New York / Town of Hempstead

Plumbing Permit in Town of Hempstead, New York

Permit required

Yes, a permit is required

Before any new plumbing or drainage work, fixture replacement, gas connection or sewer work.

Confirmed on official page Verified Town of Hempstead Department of Buildings

By Mario Bailey, verified against official sources

Quick answer

Plumbing is a separate permit from the building permit in the Town of Hempstead, and it must be filed by a plumber holding a Town of Hempstead master plumber license, not by the homeowner. The Plumbing Department runs four permit types on the Online Permit Center: Plumbing Permit, Gas Plumbing Permit, Sewer Permit and Fire Sprinkler Permit. Where a building permit job involves no plumbing, the Department requires a notarized Affidavit of No Plumbing Work in which the owner acknowledges that a plumbing permit must be applied for if plumbing is installed later. Even small jobs are caught: an in-ground pool needs a plumbing application for the vacuum breaker signed by a Town licensed master plumber.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before any new plumbing or drainage work, fixture replacement, gas connection or sewer work.

What a plumbing permit costs in Town of Hempstead

Line item
plumbing permitBy formulaTown Code 86-11N, as adopted by Local Law No. 93-2022 (effective 12-22-2022): a permit to install any new plumbing or drainage work is a minimum of $70, plus an additional $40 residential for each fixture over one; plumbing work started before the permit is issued is a minimum of $120 residential plus $60 for each fixture over one. Connecting a single fixture or replacing fixtures on an existing system is a minimum of $70 residential under 86-11P(1). Extending a vent stack is $75 residential (86-11O), a sewer permit to install or repair a house sewer is $125 plus $75 for the certificate of approval (86-11DD), and the certificate of approval of plumbing or drainage work is $100, payable when the plumbing permit is issued (86-11Q).
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Town of Hempstead compares in New York

JurisdictionPermit needed?Threshold
BuffaloIt dependsrepair or replacement of sections of the water distribution system totaling less than that length
New York CityIt dependsdirect replacement of an existing fixture or faucet that does not alter the hot and cold shutoff valves or the fixture trap
RochesterIt dependsNot specified
Town of BrookhavenIt dependsminor repairs to existing plumbing systems
Town of Hempsteadthis pagePermit requiredNot specified

How to apply in Town of Hempstead

You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.

What most plumbing permit applications include:

  • A permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
  • The application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
  • Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
  • Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
  • Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).

General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. Town of Hempstead Department of Buildings sets the exact checklist for Town of Hempstead.

Where to apply in Town of Hempstead:

Town of Hempstead Department of Buildings

Inspections and closing out your permit

Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.

  1. Piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
  2. Rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
  3. Rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
  4. The water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
  5. The framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
  6. At the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
  7. Final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Town of Hempstead permit portal or by phone at 516-538-8500.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a plumbing permit in Town of Hempstead?
Plumbing is a separate permit from the building permit in the Town of Hempstead, and it must be filed by a plumber holding a Town of Hempstead master plumber license, not by the homeowner. The Plumbing Department runs four permit types on the Online Permit Center: Plumbing Permit, Gas Plumbing Permit, Sewer Permit and Fire Sprinkler Permit. Where a building permit job involves no plumbing, the Department requires a notarized Affidavit of No Plumbing Work in which the owner acknowledges that a plumbing permit must be applied for if plumbing is installed later. Even small jobs are caught: an in-ground pool needs a plumbing application for the vacuum breaker signed by a Town licensed master plumber. Always confirm with the Town of Hempstead Department of Buildings before starting.
How much does a plumbing permit cost in Town of Hempstead?
Town Code 86-11N, as adopted by Local Law No. 93-2022 (effective 12-22-2022): a permit to install any new plumbing or drainage work is a minimum of $70, plus an additional $40 residential for each fixture over one; plumbing work started before the permit is issued is a minimum of $120 residential plus $60 for each fixture over one. Connecting a single fixture or replacing fixtures on an existing system is a minimum of $70 residential under 86-11P(1). Extending a vent stack is $75 residential (86-11O), a sewer permit to install or repair a house sewer is $125 plus $75 for the certificate of approval (86-11DD), and the certificate of approval of plumbing or drainage work is $100, payable when the plumbing permit is issued (86-11Q). See the official fee schedule for current amounts.
Where do you apply for a plumbing permit in Town of Hempstead?
You can apply through the Town of Hempstead permit portal or contact the Town of Hempstead Department of Buildings directly. The links are listed on this page.
Can a homeowner pull a plumbing permit themselves in Town of Hempstead?
Under New York law (Inside New York City: NYC Admin. Code 28-104.1, 28-105.1, 28-105.4, 28-105.5.1, 28-401.3 (definition of "general contractor"). Outside New York City: N.Y. Exec. Law 381(2); 19 NYCRR 1203.3(a)(1).): New York State sets no owner-builder rule at all outside New York City. Executive Law 381(2) puts administration and enforcement in the hands of each local government, and 19 NYCRR 1203.3(a)(1) only requires each authority having jurisdiction to make building permits mandatory for work that must conform to the codes, leaving who may apply to local law. The state licenses no general contractors and imposes no owner-builder affidavit, disclosure form or post-permit sale restriction of the kind Florida uses, so whether a homeowner may pull the permit is a question for the specific city, town, village or county. New York City is the genuine outlier. Administrative Code 28-105.1 makes the work itself unlawful without a written permit, and Administrative Code 28-104.1 bars the department from issuing that permit until it approves the required construction documents, which must be prepared by or under the supervision of a registered design professional, meaning a licensed architect or engineer, as required by the code. A homeowner therefore cannot self-prepare and file the plans for permit-requiring work in New York City even though Administrative Code 28-105.5.1 defines the permit applicant as the person who performs the work or retains a subcontractor, and even though the general contractor registration definition in Administrative Code 28-401.3 expressly excludes an individual who constructs a residential structure of no more than three dwelling units for his or her own occupancy. Note that Administrative Code 28-105.4 exempts minor alterations and ordinary repairs from the permit requirement entirely, so the design professional bottleneck applies only to work that needs a permit in the first place. Confirm how Town of Hempstead applies this before you apply.

From the Library

What else needs a permit in Town of Hempstead

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedCharged as a building permit under Town Code 86-11C(1) as amended by Local Law No.
Electrical PermitPermit requiredNot specifiedThe Town charges no electrical permit fee.
Fence PermitPermit requiredNot specifiedCharged as a building permit under Town Code 86-11C(1) as amended by Local Law No.
HVAC PermitPermit requiredNot specifiedTown Code 86-11I(2), as adopted by Local Law No.
Pool PermitPermit requiredNot specifiedCharged as a building permit under Town Code 86-11C(1) as amended by Local Law No.
Shed PermitPermit requiredNot specifiedCharged as a building permit under Town Code 86-11C(1) as amended by Local Law No.
Solar PermitPermit requiredNot specifiedThe flat solar fee is gone.

Plumbing Permit in other New York localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Town of Hempstead documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Town of Hempstead Department of Buildings. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Plumbing Permit requirements across New York localities

Permit required
Get quotes