Solar Permit in Tulsa, Oklahoma
Permit required
Yes, a permit is required
Before installing a solar photovoltaic system, because the wiring is electrical work
Quick answer
Tulsa publishes no solar-specific permit page, but its electrical ordinance answers the question flatly: Tulsa Revised Ordinances Title 52, Section 104.2 says no person or company shall do or cause to be done any electrical work without first having obtained an electrical permit, and a photovoltaic installation is electrical work. Electrical permits are administered under Title 52 even for one- and two-family dwellings, because Title 51, Chapter 2, Section 201 (R105.3.(a)) directs that all electrical permits and required licensing be administered as described in Title 52. Only a contractor registered with the City and holding a current State of Oklahoma license issued under 59 O.S. Section 1680 et seq. may be issued the permit.
- Issued by
- City of Tulsa Development Services Department, Permit Center
- Phone
- (918) 596-9456
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
Oklahoma's owner-builder rule (11 O.S. 43-109.2(B); 59 O.S. 1692(B)(3), 1017(6), 1151.17(B), 1850.10(A) and (B)(1), 1693(A)) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Tulsa
- Fee schedule in force
- Official scheduleRead .
- Title 49 has no solar line item.
- Electrical permit fees are in Title 49, Chapter 4: electrical service is $98.00 for the first 100 amps and $18.00 for each additional 100 amps or portion thereof (Section 404.A), and electrical equipment is $81.00 for 1 to 25 items plus $2.68 each additional (Section 404.H), per Ord. No. 25351, 7-17-2024.
- Every permit also carries the general administrative fees in Title 49, Chapter 1: a $5.00 permit system maintenance surcharge on each permit (Section 103), a $4.00 Uniform Building Code Commission fee plus a $0.50 city administrative fee collected under 59 O.S. Section 1000.25 (Section 100), and a minimum fee of $80.00 on any permit (Section 107).
- Starting work before the permit is issued adds a penalty fee of $214.00 or three times the regular fee, whichever is greater (Section 105).
- All Title 49 figures are from Ord. No. 25351, 7-17-2024.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in Tulsa
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
City of Tulsa Development Services Department, Permit Center
- 175 E. 2nd Street, 4th Floor, Tulsa, OK 74103
- Phone: (918) 596-9456
- Email: bldgandLic@cityoftulsa.org
Solar Permit in Tulsa compared with nearby Oklahoma localities
| Locality | Permit needed? | Threshold | What each Oklahoma schedule says | Verified |
|---|---|---|---|---|
| Tulsa | Permit required | Any size | See schedule | |
| Oklahoma City | Permit required | Any size | Oklahoma City Municipal Code Chapter 60, General Schedule of Fees, Section 60-12-10(i) "Photovoltaic system": $86.40 effective July 1; the schedule has the rest |
Your Solar Permit checklist for Tulsa
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: cityoftulsa.org: permit center.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Tulsa permit portal.
- Keep the office details handy. City of Tulsa Development Services Department, Permit Center. Phone: (918) 596-9456. Email: bldgandLic@cityoftulsa.org. Address: 175 E. 2nd Street, 4th Floor, Tulsa, OK 74103.
Compiled from the official sources on this page. Last checked .
Permitting activity in Tulsa
In 2025, Tulsa authorized permits for 865 new residential housing units (385 single-family, 480 in multi-family buildings), valued at $175M, up from 723 the year before. That works out to about 2.2 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 385,613.
What else needs a permit in Tulsa
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Any size | See schedule |
| Electrical Permit | It depends | Before any electrical work other than a repair that does not alter or rearrange the... | See schedule |
| Fence Permit | Permit required | Any size | Residential zoning clearance permit fee: $75.50 (Tulsa Revised Ordinances Title 49, Section 303.G) |
| HVAC Permit | Permit required | Any size | Title 49, Chapter 5, Section 501 prices mechanical work by item: heating appliance, each $35.00 |
| Patio Permit | It depends | covered patios, carports and porches | A carport permit fee is $98.00 (Tulsa Revised Ordinances Title 49, Section 304) |
| Plumbing Permit | Permit required | Any size | Title 49, Chapter 8, Section 801 prices plumbing work by item: backflow prevention assembly $79.00 |
| Pool Permit | It depends | prefabricated swimming pools | See schedule |
| Roof Replacement Permit | Permit required | Any size | See schedule |
| Shed Permit | Permit required | Any size | Residential zoning clearance permit fee: $75.50 (Tulsa Revised Ordinances Title 49, Section 303.G) |
Frequently asked questions
- Do you need a solar permit in Tulsa?
- Yes, before installing a solar photovoltaic system, because the wiring is electrical work. If you are unsure how that applies to your project, call the City of Tulsa Development Services Department, Permit Center at (918) 596-9456 before you start.
- How much does a solar permit cost in Tulsa?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the City of Tulsa Development Services Department, Permit Center at (918) 596-9456.
- Where do you apply for a solar permit in Tulsa?
- You can apply through the Tulsa permit portal or contact the City of Tulsa Development Services Department, Permit Center directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Tulsa?
- Under Oklahoma law (11 O.S. 43-109.2(B); 59 O.S. 1692(B)(3), 1017(6), 1151.17(B), 1850.10(A) and (B)(1), 1693(A)): Oklahoma does not license general or residential contractors at the state level, which is unusual and was verified by reading the whole of Title 59: the state licenses plumbing (59 O.S. 1001 et seq.), electrical (59 O.S. 1680 through 1699), mechanical (59 O.S. 1850.1 et seq.), roofing by registration (59 O.S. 1151.1 et seq.) and building and construction inspectors (59 O.S. 1031 through 1046), and no chapter licenses a general contractor. A homeowner may pull their own permit and do their own work. 11 O.S. 43-109.2(B) exempts a person doing construction or remodeling on their own single-family or duplex structure on their own property from the insurance verification a permit office must otherwise obtain before issuing a residential building permit, and it applies even when the structure is a rental, but the exemption disappears the moment a general contractor or subcontractor performs the work and pulls the permit. The trade acts carry matching self-work exemptions: no state license is needed to do electrical work on your own property or residence (59 O.S. 1692(B)(3)) or plumbing work on your own property of residence (59 O.S. 1017(6)), and a person roofing their own property is exempt from roofing registration though they must still give the permit office the registration number of any roofing subcontractor (59 O.S. 1151.17(B)). Every one of those is a licensing exemption only, expressly subject to local ordinances in the electrical case, and none of them waives the city permit; 59 O.S. 1693(A) still bars electrical work in a city or town without a permit first being obtained. Mechanical work is the sharp exception: the property-owner exemption in 59 O.S. 1850.10(B)(1) reaches only minor repair, and 59 O.S. 1850.10(A) requires a mechanical or plumbing licensee to install, replace or repair gas piping, floor furnaces, wall heaters or radiant-floor heating with no owner carve-out. Oklahoma has no statewide owner-builder disclosure form and no sale restriction comparable to Florida's one-year rule; the term owner-builder appears nowhere in Title 11 or Title 59. Confirm how Tulsa applies this before you apply.
From the Library
Solar Permit in other Oklahoma localities
Everything above, sourced
How this solar permit page for Tulsa was verified. 2 official sources: cityoftulsa.org, library.municode.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Tulsa Development Services Department, Permit Center. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page