Shed Permit in Gwinnett County, Georgia
It depends
Sometimes, depending on the project
Before erecting a storage building, shed or detached garage larger than 120 square feet, and before any land disturbance for it.
By Mario Bailey, verified against official sources
Quick answer
A detached storage building of 120 square feet or less needs no building permit in unincorporated Gwinnett, but the size exemption falls away if the structure has power or water: the county's Code Enforcement sheet states that a building permit is required regardless of size if the proposed structure contains electrical or plumbing systems. Anything larger than 120 square feet needs a permit and an approved "Accessory Building Location Plan", plus Gwinnett Environmental Health approval first if the home is on a septic system. Separately from permitting, Unified Development Ordinance Table 230.2 caps how big an accessory building may be at all: on a lot under 10,500 square feet the maximum without a variance is 120 square feet, rising to 500 square feet on lots up to 0.99 acre and 650 square feet on lots of 1.00 to 2.99 acres.
Typical threshold: floor area of a one-story detached accessory structure that contains no electrical or plumbing system.

Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before erecting a storage building, shed or detached garage larger than 120 square feet, and before any land disturbance for it.
What a shed permit costs in Gwinnett County
How Gwinnett County compares in Georgia
No Georgia jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Atlanta | Permit required | Not published |
| Cobb County | Permit required | Accessory structures are subject to a $100 site plan review fee in addition to... |
| DeKalb County | Permit required | Building Permit Application (revised 01/01/2025): "Total Minimum Fees $245... |
| Gwinnett Countythis page | It depends | Planning and Development Fee Schedule, "Building Permit Fees (Effective July... |
Closest shed permit thresholds outside Georgia
Jurisdictions we cover whose limit sits nearest Gwinnett County's 120 sq ft.
- Alameda County, California, Floor area of a one-story detached tool or storage shed accessory to a house, at which the building permit exemption stops
- Aurora, Colorado, shed floor area at which a building permit is required
- Baltimore County, Maryland, accessory structure floor area
- Boston, Massachusetts, one-story detached accessory sheds used for tools or storage are exempt if floor area does not exceed 120 sq ft
How to apply in Gwinnett County
A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.
What most shed permit applications include:
- A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
- A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
- Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
- Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
- Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).
General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Gwinnett County Department of Planning and Development, Building Division sets the exact checklist for Gwinnett County.
Where to apply in Gwinnett County:
Gwinnett County Department of Planning and Development, Building Division
- Innovation Square, 446 West Crogan Street, Suite 300, Lawrenceville, GA 30046
- Phone: 678-518-6020
- Email: P&D-BuildingPermits@GwinnettCounty.com
Inspections and closing out your permit
A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.
- Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
- Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
- Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
- For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Gwinnett County permit portal or by phone at 678-518-6020.
Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Shed Permit checklist for Gwinnett County
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: floor area of a one-story detached accessory structure that contains no electrical or plumbing system. Usually needed: Before erecting a storage building, shed or detached garage larger than 120 square feet, and before any land disturbance for it.
- Budget the fee. Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". The schedule has no accessory-building line item; the department's "Regulatory Requirements for Residential Permits" lists "Accessory Bldgs" as needing an Application plus a Site Plan authorized by Plan Review. Caution on figures: the department's older undated handout "Regulatory Requirements for Residential Permits" still prices this work at "$0.006 x Value of Construction" and the 2012-era step sheets at "$6 per $1,000 of estimated construction cost (minimum fee is $30)", both of which predate the July 1, 2024 schedule. Confirm the current amount with the Permits Section at 678-518-6020 before budgeting. Official fee schedule.
- Apply. A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing. Start at the Gwinnett County permit portal.
- Keep the office details handy. Gwinnett County Department of Planning and Development, Building Division. Phone: 678-518-6020. Address: Innovation Square, 446 West Crogan Street, Suite 300, Lawrenceville, GA 30046.
- Plan for inspections. A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a shed permit in Gwinnett County?
