Solar Permit in Tulsa, Oklahoma
Permit required
Yes, a permit is required
Before installing a solar photovoltaic system, because the wiring is electrical work
By Mario Bailey, verified against official sources
Quick answer
Tulsa publishes no solar-specific permit page, but its electrical ordinance answers the question flatly: Tulsa Revised Ordinances Title 52, Section 104.2 says no person or company shall do or cause to be done any electrical work without first having obtained an electrical permit, and a photovoltaic installation is electrical work. Electrical permits are administered under Title 52 even for one- and two-family dwellings, because Title 51, Chapter 2, Section 201 (R105.3.(a)) directs that all electrical permits and required licensing be administered as described in Title 52. Only a contractor registered with the City and holding a current State of Oklahoma license issued under 59 O.S. Section 1680 et seq. may be issued the permit.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before installing a solar photovoltaic system, because the wiring is electrical work
What a solar permit costs in Tulsa
How to apply in Tulsa
A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.
What most solar permit applications include:
- Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
- The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
- Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
- The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
- The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
- Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
- Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).
General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Tulsa Development Services Department, Permit Center sets the exact checklist for Tulsa.
Where to apply in Tulsa:
City of Tulsa Development Services Department, Permit Center
- 175 E. 2nd Street, 4th Floor, Tulsa, OK 74103
- Phone: (918) 596-9456
- Email: bldgandLic@cityoftulsa.org
Inspections and closing out your permit
Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
- Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
- The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
- PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
- Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
- At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
- Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Tulsa permit portal or by phone at (918) 596-9456.
Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Solar Permit checklist for Tulsa
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing a solar photovoltaic system, because the wiring is electrical work.
- Budget the fee. Title 49 has no solar line item. Electrical permit fees are in Title 49, Chapter 4: electrical service is $98.00 for the first 100 amps and $18.00 for each additional 100 amps or portion thereof (Section 404.A), and electrical equipment is $81.00 for 1 to 25 items plus $2.68 each additional (Section 404.H), per Ord. No. 25351, 7-17-2024. Every permit also carries the general administrative fees in Title 49, Chapter 1: a $5.00 permit system maintenance surcharge on each permit (Section 103), a $4.00 Uniform Building Code Commission fee plus a $0.50 city administrative fee collected under 59 O.S. Section 1000.25 (Section 100), and a minimum fee of $80.00 on any permit (Section 107). Starting work before the permit is issued adds a penalty fee of $214.00 or three times the regular fee, whichever is greater (Section 105). All Title 49 figures are from Ord. No. 25351, 7-17-2024. Official fee schedule.
- Apply. A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit. Start at the Tulsa permit portal.
- Keep the office details handy. City of Tulsa Development Services Department, Permit Center. Phone: (918) 596-9456. Address: 175 E. 2nd Street, 4th Floor, Tulsa, OK 74103.
- Plan for inspections. Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a solar permit in Tulsa?
- Tulsa publishes no solar-specific permit page, but its electrical ordinance answers the question flatly: Tulsa Revised Ordinances Title 52, Section 104.2 says no person or company shall do or cause to be done any electrical work without first having obtained an electrical permit, and a photovoltaic installation is electrical work. Electrical permits are administered under Title 52 even for one- and two-family dwellings, because Title 51, Chapter 2, Section 201 (R105.3.(a)) directs that all electrical permits and required licensing be administered as described in Title 52. Only a contractor registered with the City and holding a current State of Oklahoma license issued under 59 O.S. Section 1680 et seq. may be issued the permit. Always confirm with the City of Tulsa Development Services Department, Permit Center before starting.
- How much does a solar permit cost in Tulsa?
- Title 49 has no solar line item. Electrical permit fees are in Title 49, Chapter 4: electrical service is $98.00 for the first 100 amps and $18.00 for each additional 100 amps or portion thereof (Section 404.A), and electrical equipment is $81.00 for 1 to 25 items plus $2.68 each additional (Section 404.H), per Ord. No. 25351, 7-17-2024. Every permit also carries the general administrative fees in Title 49, Chapter 1: a $5.00 permit system maintenance surcharge on each permit (Section 103), a $4.00 Uniform Building Code Commission fee plus a $0.50 city administrative fee collected under 59 O.S. Section 1000.25 (Section 100), and a minimum fee of $80.00 on any permit (Section 107). Starting work before the permit is issued adds a penalty fee of $214.00 or three times the regular fee, whichever is greater (Section 105). All Title 49 figures are from Ord. No. 25351, 7-17-2024. See the official fee schedule for current amounts.
