Search “how much does a building permit cost” and you will find a single number, a national average. It is not wrong so much as unable to be right. PermitNotebook’s own permit cost data, read directly from official fee schedules across the localities we cover, shows the same permit type priced by different mechanics from one city to the next, sometimes within the same state. This guide walks through why, using examples pulled straight from that verified fee data: valuation-based fees versus flat fees, plan review billed as its own separate line, and permits your own city does not even charge for because a different agency handles that trade entirely.
Valuation-based fees: the charge scales with what you say the project costs
Most localities PermitNotebook covers price at least some permits off the declared value of the work, not a flat number. Bellevue, Washington’s building permit fee for a deck or fence runs off Table 4 of Ordinance 6879: a $44 minimum inspection fee for a project valued up to $500, rising from there, plus a $25 state building code fee added at issuance. Chandler, Arizona bills the same way for its deck, patio, and roof-replacement permits, a standard building permit fee by construction valuation with a $50 minimum, since none of those project types gets its own line item on the fee schedule. Clark County, Nevada does the same under its own Building Administrative Code, Table 3-A: a deck or patio cover permit starts at $54 for the first $500 of value and climbs from there. In each case, the number on the fee schedule is a formula, not a price, and what you pay depends on the value you declare for your specific project.
Flat fees: sometimes the same city charges a fixed number instead
The same jurisdictions that price some permits by valuation charge others a flat number regardless of project size, sometimes for the exact same trade. Bellevue is the clearest example: its 2026 fee ordinance charges a flat $290 for a standard re-roof permit, a fixed issuance fee under Table 5, priced completely differently from the valuation-based deck and fence fees in Table 4 of that same ordinance. Chandler runs the same split within one fee schedule: an electrical service upgrade of 400 amps or less is a flat $100 under section 4.6.4(b), while other electrical work is billed by valuation with that same $50 minimum, and a minor combined plumbing job of one to six plumbing openings with limited gas or electrical work is a flat $100 under 4.6.4(q), while a larger plumbing project reverts to the valuation formula. Austin, Texas prices fences, uncovered decks, and pools with a flat Small Projects Plan Review fee of $132.86 regardless of size, the same project types Bellevue, Chandler, and Clark County all price by valuation instead. There is no version of “the average fence permit fee” that is true in all four of those places at once.
Plan review: often billed as its own line, not folded into the permit fee
Plan review is frequently a separate charge on top of the base permit fee, not something the base fee already covers. Bellevue adds plan review at 65 percent of the inspection fee for a building permit like a deck, or 10 percent of the inspection fee, with a $35 minimum, for an electrical or solar permit. Chandler adds its own 65 percent plan review fee on top of the valuation-based building permit for projects like a deck or an HVAC system. Clark County, Nevada layers on two separate plan review charges at once, a 65 percent building plan review fee and a 10 percent zoning plan review fee, both on top of the base valuation charge. Austin folds plan review into its flat Small Projects fee instead of billing it separately. None of these approaches is wrong. They are just different, and a quoted “permit fee” that leaves out plan review can understate what you actually owe by more than half.
Trade handoffs: sometimes your own city does not charge the fee at all
Some permits are not priced, or even issued, by the office you would expect, because state or regional law hands that specific trade to a different agency. In Washington, electrical permits for unincorporated King County and unincorporated Clark County are not issued by the county at all. Both counties’ own fee schedules say the same thing: electrical work is permitted through the Washington State Department of Labor and Industries (L&I), not through the county permitting office, so no county fee applies. King County’s schedule adds the specific number, citing WAC 296-46B-906: new single- or two-family home wiring starts at $119.90 for the first 1,300 square feet plus $38.20 per additional 500 square feet, all under L&I’s own fee schedule rather than the county’s.
Plumbing works the same way around Seattle. Neither Seattle’s SDCI nor unincorporated King County charges a plumbing permit fee on its own building fee schedule. Public Health Seattle and King County, a health department rather than a building department, enforces the plumbing code and issues the permit instead, at $137 plus $27 per fixture. Look for a Seattle plumbing permit fee on SDCI’s own fee schedule and you will not find one, because SDCI is not who charges it.
