Permit required

Yes, a permit is required

Before erecting, installing, enlarging, altering, repairing, removing, converting or replacing any plumbing system regulated by the code, including a water heater replacement, a sewer or water line, or a gas line.

Confirmed on official page Verified City of Arlington Planning and Development Services Department, Building Inspections Division

By Mario Bailey, verified against official sources

Quick answer

Arlington issues its own plumbing permits under a locally amended 2021 International Plumbing Code and 2021 International Fuel Gas Code. Amended Section 106.1 requires the owner, authorized agent or contractor to apply to the code official and obtain a permit before any regulated plumbing work, and adds that a permit may only be issued to a registrant under Article III of the chapter, so the plumber must hold an active City of Arlington business registration. The city's own FAQ names water heater replacement as one of the most common homeowner projects that requires a permit and inspection. Commencing plumbing work before obtaining the necessary permits costs 100 percent of the usual permit fee in addition to the required fees.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before erecting, installing, enlarging, altering, repairing, removing, converting or replacing any plumbing system regulated by the code, including a water heater replacement, a sewer or water line, or a gas line.

What a plumbing permit costs in Arlington

Line item
plumbing permitBy formulaPlanning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No. 26 - 151, Plumbing Permits: "Per Trade - Commercial and Residential New Construction Permits $100.00" where associated with a building permit. Not associated with a building permit: "Base permit fee $100.00" plus items such as "Water heater, first water heater $20.00", "New fixtures (lavatory, sink, water closet, tub, etc.) for the first three $40.00", "Replace fixtures (lavatory, sink, water closet, tub, etc.) for the first five $30.00" with a "Maximum fee of $600.00 per building address", "Sewer line $15.00", "Water line $15.00", and "Install new gas line $30.00".
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Arlington compares in Texas

No Texas jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Arlingtonthis pagePermit requiredPlanning and Development Services Fee Schedule, Effective June 1, 2026...
AustinPermit requiredPlumbing trade permit base fee is $200.43, per the FY2025-26 DSD residential...
Corpus ChristiPermit requiredFY 2026 Development Fee Schedule, Plumbing Permits: Residential $0.075 per...
DallasPermit requiredBilled under the Alterations or Repairs schedule (Table B-I), value of work...
El PasoPermit requiredFY 2026 Schedule C Departmental Fee List, Planning & Inspections, Plumbing:...
Fort WorthPermit requiredBilled per fixture on the Schedule of Plumbing Fees, Table 1-I: first fixture...
HoustonPermit requiredMinimum plumbing permit fee is $97.56 plus the $33.56 administrative fee, with...

How to apply in Arlington

You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.

What most plumbing permit applications include:

  • A permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
  • The application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
  • Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
  • Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
  • Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).

General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. City of Arlington Planning and Development Services Department, Building Inspections Division sets the exact checklist for Arlington.

Where to apply in Arlington:

City of Arlington Planning and Development Services Department, Building Inspections Division

Inspections and closing out your permit

Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.

  1. Piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
  2. Rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
  3. Rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
  4. The water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
  5. The framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
  6. At the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
  7. Final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Arlington permit portal or by phone at 817-459-6502.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a plumbing permit in Arlington?
Arlington issues its own plumbing permits under a locally amended 2021 International Plumbing Code and 2021 International Fuel Gas Code. Amended Section 106.1 requires the owner, authorized agent or contractor to apply to the code official and obtain a permit before any regulated plumbing work, and adds that a permit may only be issued to a registrant under Article III of the chapter, so the plumber must hold an active City of Arlington business registration. The city's own FAQ names water heater replacement as one of the most common homeowner projects that requires a permit and inspection. Commencing plumbing work before obtaining the necessary permits costs 100 percent of the usual permit fee in addition to the required fees. Always confirm with the City of Arlington Planning and Development Services Department, Building Inspections Division before starting.
How much does a plumbing permit cost in Arlington?
Planning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No. 26 - 151, Plumbing Permits: "Per Trade - Commercial and Residential New Construction Permits $100.00" where associated with a building permit. Not associated with a building permit: "Base permit fee $100.00" plus items such as "Water heater, first water heater $20.00", "New fixtures (lavatory, sink, water closet, tub, etc.) for the first three $40.00", "Replace fixtures (lavatory, sink, water closet, tub, etc.) for the first five $30.00" with a "Maximum fee of $600.00 per building address", "Sewer line $15.00", "Water line $15.00", and "Install new gas line $30.00". See the official fee schedule for current amounts.
Where do you apply for a plumbing permit in Arlington?
You can apply through the Arlington permit portal or contact the City of Arlington Planning and Development Services Department, Building Inspections Division directly. The links are listed on this page.
Can a homeowner pull a plumbing permit themselves in Arlington?
Under Texas law (Tex. Occupations Code 1305.003(a)(6), 1301.051; Tex. Local Government Code 233.157(c)): Texas licenses individual construction trades rather than general contractors, so no state statute requires a license to act as your own general contractor on your own house. For electrical work, the state licensing law does not apply to work performed in or on a dwelling by a person who owns and resides in it, but only where no municipal ordinance specifically regulates that work, so city electrical licensing and permit rules still control inside city limits (Occupations Code 1305.003(a)(6)). For plumbing, a property owner does not need a state license to perform plumbing in the owner's homestead (Occupations Code 1301.051). In opt-in counties' unincorporated areas, an individual who builds their own house or acts as their own contractor is exempt from the Class C misdemeanor penalty for inspection notice failures if they intend to use the home as their primary residence (Local Government Code 233.157(c)). None of these exemptions waive local permit or inspection requirements where they apply. Confirm how Arlington applies this before you apply.

From the Library

What else needs a permit in Arlington

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

Planning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No, for every permit type below. The fee column shows what differs by project.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsheight of an uncovered deck above grade at any point26 - 151, Residential Construction: "Patio Cover, Screened Porch, Gazebo & Decks*...
Electrical PermitPermit requiredNot specified26 - 151, Building Permit for Electrical: "Per Trade - Commercial and Residential New...
Fence PermitIt dependsshare of one side of an existing fence being repaired or replaced26 - 151, Residential Construction: "Fence, Residential Lot $50.00 each"
HVAC PermitPermit requiredNot specified26 - 151, Mechanical: "Per Trade - Commercial and Residential New Construction Permits...
Patio PermitIt dependsheight of an uncovered patio above grade at any point26 - 151, Residential Construction: "Patio Cover, Screened Porch, Gazebo & Decks*...
Pool PermitIt dependsdepth of a prefabricated inflatable swimming pool26 - 151, Residential Construction: "Swimming Pool - In-ground (1 & 2 Family) (Spa...
Roof Replacement PermitIt dependsarea of roof covering material being replaced26 - 151, Residential Construction: "Reroof* $325.00".
Shed PermitIt dependsfloor area of a one-story detached tool or storage shed26 - 151, Residential Construction: "Portable Storage/Accessory Building 320 sq.ft.
Solar PermitPermit requiredNot specified26 - 151, Residential Construction: "Solar Panel* $325.00" and "Home Backup Power...

Plumbing Permit in other Texas localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Arlington documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Arlington Planning and Development Services Department, Building Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Plumbing Permit requirements across Texas localities

Look up an existing Arlington permit record

Permit required
Get quotes