- Where do you apply for a solar permit in Tulsa?
- You can apply through the Tulsa permit portal or contact the City of Tulsa Development Services Department, Permit Center directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Tulsa?
- Under Oklahoma law (11 O.S. 43-109.2(B); 59 O.S. 1692(B)(3), 1017(6), 1151.17(B), 1850.10(A) and (B)(1), 1693(A)): Oklahoma does not license general or residential contractors at the state level, which is unusual and was verified by reading the whole of Title 59: the state licenses plumbing (59 O.S. 1001 et seq.), electrical (59 O.S. 1680 through 1699), mechanical (59 O.S. 1850.1 et seq.), roofing by registration (59 O.S. 1151.1 et seq.) and building and construction inspectors (59 O.S. 1031 through 1046), and no chapter licenses a general contractor. A homeowner may pull their own permit and do their own work. 11 O.S. 43-109.2(B) exempts a person doing construction or remodeling on their own single-family or duplex structure on their own property from the insurance verification a permit office must otherwise obtain before issuing a residential building permit, and it applies even when the structure is a rental, but the exemption disappears the moment a general contractor or subcontractor performs the work and pulls the permit. The trade acts carry matching self-work exemptions: no state license is needed to do electrical work on your own property or residence (59 O.S. 1692(B)(3)) or plumbing work on your own property of residence (59 O.S. 1017(6)), and a person roofing their own property is exempt from roofing registration though they must still give the permit office the registration number of any roofing subcontractor (59 O.S. 1151.17(B)). Every one of those is a licensing exemption only, expressly subject to local ordinances in the electrical case, and none of them waives the city permit; 59 O.S. 1693(A) still bars electrical work in a city or town without a permit first being obtained. Mechanical work is the sharp exception: the property-owner exemption in 59 O.S. 1850.10(B)(1) reaches only minor repair, and 59 O.S. 1850.10(A) requires a mechanical or plumbing licensee to install, replace or repair gas piping, floor furnaces, wall heaters or radiant-floor heating with no owner carve-out. Oklahoma has no statewide owner-builder disclosure form and no sale restriction comparable to Florida's one-year rule; the term owner-builder appears nowhere in Title 11 or Title 59. Confirm how Tulsa applies this before you apply.
From the Library
What else needs a permit in Tulsa
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Not specified | Priced as a building permit from valuation: the application fee is $64.00 for $0 to... |
| Electrical Permit | It depends | Not specified | Title 49, Chapter 4, Section 401 sets residential electrical permit fees for one- and... |
| Fence Permit | Permit required | Not specified | Residential zoning clearance permit fee is $75.50 under Tulsa Revised Ordinances Title... |
| HVAC Permit | Permit required | Not specified | Title 49, Chapter 5, Section 501 prices mechanical work by item: heating appliance, each... |
| Patio Permit | It depends | covered patios, carports and porches | A carport permit fee is $98.00 under Title 49, Chapter 3, Section 304. |
| Plumbing Permit | Permit required | Not specified | Title 49, Chapter 8, Section 801 prices plumbing work by item: backflow prevention... |
| Pool Permit | It depends | prefabricated swimming pools | Priced as a building permit from declared valuation: application fee $64.00 for $0 to... |
| Roof Replacement Permit | Permit required | Not specified | Priced as a building permit from valuation: $64.00 application fee for $0 to $15,000.00... |
| Shed Permit | Permit required | Not specified | Residential zoning clearance permit fee is $75.50 under Title 49, Chapter 3, Section... |
Solar Permit in other Oklahoma localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Tulsa documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with City of Tulsa Development Services Department, Permit Center. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Solar Permit requirements across Oklahoma localities
Permit office
City of Tulsa Development Services Department, Permit Center
(918) 596-9456Permit portalCompare
Solar Permit across Oklahoma