Electrical Permit in Town of Brookhaven, New York

Permit required

Yes, a permit is required

Before any electrical work starts, contact one of the town's approved electrical inspection agencies. The agency's certificate is required before the Building Division will issue a certificate of occupancy or compliance.

Quick answer

This is a jurisdictional handoff, and it is the answer. Brookhaven does not issue or inspect an electrical permit itself. Town Code Chapter 16A requires all electrical systems and wiring in the town to conform to the National Electrical Code, and Sec. 16A-4 provides that inspections shall be made only by qualified inspectors designated by the Town Board, which is a list of private agencies. The Building Division publishes that list of Approved Electrical Inspection Agencies and tells owners to contact their chosen agency before beginning any work. Rough and final electrical inspections are performed by that independent agency, and an original certificate from a certified electrical inspector showing rough and final dates plus the permit number is one of the items the Building Division must receive before a certificate of occupancy is issued.

Issued by
Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What an electrical permit costs in Town of Brookhaven

Fee schedule in force
Official scheduleRead .
Published in
Town of Brookhaven Building Division Fee Schedule 2026, Construction table:
  • the schedule has no line naming an electrical permit.
  • It does list an "Electrical Transfer Switch Fee" of $90 for the first $1,000 of construction costs, plus $10 for every additional $1,000 thereafter, and "Residential Generator Fee $135".
  • The same table opens with "Application Fee $100";
  • the schedule does not say whether it is added to each permit.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Town of Brookhaven compares in New York

JurisdictionPermit needed?Threshold
BuffaloIt dependsrepair or in-kind replacement of a short published list of low-voltage devices, light fixtures and fans at an existing one- or two-family dwelling
New York CityIt dependsBefore any new installation, alteration or repair of electric wires, wiring apparatus...
RochesterIt dependsBefore replacing, repairing or altering an electrical service, before new interior or...
Town of Brookhaventhis pagePermit requiredAny size
Town of HempsteadPermit requiredAny size

How to apply in Town of Brookhaven

General guide, not specific to this office

What an electrical permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an electrical permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management

  • 1 Independence Hill, Farmingville, NY 11738
  • Phone: 631-451-8696

Permitting activity in Town of Brookhaven

In 2025, Town of Brookhaven authorized permits for 286 new residential housing units (266 single-family, 20 in multi-family buildings), valued at $94M, down from 514 the year before. That works out to about 0.6 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 479,883.

What else needs a permit in Town of Brookhaven

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsdeck rising more than eight inches above grade at any pointTown of Brookhaven Building Division Fee Schedule 2026, Construction table: "Deck Fee $0.50/SF"
Fence PermitIt dependsfence taller than four feet in a secondary front yard on a corner lot or through lotTown of Brookhaven Building Division Fee Schedule 2026, Construction table: "Fence Fee $1/LF"
HVAC PermitIt dependsinstallation of listed portable heating, ventilation or cooling equipment or appliancesTown of Brookhaven Building Division Fee Schedule 2026, Construction table: "CAC/HVAC Fee $160" and "Heating Unit Replacement Fee $135"
Patio PermitIt dependspatio rising more than eight inches above grade at any pointThe same table opens with "Application Fee $100"
Plumbing PermitIt dependsminor repairs to existing plumbing systemsSee schedule
Pool PermitIt dependspool structure extending more than 18 inches below grade, measuring how far the pool sits below grade and not the depth of the water, which is the code's test for an in-ground poolTown of Brookhaven Building Division Fee Schedule 2026, Construction table: "Inground Pool Fee $260" and "Above Ground Pool / Hot Tub Fee $135"
Roof Replacement PermitIt dependsrepair work that has no impact on fire and life safety, meaning no impact on the structural system, the required means of egress, or the fire protection systemIt lists a "Roof Over Fee" of $90 for the first $1,000 of construction costs, plus $10 for every additional $1,000 thereafter; the schedule has the rest
Shed PermitIt dependsdetached one-story storage shed larger than 144 square feet, or any shed not located in the rear yardTown of Brookhaven Building Division Fee Schedule 2026, Construction table: "Shed Fee $200"
Solar PermitPermit requiredAny sizeTown of Brookhaven Building Division Fee Schedule 2026, Construction table: "Solar Panel (Residential) $135"

Frequently asked questions

Do you need an electrical permit in Town of Brookhaven?
Yes, before any electrical work starts, contact one of the town's approved electrical inspection agencies. The agency's certificate is required before the Building Division will issue a certificate of occupancy or compliance. If you are unsure how that applies to your project, call the permit office at 631-451-8696 before you start.
How much does an electrical permit cost in Town of Brookhaven?
The fee wording from the official schedule is in the cost table on this page, as we read it on 11 Nov 2026. For the figure on your own project, call the permit office at 631-451-8696.
Where do you apply for an electrical permit in Town of Brookhaven?
You can apply through the Town of Brookhaven permit portal or contact the Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Town of Brookhaven?
Under New York law (Inside New York City: NYC Admin. Code 28-104.1, 28-105.1, 28-105.4, 28-105.5.1, 28-401.3 (definition of "general contractor"). Outside New York City: N.Y. Exec. Law 381(2); 19 NYCRR 1203.3(a)(1).): New York State sets no owner-builder rule at all outside New York City. Executive Law 381(2) puts administration and enforcement in the hands of each local government, and 19 NYCRR 1203.3(a)(1) only requires each authority having jurisdiction to make building permits mandatory for work that must conform to the codes, leaving who may apply to local law. The state licenses no general contractors and imposes no owner-builder affidavit, disclosure form or post-permit sale restriction of the kind Florida uses, so whether a homeowner may pull the permit is a question for the specific city, town, village or county. New York City is the genuine outlier. Administrative Code 28-105.1 makes the work itself unlawful without a written permit, and Administrative Code 28-104.1 bars the department from issuing that permit until it approves the required construction documents, which must be prepared by or under the supervision of a registered design professional, meaning a licensed architect or engineer, as required by the code. A homeowner therefore cannot self-prepare and file the plans for permit-requiring work in New York City even though Administrative Code 28-105.5.1 defines the permit applicant as the person who performs the work or retains a subcontractor, and even though the general contractor registration definition in Administrative Code 28-401.3 expressly excludes an individual who constructs a residential structure of no more than three dwelling units for his or her own occupancy. Note that Administrative Code 28-105.4 exempts minor alterations and ordinary repairs from the permit requirement entirely, so the design professional bottleneck applies only to work that needs a permit in the first place. Confirm how Town of Brookhaven applies this before you apply.

From the Library

Electrical Permit in other New York localities

Everything above, sourced

How this electrical permit page for Town of Brookhaven was verified. 1 official source: brookhavenny.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Town of Brookhaven Division of Building (Building Division), Department of Planning, Environment and Land Management. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project