Montgomery County, Maryland splits the same way for plumbing and water heater work. The county’s Department of Permitting Services charges no fee for either, because those permits go through WSSC (the Washington Suburban Sanitary Commission) instead, on WSSC’s own schedule. A Montgomery County bathroom remodel makes the split concrete: the remodel itself is filed as a residential Alteration Building Permit at $0.78 per square foot of altered area, with a minimum filing fee of $329.59, through the county, while any plumbing fixture work inside that same remodel needs a separate WSSC plumbing permit outside the county process entirely. One project, one address, two agencies, two fee schedules.
Re-inspection fees are real, and they add to whatever you started with
If work fails an inspection, most localities charge again to look at it a second time, and that charge is not part of the original permit fee either. We have verified exact re-inspection fees for three of the localities PermitNotebook covers, Fairfax County, Virginia; Chandler, Arizona; and Seattle, Washington, in What Happens After a Failed Permit Inspection, rather than repeating the numbers here. The short version: it is a real, locality-set charge, and it is one more reason a single quoted permit fee rarely turns out to be the last number you pay.
Why a single national average cannot capture any of this
Put those mechanics together, valuation-based versus flat pricing, plan review billed separately or bundled in, an entire trade handed off to a different agency, and a possible re-inspection fee on top, and it becomes clear why one national average permit cost is close to meaningless. Averaging a valuation-based fee from one city against a flat fee from another blends two different pricing systems into a number that describes neither. Leaving out plan review understates the true cost wherever it is charged separately. A number that assumes your city charges for electrical or plumbing, when a state agency or a health department actually does, is not describing your bill at all. The only number worth trusting is the one read directly from your own locality’s own fee schedule, for your own permit type, checked against the specifics, valuation, trade, whether plan review is separate, that make it different from the next city over.
What to do next
Start with What does a building permit cost? for the fee data itself, read directly from official schedules across every locality PermitNotebook covers, with the source and verification date cited for each one. If you want the number for your specific project rather than working through a fee schedule yourself, run it through Project Check for a free, cited breakdown.
Sources
- Bellevue, WA Ordinance 6879 fee schedule: Table 4 valuation-based building permit fee for a deck or fence, and Table 5 flat $290 re-roof permit fee, effective 2026-01-01. (accessed 2026-07-25)
- Chandler, AZ Development Department Fee Schedule: valuation-based building permit fee with a $50 minimum (4.6.1-4.6.2), flat $100 electrical service upgrade fee (4.6.4(b)), flat $100 minor combined plumbing fee (4.6.4(q)), and a 65 percent plan review fee. (accessed 2026-07-25)
- Clark County, NV Building Administrative Code Ch. 22.02, Table 3-A: valuation-based building permit fee plus separate 65 percent building plan review and 10 percent zoning plan review fees. (accessed 2026-07-25)
- Austin, TX FY2025-26 DSD residential fee schedule: flat $132.86 Small Projects Plan Review fee covering fences, uncovered decks, and pools. (accessed 2026-07-25)
- King County, WA permit fee schedule: no county electrical fee, since electrical permits are issued by Washington State L&I under WAC 296-46B-906. (accessed 2026-07-25)
- Washington State L&I electrical permit fees: new single- or two-family home wiring starts at $119.90 for the first 1,300 sq ft plus $38.20 per additional 500 sq ft, effective 7/1/2026. (accessed 2026-07-25)
- Public Health Seattle and King County issues residential plumbing and gas piping permits for both Seattle and unincorporated King County; fee $137 plus $27 per fixture, effective 1/1/2026. (accessed 2026-07-25)
- Seattle SDCI fee schedule: no SDCI plumbing fee, since plumbing permits are issued by Public Health Seattle and King County instead. (accessed 2026-07-25)
- Montgomery County, MD DPS FY27 fee schedule: alteration building permit at $0.78 per sq ft of altered area, minimum filing fee $329.59; plumbing fixture work needs a separate WSSC permit outside county DPS. (accessed 2026-07-25)
- Montgomery County, MD DPS fees page confirming no county DPS fee for plumbing or water heater work, since WSSC (Washington Suburban Sanitary Commission) issues those permits instead. (accessed 2026-07-25)
Get rule-change alerts
We catch permit rule and fee changes in our verification passes and post them to the rule tracker. Get them by email instead.
We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Look up your locality
- Washington permit pages rules by locality
- Arizona permit pages rules by locality
- Nevada permit pages rules by locality
- Maryland permit pages rules by locality
- Texas permit pages rules by locality