential construction cost table, $80 base for cost...
DeKalb CountyPermit requiredBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245...
Gwinnett Countythis pagePermit requiredPlanning and Development Fee Schedule, "Building Permit Fees (Effective July...

How to apply in Gwinnett County

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Gwinnett County Department of Planning and Development, Building Division sets the exact checklist for Gwinnett County.

Where to apply in Gwinnett County:

Gwinnett County Department of Planning and Development, Building Division

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Gwinnett County permit portal or by phone at 678-518-6020.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Gwinnett County?
A residential solar photovoltaic installation is the installation of an electrical system, so Gwinnett County Construction Code section 106.1 requires a permit before the work starts, and no solar exemption appears in the section 106.4 exempt-work list. The county's current fee schedule confirms the permit exists by discounting it, giving a 5 percent building permit fee reduction for solar panel installations on residential and nonresidential buildings. Gwinnett's weekly Building Permits Issued reports show these permits going out to solar contractors on single family houses with a type of work of "Electrical Only". Always confirm with the Gwinnett County Department of Planning and Development, Building Division before starting.
How much does a solar permit cost in Gwinnett County?
Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". The schedule grants a discount rather than setting a separate solar price: "Green Building Credit [...] There will be a 5% Building Permit Fee reduction for the installation of the following: - Solar panel installations for nonresidential and residential buildings - EV charger unit installations for nonresidential and residential developments". The underlying permit is priced from the Other Building Permit Fees table, where "Minor Renovation Projects (valued less than $75,000) | Residential Renovation Permit | $125". See the official fee schedule for current amounts.
Where do you apply for a solar permit in Gwinnett County?
You can apply through the Gwinnett County permit portal or contact the Gwinnett County Department of Planning and Development, Building Division directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Gwinnett County?
Under Georgia law (O.C.G.A. 43-41-17(h); O.C.G.A. 43-14-13(d); O.C.G.A. 43-14-14): Georgia's contractor licensing law has a true owner builder exemption at O.C.G.A. 43-41-17(h), not 43-41-17(b). A property owner may construct a building on land the owner owns and act as his or her own contractor, personally providing direct supervision and management, but only if the finished building is intended solely for occupancy by the owner and the owner's family, firm, or corporation, is not for use by the general public, and is not offered for sale or lease. If the owner sold or transferred a self-built structure within the prior 24 months, measured from that structure's certificate of occupancy, the law presumes the new project was not really for personal occupancy and the exemption is unavailable without a license. The owner may not delegate supervision to any unlicensed person, and all work must still comply with county or municipal permitting and inspection requirements. For trade work, O.C.G.A. 43-14-13(d) separately allows an individual to install, alter, or repair plumbing, heating and air conditioning fixtures, and electrical or low-voltage wiring in a residential dwelling the individual owns or occupies, again in conformity with the codes and any local permit and inspection rules. Unlicensed trade work outside these exemptions is a misdemeanor punishable by up to a $1,000 fine or six months imprisonment or both (O.C.G.A. 43-14-14). Confirm how Gwinnett County applies this before you apply.

From the Library

What else needs a permit in Gwinnett County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024", for every permit type below. The fee column shows what differs by project.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specified"Other Building Permit Fees: Minor Renovation Projects (valued less than $75,000) |...
Electrical PermitIt dependsNot specifiedThe schedule has no separate electrical trade permit line
Fence PermitIt dependsheight of a fence; masonry and concrete fence walls follow a separate 4 foot limitThe schedule publishes no fence line item.
HVAC PermitIt dependsNot specifiedThe schedule has no separate mechanical trade permit line
Plumbing PermitIt dependsNot specifiedThe schedule has no separate plumbing trade permit line
Pool PermitIt dependsprefabricated pools installed entirely above ground that also hold no more than 5,000 gallonsThe schedule publishes no swimming pool line item.
Roof Replacement PermitPermit requiredNot specified"Other Building Permit Fees: Minor Renovation Projects (valued less than $75,000) |...
Shed PermitIt dependsfloor area of a one-story detached accessory structure that contains no electrical or plumbing systemThe schedule has no accessory-building line item

Solar Permit in other Georgia localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Gwinnett County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Gwinnett County Department of Planning and Development, Building Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Solar Permit requirements across Georgia localities

Look up an existing Gwinnett County permit record

Permit required
Get quotes