Plumbing Permit in Town of Brookhaven, New York
It depends
Sometimes, depending on the project
Before any plumbing work other than minor repairs to an existing system, including new or altered gas piping, water heaters, generators, lawn sprinklers and pool heaters.
Quick answer
Zoning Sec. 85-12.B states that a building permit shall not be required for minor repairs to existing plumbing systems, which makes everything beyond a minor repair permit work. Brookhaven handles it through the standard building permit application plus a Plumbing Worksheet, which the application says is required if the project includes any type of plumbing work, along with a riser diagram for gas lines. The worksheet counts fixtures and must be signed by a plumber holding a Suffolk County Consumer Affairs license; an owner's signature is accepted only for an existing residential dwelling, and new construction must carry a plumber's signature.
- Typical threshold
- minor repairs to existing plumbing systems
- Issued by
- Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management
- Phone
- 631-451-8696
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Plumbing permits are usually pulled by the plumber doing the job. If you are still choosing one, compare a few quotes first.
Compare plumber quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
What a plumbing permit costs in Town of Brookhaven
- Fee schedule in force
- Official scheduleRead .
- Published in
- Town of Brookhaven Building Division Fee Schedule 2026, Construction table:
- plumbing fixtures are priced each, for example "Water Closet Fee $10/per", "Lavatory Fee $10/per", "Kitchen Sink Fee $10/per" and "Shower Fee $10/per", with "Residential Stack Fee $32/per" and "Gas Piping $80".
- The same table opens with "Application Fee $100";
- the schedule does not say whether it is added to each permit.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How Town of Brookhaven compares in New York
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Buffalo | It depends | repair or replacement of sections of the water distribution system totaling less than that length |
| New York City | It depends | direct replacement of an existing fixture or faucet that does not alter the hot and cold shutoff valves or the fixture trap |
| Rochester | It depends | Before replacing, repairing or altering water service, sewer, drain, waste, vent or... |
| Town of Brookhaventhis page | It depends | minor repairs to existing plumbing systems |
| Town of Hempstead | Permit required | Any size |
How to apply in Town of Brookhaven
General guide, not specific to this office
What a plumbing permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a plumbing permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management
- 1 Independence Hill, Farmingville, NY 11738
- Phone: 631-451-8696
Your Plumbing Permit checklist for Town of Brookhaven
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: minor repairs to existing plumbing systems. Read the rule where we read it: brookhavenny.gov: Building Division.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Town of Brookhaven permit portal.
- Keep the office details handy. Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management. Phone: 631-451-8696. Address: 1 Independence Hill, Farmingville, NY 11738.
Compiled from the official sources on this page. Last checked .
Permitting activity in Town of Brookhaven
In 2025, Town of Brookhaven authorized permits for 286 new residential housing units (266 single-family, 20 in multi-family buildings), valued at $94M, down from 514 the year before. That works out to about 0.6 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 479,883.
What else needs a permit in Town of Brookhaven
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | deck rising more than eight inches above grade at any point | Town of Brookhaven Building Division Fee Schedule 2026, Construction table: "Deck Fee $0.50/SF" |
| Electrical Permit | Permit required | Any size | It does list an "Electrical Transfer Switch Fee" of $90 for the first $1,000 of construction costs; the schedule has the rest |
| Fence Permit | It depends | fence taller than four feet in a secondary front yard on a corner lot or through lot | Town of Brookhaven Building Division Fee Schedule 2026, Construction table: "Fence Fee $1/LF" |
| HVAC Permit | It depends | installation of listed portable heating, ventilation or cooling equipment or appliances | Town of Brookhaven Building Division Fee Schedule 2026, Construction table: "CAC/HVAC Fee $160" and "Heating Unit Replacement Fee $135" |
| Patio Permit | It depends | patio rising more than eight inches above grade at any point | The same table opens with "Application Fee $100" |
| Pool Permit | It depends | pool structure extending more than 18 inches below grade, measuring how far the pool sits below grade and not the depth of the water, which is the code's test for an in-ground pool | Town of Brookhaven Building Division Fee Schedule 2026, Construction table: "Inground Pool Fee $260" and "Above Ground Pool / Hot Tub Fee $135" |
| Roof Replacement Permit | It depends | repair work that has no impact on fire and life safety, meaning no impact on the structural system, the required means of egress, or the fire protection system | It lists a "Roof Over Fee" of $90 for the first $1,000 of construction costs, plus $10 for every additional $1,000 thereafter; the schedule has the rest |
| Shed Permit | It depends | detached one-story storage shed larger than 144 square feet, or any shed not located in the rear yard | Town of Brookhaven Building Division Fee Schedule 2026, Construction table: "Shed Fee $200" |
| Solar Permit | Permit required | Any size | Town of Brookhaven Building Division Fee Schedule 2026, Construction table: "Solar Panel (Residential) $135" |
Frequently asked questions
- Do you need a plumbing permit in Town of Brookhaven?
- It depends on the project. Minor repairs to existing plumbing systems. If you are unsure how that applies to your project, call the permit office at 631-451-8696 before you start.
- How much does a plumbing permit cost in Town of Brookhaven?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 11 Nov 2026. For the figure on your own project, call the permit office at 631-451-8696.
- Where do you apply for a plumbing permit in Town of Brookhaven?
- You can apply through the Town of Brookhaven permit portal or contact the Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management directly. The links are listed on this page.
- Can a homeowner pull a plumbing permit themselves in Town of Brookhaven?
- Under New York law (Inside New York City: NYC Admin. Code 28-104.1, 28-105.1, 28-105.4, 28-105.5.1, 28-401.3 (definition of "general contractor"). Outside New York City: N.Y. Exec. Law 381(2); 19 NYCRR 1203.3(a)(1).): New York State sets no owner-builder rule at all outside New York City. Executive Law 381(2) puts administration and enforcement in the hands of each local government, and 19 NYCRR 1203.3(a)(1) only requires each authority having jurisdiction to make building permits mandatory for work that must conform to the codes, leaving who may apply to local law. The state licenses no general contractors and imposes no owner-builder affidavit, disclosure form or post-permit sale restriction of the kind Florida uses, so whether a homeowner may pull the permit is a question for the specific city, town, village or county. New York City is the genuine outlier. Administrative Code 28-105.1 makes the work itself unlawful without a written permit, and Administrative Code 28-104.1 bars the department from issuing that permit until it approves the required construction documents, which must be prepared by or under the supervision of a registered design professional, meaning a licensed architect or engineer, as required by the code. A homeowner therefore cannot self-prepare and file the plans for permit-requiring work in New York City even though Administrative Code 28-105.5.1 defines the permit applicant as the person who performs the work or retains a subcontractor, and even though the general contractor registration definition in Administrative Code 28-401.3 expressly excludes an individual who constructs a residential structure of no more than three dwelling units for his or her own occupancy. Note that Administrative Code 28-105.4 exempts minor alterations and ordinary repairs from the permit requirement entirely, so the design professional bottleneck applies only to work that needs a permit in the first place. Confirm how Town of Brookhaven applies this before you apply.
From the Library
Plumbing Permit in other New York localities
Everything above, sourced
How this plumbing permit page for Town of Brookhaven was verified. 2 official sources: brookhavenny.gov, web.archive.org; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page