Plumbing Permit in Tulsa, Oklahoma
Permit required
Yes, a permit is required
Before erecting, installing, enlarging, altering, repairing, removing, converting or replacing any plumbing system
By Mario Bailey, verified against official sources
Quick answer
A plumbing permit is required for residential plumbing work in Tulsa. Tulsa Revised Ordinances Title 56, Section 101 amends International Plumbing Code Section 106.1 so that anyone who wants to erect, install, enlarge, alter, repair, remove, convert or replace a plumbing system regulated by the code, or cause that work to be done, must first apply to the code official and obtain the required permit; the only carve-out is that emergency equipment replacements and repairs may have their application submitted the next working business day. A separate permit is required for each building in a complex and for each water meter in a multi-meter installation. Registration with the City plus a current state license under 59 O.S. Section 1001 et seq. is required before a Certificate of Registration is issued.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before erecting, installing, enlarging, altering, repairing, removing, converting or replacing any plumbing system
What a plumbing permit costs in Tulsa
How to apply in Tulsa
You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.
What most plumbing permit applications include:
- A permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
- The application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
- Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
- Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
- Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).
General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. City of Tulsa Development Services Department, Permit Center sets the exact checklist for Tulsa.
Where to apply in Tulsa:
City of Tulsa Development Services Department, Permit Center
- 175 E. 2nd Street, 4th Floor, Tulsa, OK 74103
- Phone: (918) 596-9456
- Email: bldgandLic@cityoftulsa.org
Inspections and closing out your permit
Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.
- Piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
- Rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
- Rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
- The water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
- The framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
- At the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
- Final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Tulsa permit portal or by phone at (918) 596-9456.
Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Plumbing Permit checklist for Tulsa
- Confirm the requirement. Yes, a permit is required. Usually needed: Before erecting, installing, enlarging, altering, repairing, removing, converting or replacing any plumbing system.
- Budget the fee. Title 49, Chapter 8, Section 801 prices plumbing work by item: backflow prevention assembly $79.00; interceptor/separator $150.00; water heater $35.00; water service $35.00; and plumbing fixtures, appliances and appurtenances at a base fee of $81.00 including the first fixture plus $3.31 for each additional fixture. Per Ord. No. 25351, 7-17-2024. Every permit also carries the general administrative fees in Title 49, Chapter 1: a $5.00 permit system maintenance surcharge on each permit (Section 103), a $4.00 Uniform Building Code Commission fee plus a $0.50 city administrative fee collected under 59 O.S. Section 1000.25 (Section 100), and a minimum fee of $80.00 on any permit (Section 107). Starting work before the permit is issued adds a penalty fee of $214.00 or three times the regular fee, whichever is greater (Section 105). All Title 49 figures are from Ord. No. 25351, 7-17-2024. Official fee schedule.
- Apply. You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit. Start at the Tulsa permit portal.
- Keep the office details handy. City of Tulsa Development Services Department, Permit Center. Phone: (918) 596-9456. Address: 175 E. 2nd Street, 4th Floor, Tulsa, OK 74103.
- Plan for inspections. Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a plumbing permit in Tulsa?
- A plumbing permit is required for residential plumbing work in Tulsa. Tulsa Revised Ordinances Title 56, Section 101 amends International Plumbing Code Section 106.1 so that anyone who wants to erect, install, enlarge, alter, repair, remove, convert or replace a plumbing system regulated by the code, or cause that work to be done, must first apply to the code official and obtain the required permit; the only carve-out is that emergency equipment replacements and repairs may have their application submitted the next working business day. A separate permit is required for each building in a complex and for each water meter in a multi-meter installation. Registration with the City plus a current state license under 59 O.S. Section 1001 et seq. is required before a Certificate of Registration is issued. Always confirm with the City of Tulsa Development Services Department, Permit Center before starting.
- How much does a plumbing permit cost in Tulsa?