- A detached storage building of 120 square feet or less needs no building permit in unincorporated Gwinnett, but the size exemption falls away if the structure has power or water: the county's Code Enforcement sheet states that a building permit is required regardless of size if the proposed structure contains electrical or plumbing systems. Anything larger than 120 square feet needs a permit and an approved "Accessory Building Location Plan", plus Gwinnett Environmental Health approval first if the home is on a septic system. Separately from permitting, Unified Development Ordinance Table 230.2 caps how big an accessory building may be at all: on a lot under 10,500 square feet the maximum without a variance is 120 square feet, rising to 500 square feet on lots up to 0.99 acre and 650 square feet on lots of 1.00 to 2.99 acres. Floor area of a one-story detached accessory structure that contains no electrical or plumbing system. Always confirm with the office before starting.
- How much does a shed permit cost in Gwinnett County?
- Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". The schedule has no accessory-building line item; the department's "Regulatory Requirements for Residential Permits" lists "Accessory Bldgs" as needing an Application plus a Site Plan authorized by Plan Review. Caution on figures: the department's older undated handout "Regulatory Requirements for Residential Permits" still prices this work at "$0.006 x Value of Construction" and the 2012-era step sheets at "$6 per $1,000 of estimated construction cost (minimum fee is $30)", both of which predate the July 1, 2024 schedule. Confirm the current amount with the Permits Section at 678-518-6020 before budgeting. See the official fee schedule for current amounts.
- Where do you apply for a shed permit in Gwinnett County?
- You can apply through the Gwinnett County permit portal or contact the Gwinnett County Department of Planning and Development, Building Division directly. The links are listed on this page.
- Can a homeowner pull a shed permit themselves in Gwinnett County?
- Under Georgia law (O.C.G.A. 43-41-17(h); O.C.G.A. 43-14-13(d); O.C.G.A. 43-14-14): Georgia's contractor licensing law has a true owner builder exemption at O.C.G.A. 43-41-17(h), not 43-41-17(b). A property owner may construct a building on land the owner owns and act as his or her own contractor, personally providing direct supervision and management, but only if the finished building is intended solely for occupancy by the owner and the owner's family, firm, or corporation, is not for use by the general public, and is not offered for sale or lease. If the owner sold or transferred a self-built structure within the prior 24 months, measured from that structure's certificate of occupancy, the law presumes the new project was not really for personal occupancy and the exemption is unavailable without a license. The owner may not delegate supervision to any unlicensed person, and all work must still comply with county or municipal permitting and inspection requirements. For trade work, O.C.G.A. 43-14-13(d) separately allows an individual to install, alter, or repair plumbing, heating and air conditioning fixtures, and electrical or low-voltage wiring in a residential dwelling the individual owns or occupies, again in conformity with the codes and any local permit and inspection rules. Unlicensed trade work outside these exemptions is a misdemeanor punishable by up to a $1,000 fine or six months imprisonment or both (O.C.G.A. 43-14-14). Confirm how Gwinnett County applies this before you apply.
From the Library
What else needs a permit in Gwinnett County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024", for every permit type below. The fee column shows what differs by project.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Not specified | "Other Building Permit Fees: Minor Renovation Projects (valued less than $75,000) |... |
| Electrical Permit | It depends | Not specified | The schedule has no separate electrical trade permit line |
| Fence Permit | It depends | height of a fence; masonry and concrete fence walls follow a separate 4 foot limit | The schedule publishes no fence line item. |
| HVAC Permit | It depends | Not specified | The schedule has no separate mechanical trade permit line |
| Plumbing Permit | It depends | Not specified | The schedule has no separate plumbing trade permit line |
| Pool Permit | It depends | prefabricated pools installed entirely above ground that also hold no more than 5,000 gallons | The schedule publishes no swimming pool line item. |
| Roof Replacement Permit | Permit required | Not specified | "Other Building Permit Fees: Minor Renovation Projects (valued less than $75,000) |... |
| Solar Permit | Permit required | Not specified | The schedule grants a discount rather than setting a separate solar price: "Green... |
Shed Permit in other Georgia localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Gwinnett County documents; the office above sets the local rules.
- IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC
- IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC
Verified by a person against the sources above on , not confirmed with Gwinnett County Department of Planning and Development, Building Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Permit office
Gwinnett County Department of Planning and Development, Building Division
678-518-6020Permit portalCompare