Oklahoma / Tulsa

Patio Permit in Tulsa, Oklahoma

It depends

Sometimes, depending on the project

Before building a covered patio, patio cover, carport or porch

Quick answer

Tulsa's published patio rule attaches to covered patios. The Development Services Residential Building Guidelines treat carports, covered patios and porches as one project type and direct the applicant to apply online for Building (Residential): Building: Accessory Structure, or on paper for the Residential Building and Zoning Clearance Permit, with a site plan, structural cross-section, foundation plan and elevations. The city does not publish a separate answer for an uncovered, at-grade patio slab, and patios do not appear on either the city's short no-permit list or its list of residential zoning clearance only permits.

Typical threshold
covered patios, carports and porches
Issued by
City of Tulsa Development Services Department, Permit Center
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

If a contractor builds your patio, they usually handle any required permit as part of the job. Compare a few bids before you commit.

Compare patio contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What a patio permit costs in Tulsa

Fee basis
Project valuation
Fee schedule in force
Official scheduleRead .
  • A carport permit fee is $98.00 (Tulsa Revised Ordinances Title 49, Section 304).
  • A covered patio or porch is otherwise priced as a building permit from valuation: a $66.00 application fee for $0 to $15,000.00 of declared valuation (Section 301) and a building permit fee of $137.00 for $0 to $5,000.00 of estimated valuation, reduced by the application fee already paid (Section 302), both as amended by Ord. No. 25794, 5-13-2026.
  • A minimum fee of $80.00 applies to any permit (Title 49, Section 107).

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Tulsa

General guide, not specific to this office

What a patio permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a patio permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

City of Tulsa Development Services Department, Permit Center

Patio Permit in Tulsa compared with nearby Oklahoma localities

LocalityPermit needed?ThresholdWhat each Oklahoma schedule saysVerified
TulsaIt dependscovered patios, carports and porchesA carport permit fee is $98.00 (Tulsa Revised Ordinances Title 49, Section 304)
Oklahoma CityPermit requiredAny sizeSee schedule

Permitting activity in Tulsa

In 2025, Tulsa authorized permits for 865 new residential housing units (385 single-family, 480 in multi-family buildings), valued at $175M, up from 723 the year before. That works out to about 2.2 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 385,613.

What else needs a permit in Tulsa

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeSee schedule
Electrical PermitIt dependsBefore any electrical work other than a repair that does not alter or rearrange the...See schedule
Fence PermitPermit requiredAny sizeResidential zoning clearance permit fee: $75.50 (Tulsa Revised Ordinances Title 49, Section 303.G)
HVAC PermitPermit requiredAny sizeTitle 49, Chapter 5, Section 501 prices mechanical work by item: heating appliance, each $35.00
Plumbing PermitPermit requiredAny sizeTitle 49, Chapter 8, Section 801 prices plumbing work by item: backflow prevention assembly $79.00
Pool PermitIt dependsprefabricated swimming poolsSee schedule
Roof Replacement PermitPermit requiredAny sizeSee schedule
Shed PermitPermit requiredAny sizeResidential zoning clearance permit fee: $75.50 (Tulsa Revised Ordinances Title 49, Section 303.G)
Solar PermitPermit requiredAny sizeSee schedule

Frequently asked questions

Do you need a patio permit in Tulsa?
It depends on the project. Covered patios, carports and porches. If you are unsure how that applies to your project, call the City of Tulsa Development Services Department, Permit Center at (918) 596-9456 before you start.
How much does a patio permit cost in Tulsa?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the City of Tulsa Development Services Department, Permit Center at (918) 596-9456.
How long does a patio permit take in Tulsa?
Average time to first review, May 2026: 6.00 business days for the building review of a Building (Residential) Accessory Structure permit. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a patio permit in Tulsa?
You can apply through the Tulsa permit portal or contact the City of Tulsa Development Services Department, Permit Center directly. The links are listed on this page.
Can a homeowner pull a patio permit themselves in Tulsa?
Under Oklahoma law (11 O.S. 43-109.2(B); 59 O.S. 1692(B)(3), 1017(6), 1151.17(B), 1850.10(A) and (B)(1), 1693(A)): Oklahoma does not license general or residential contractors at the state level, which is unusual and was verified by reading the whole of Title 59: the state licenses plumbing (59 O.S. 1001 et seq.), electrical (59 O.S. 1680 through 1699), mechanical (59 O.S. 1850.1 et seq.), roofing by registration (59 O.S. 1151.1 et seq.) and building and construction inspectors (59 O.S. 1031 through 1046), and no chapter licenses a general contractor. A homeowner may pull their own permit and do their own work. 11 O.S. 43-109.2(B) exempts a person doing construction or remodeling on their own single-family or duplex structure on their own property from the insurance verification a permit office must otherwise obtain before issuing a residential building permit, and it applies even when the structure is a rental, but the exemption disappears the moment a general contractor or subcontractor performs the work and pulls the permit. The trade acts carry matching self-work exemptions: no state license is needed to do electrical work on your own property or residence (59 O.S. 1692(B)(3)) or plumbing work on your own property of residence (59 O.S. 1017(6)), and a person roofing their own property is exempt from roofing registration though they must still give the permit office the registration number of any roofing subcontractor (59 O.S. 1151.17(B)). Every one of those is a licensing exemption only, expressly subject to local ordinances in the electrical case, and none of them waives the city permit; 59 O.S. 1693(A) still bars electrical work in a city or town without a permit first being obtained. Mechanical work is the sharp exception: the property-owner exemption in 59 O.S. 1850.10(B)(1) reaches only minor repair, and 59 O.S. 1850.10(A) requires a mechanical or plumbing licensee to install, replace or repair gas piping, floor furnaces, wall heaters or radiant-floor heating with no owner carve-out. Oklahoma has no statewide owner-builder disclosure form and no sale restriction comparable to Florida's one-year rule; the term owner-builder appears nowhere in Title 11 or Title 59. Confirm how Tulsa applies this before you apply.

From the Library

Patio Permit in other Oklahoma localities

Everything above, sourced

How this patio permit page for Tulsa was verified. 2 official sources: cityoftulsa.org, cityoftulsa.org; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Tulsa Development Services Department, Permit Center. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

It depends
Check my project