- Title 49, Chapter 8, Section 801 prices plumbing work by item: backflow prevention assembly $79.00; interceptor/separator $150.00; water heater $35.00; water service $35.00; and plumbing fixtures, appliances and appurtenances at a base fee of $81.00 including the first fixture plus $3.31 for each additional fixture. Per Ord. No. 25351, 7-17-2024. Every permit also carries the general administrative fees in Title 49, Chapter 1: a $5.00 permit system maintenance surcharge on each permit (Section 103), a $4.00 Uniform Building Code Commission fee plus a $0.50 city administrative fee collected under 59 O.S. Section 1000.25 (Section 100), and a minimum fee of $80.00 on any permit (Section 107). Starting work before the permit is issued adds a penalty fee of $214.00 or three times the regular fee, whichever is greater (Section 105). All Title 49 figures are from Ord. No. 25351, 7-17-2024. See the official fee schedule for current amounts.
- Where do you apply for a plumbing permit in Tulsa?
- You can apply through the Tulsa permit portal or contact the City of Tulsa Development Services Department, Permit Center directly. The links are listed on this page.
- Can a homeowner pull a plumbing permit themselves in Tulsa?
- Under Oklahoma law (11 O.S. 43-109.2(B); 59 O.S. 1692(B)(3), 1017(6), 1151.17(B), 1850.10(A) and (B)(1), 1693(A)): Oklahoma does not license general or residential contractors at the state level, which is unusual and was verified by reading the whole of Title 59: the state licenses plumbing (59 O.S. 1001 et seq.), electrical (59 O.S. 1680 through 1699), mechanical (59 O.S. 1850.1 et seq.), roofing by registration (59 O.S. 1151.1 et seq.) and building and construction inspectors (59 O.S. 1031 through 1046), and no chapter licenses a general contractor. A homeowner may pull their own permit and do their own work. 11 O.S. 43-109.2(B) exempts a person doing construction or remodeling on their own single-family or duplex structure on their own property from the insurance verification a permit office must otherwise obtain before issuing a residential building permit, and it applies even when the structure is a rental, but the exemption disappears the moment a general contractor or subcontractor performs the work and pulls the permit. The trade acts carry matching self-work exemptions: no state license is needed to do electrical work on your own property or residence (59 O.S. 1692(B)(3)) or plumbing work on your own property of residence (59 O.S. 1017(6)), and a person roofing their own property is exempt from roofing registration though they must still give the permit office the registration number of any roofing subcontractor (59 O.S. 1151.17(B)). Every one of those is a licensing exemption only, expressly subject to local ordinances in the electrical case, and none of them waives the city permit; 59 O.S. 1693(A) still bars electrical work in a city or town without a permit first being obtained. Mechanical work is the sharp exception: the property-owner exemption in 59 O.S. 1850.10(B)(1) reaches only minor repair, and 59 O.S. 1850.10(A) requires a mechanical or plumbing licensee to install, replace or repair gas piping, floor furnaces, wall heaters or radiant-floor heating with no owner carve-out. Oklahoma has no statewide owner-builder disclosure form and no sale restriction comparable to Florida's one-year rule; the term owner-builder appears nowhere in Title 11 or Title 59. Confirm how Tulsa applies this before you apply.
From the Library
What else needs a permit in Tulsa
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Not specified | Priced as a building permit from valuation: the application fee is $64.00 for $0 to... |
| Electrical Permit | It depends | Not specified | Title 49, Chapter 4, Section 401 sets residential electrical permit fees for one- and... |
| Fence Permit | Permit required | Not specified | Residential zoning clearance permit fee is $75.50 under Tulsa Revised Ordinances Title... |
| HVAC Permit | Permit required | Not specified | Title 49, Chapter 5, Section 501 prices mechanical work by item: heating appliance, each... |
| Patio Permit | It depends | covered patios, carports and porches | A carport permit fee is $98.00 under Title 49, Chapter 3, Section 304. |
| Pool Permit | It depends | prefabricated swimming pools | Priced as a building permit from declared valuation: application fee $64.00 for $0 to... |
| Roof Replacement Permit | Permit required | Not specified | Priced as a building permit from valuation: $64.00 application fee for $0 to $15,000.00... |
| Shed Permit | Permit required | Not specified | Residential zoning clearance permit fee is $75.50 under Title 49, Chapter 3, Section... |
| Solar Permit | Permit required | Not specified | Title 49 has no solar line item. |
Plumbing Permit in other Oklahoma localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Tulsa documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with City of Tulsa Development Services Department, Permit Center. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Plumbing Permit requirements across Oklahoma localities
Permit office
City of Tulsa Development Services Department, Permit Center
(918) 596-9456Permit portal