New York / Town of Hempstead

Plumbing Permit in Town of Hempstead, New York

Permit required

Yes, a permit is required

Before any new plumbing or drainage work, fixture replacement, gas connection or sewer work.

Quick answer

Plumbing is a separate permit from the building permit in the Town of Hempstead, and it must be filed by a plumber holding a Town of Hempstead master plumber license, not by the homeowner. The Plumbing Department runs four permit types on the Online Permit Center: Plumbing Permit, Gas Plumbing Permit, Sewer Permit and Fire Sprinkler Permit. Where a building permit job involves no plumbing, the Department requires a notarized Affidavit of No Plumbing Work in which the owner acknowledges that a plumbing permit must be applied for if plumbing is installed later. Even small jobs are caught: an in-ground pool needs a plumbing application for the vacuum breaker signed by a Town licensed master plumber.

Issued by
Town of Hempstead Department of Buildings
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

Plumbing permits are usually pulled by the plumber doing the job. If you are still choosing one, compare a few quotes first.

Compare plumber quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What a plumbing permit costs in Town of Hempstead

Fee schedule in force
Official scheduleRead .
Published in
Town Code 86-11N, as adopted by Local Law No. 93-2022 (effective 12-22-2022):
  • a permit to install any new plumbing or drainage work is a minimum of $70, plus an additional $40 residential for each fixture over one;
  • plumbing work started before the permit is issued is a minimum of $120 residential plus $60 for each fixture over one.
  • Connecting a single fixture or replacing fixtures on an existing system is a minimum of $70 residential under 86-11P(1).
  • Extending a vent stack is $75 residential (86-11O), a sewer permit to install or repair a house sewer is $125 plus $75 for the certificate of approval (86-11DD), and the certificate of approval of plumbing or drainage work is $100, payable when the plumbing permit is issued (86-11Q).

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Town of Hempstead compares in New York

JurisdictionPermit needed?Threshold
BuffaloIt dependsrepair or replacement of sections of the water distribution system totaling less than that length
New York CityIt dependsdirect replacement of an existing fixture or faucet that does not alter the hot and cold shutoff valves or the fixture trap
RochesterIt dependsBefore replacing, repairing or altering water service, sewer, drain, waste, vent or...
Town of BrookhavenIt dependsminor repairs to existing plumbing systems
Town of Hempsteadthis pagePermit requiredAny size

How to apply in Town of Hempstead

General guide, not specific to this office

What a plumbing permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a plumbing permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Town of Hempstead Department of Buildings

Permitting activity in Town of Hempstead

In 2025, Town of Hempstead authorized permits for 270 new residential housing units (250 single-family, 20 in multi-family buildings), valued at $98M, up from 269 the year before. That works out to about 0.4 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 764,055.

What else needs a permit in Town of Hempstead

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

None of the 7 project types verified for Town of Hempstead carry a size or scope threshold. See the Permit needed column for each project's own answer, since there is no threshold to compare here.

ProjectPermit needed?Typical fee
Deck PermitPermit requiredSee schedule
Electrical PermitPermit requiredThe building permit fee by estimated cost under § 86-11C(1) is $200 for residential work with an estimated cost up to $1,000; the schedule has the rest
Fence PermitPermit requiredSee schedule
HVAC PermitPermit requiredSee schedule
Pool PermitPermit requiredSee schedule
Shed PermitPermit requiredSee schedule
Solar PermitPermit requiredSee schedule

Frequently asked questions

Do you need a plumbing permit in Town of Hempstead?
Yes, before any new plumbing or drainage work, fixture replacement, gas connection or sewer work. If you are unsure how that applies to your project, call the Town of Hempstead Department of Buildings at 516-538-8500 before you start.
How much does a plumbing permit cost in Town of Hempstead?
The fee wording from the official schedule is in the cost table on this page, as we read it on 11 Nov 2026. For the figure on your own project, call the Town of Hempstead Department of Buildings at 516-538-8500.
Where do you apply for a plumbing permit in Town of Hempstead?
You can apply through the Town of Hempstead permit portal or contact the Town of Hempstead Department of Buildings directly. The links are listed on this page.
Can a homeowner pull a plumbing permit themselves in Town of Hempstead?
Under New York law (Inside New York City: NYC Admin. Code 28-104.1, 28-105.1, 28-105.4, 28-105.5.1, 28-401.3 (definition of "general contractor"). Outside New York City: N.Y. Exec. Law 381(2); 19 NYCRR 1203.3(a)(1).): New York State sets no owner-builder rule at all outside New York City. Executive Law 381(2) puts administration and enforcement in the hands of each local government, and 19 NYCRR 1203.3(a)(1) only requires each authority having jurisdiction to make building permits mandatory for work that must conform to the codes, leaving who may apply to local law. The state licenses no general contractors and imposes no owner-builder affidavit, disclosure form or post-permit sale restriction of the kind Florida uses, so whether a homeowner may pull the permit is a question for the specific city, town, village or county. New York City is the genuine outlier. Administrative Code 28-105.1 makes the work itself unlawful without a written permit, and Administrative Code 28-104.1 bars the department from issuing that permit until it approves the required construction documents, which must be prepared by or under the supervision of a registered design professional, meaning a licensed architect or engineer, as required by the code. A homeowner therefore cannot self-prepare and file the plans for permit-requiring work in New York City even though Administrative Code 28-105.5.1 defines the permit applicant as the person who performs the work or retains a subcontractor, and even though the general contractor registration definition in Administrative Code 28-401.3 expressly excludes an individual who constructs a residential structure of no more than three dwelling units for his or her own occupancy. Note that Administrative Code 28-105.4 exempts minor alterations and ordinary repairs from the permit requirement entirely, so the design professional bottleneck applies only to work that needs a permit in the first place. Confirm how Town of Hempstead applies this before you apply.

From the Library

Plumbing Permit in other New York localities

Everything above, sourced

How this plumbing permit page for Town of Hempstead was verified. 2 official sources: hempsteadny.gov, viewpointcloud.blob.core.windows.net; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Town of Hempstead Department of Buildings. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project