Do you need a plumbing permit?
By Mario Bailey Last checked
It depends entirely on where you live, and the differences are larger than most national guides admit. We read the code, ordinance, or fee schedule published by each of 137 US counties and cities and recorded what it actually says.
Where are you building?
The rule is set locally and the spread is wide, so start with your own jurisdiction. We have read the published rule in 137 of them.
The short answer
Of the 137 jurisdictions where we have confirmed the rule, 100 require a permit outright, 37 require one only in certain conditions.
The most common published threshold is 20 linear feet, used by 1 of the 1 jurisdictions that state a threshold in linear feet. That leaves 0 of them on a different number, which is why a national rule of thumb is not a safe answer for your own address.
The size thresholds, and how much they disagree
2 of the 137 jurisdictions publish a specific number.
Measured in linear feet (1 jurisdiction)
| Threshold | Jurisdictions | Where |
|---|---|---|
| 20 linear feet | 1 | Buffalo |
Measured in percent (1 jurisdiction)
| Threshold | Jurisdictions | Where |
|---|---|---|
| 20 percent | 1 | Indianapolis |
Thresholds are recorded as the jurisdiction states them. Which side of the number triggers the permit varies, so read your own locality's page before relying on one.
What a plumbing permit costs
131 of our plumbing permit rows carry a fee answer taken from the jurisdiction's own published schedule, across 131 localities. There is no single number to quote, and not because we did not look: jurisdictions price this permit in genuinely different ways. Some charge a flat fee, some a percentage of the job's assessed valuation, some a rate per square foot, and some do not price it at all because the work is permitted by a state agency or a utility instead. Each row below is that jurisdiction's own wording.
| Locality | What the schedule says |
|---|---|
| Kansas City Missouri | Plumbing permits for one- and two-family detached dwellings use the Sec. |
| Gwinnett County Georgia | Planning and Development Fee Schedule, "Building Permit Fees (Effective July 1, 2024)", footer "Revised 05/23/2024". |
| Charlotte County Florida | At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a... |
| Charlotte North Carolina | Plumbing is charged as a trade permit under the LUESA Fee Ordinance (revised July 1, 2026): $1 to $3,000 in total... |
| New York City New York | Limited Alteration Application is the usual homeowner-scale route. |
| St. Louis Missouri | Plumbing permit fees are established by City Ordinance 71644. |
| Milwaukee Wisconsin | Plumbing permit fees are set by MCO 200-33 and are not reproduced in the Plan Review and Permit Fees schedule, which... |
| Mesa Arizona | A stand-alone plumbing permit is valuation based via the Residential Rate Table, $220 minimum for the $0 to $8,333... |
| Columbia South Carolina | Plumbing work at a one or two family dwelling is priced under Code of Ordinances Sec. |
| Henrico County Virginia | Existing-dwelling trade permit fee applies: $100 for the first $5,000 of labor and materials cost, plus $6 per... |
| Collier County Florida | Fee Schedule (Resolution 2025-231, effective January 1, 2026), Plumbing and Gas Permit Review Fees: valuation up to... |
| Mecklenburg County North Carolina | Plumbing trade permit priced off total construction value with a $59.70 minimum for projects not requiring plan review... |
A sample of the schedule-verified rows. Full figures, sources, and dates are on each locality's page, and the whole fee study is at what building permits cost.
Plumbing Permit rules by state
27 states, 137 counties and cities. Pick your state for the locality-by-locality comparison, or go straight to your county.
| State | Localities | Required | Conditional | Not required | Thresholds published |
|---|---|---|---|---|---|
| Florida | 28 | 24 | 4 | 0 | None published |
| California uniform | 14 | 14 | 0 | 0 | None published |
| Virginia | 12 | 9 | 3 | 0 | None published |
| Texas uniform | 10 | 10 | 0 | 0 | None published |
| Arizona | 8 | 5 | 3 | 0 | None published |
| Washington | 8 | 7 | 1 | 0 | None published |
| New York | 5 | 1 | 4 | 0 | 20 linear feet |
| Georgia | 4 | 3 | 1 | 0 | None published |
| Maryland | 4 | 3 | 1 | 0 | None published |
| Michigan | 4 | 2 | 2 | 0 | None published |
| North Carolina | 4 | 1 | 3 | 0 | None published |
| Ohio | 4 | 3 | 1 | 0 | None published |
| Colorado | 3 | 2 | 1 | 0 | None published |
| Tennessee | 3 | 2 | 1 | 0 | None published |
| Illinois uniform | 2 | 2 | 0 | 0 | None published |
| Indiana uniform | 2 | 0 | 2 | 0 | 20 percent |
| Louisiana | 2 | 1 | 1 | 0 | None published |
| Massachusetts uniform | 2 | 2 | 0 | 0 | None published |
| Minnesota uniform | 2 | 2 | 0 | 0 | None published |
| Missouri uniform | 2 | 0 | 2 | 0 | None published |
| Nevada uniform | 2 | 2 | 0 | 0 | None published |
| New Jersey | 2 | 1 | 1 | 0 | None published |
| Oklahoma | 2 | 1 | 1 | 0 | None published |
| Oregon | 2 | 1 | 1 | 0 | None published |
| Pennsylvania uniform | 2 | 2 | 0 | 0 | None published |
| South Carolina uniform | 2 | 0 | 2 | 0 | None published |
| Wisconsin uniform | 2 | 0 | 2 | 0 | None published |
A state marked uniform applies the same verdict in every locality we checked there, usually because a statewide code forbids local divergence.
How plumbing permits work, start to finish
Applying
You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.
- A permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
- The application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
- Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
- Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
- Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).
Inspections and close-out
Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.
- Piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
- Rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
- Rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
- The water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
- The framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
- At the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
- Final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).
General practice; your locality's page carries its own process, fees, and portal. Sources: 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents, 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests.
Find the plumbing permit rule where you live
Look up your locality
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
Planning more than a plumbing permit? Check your whole project