Permit required

Yes, a permit is required

Before installing roof-mounted photovoltaic panels, battery storage, or a standby generator at a one- or two-family dwelling. The application is filed at ArlingtonPermits.com under permit type Solar Panel (SOLR), sub type Residential, work type New.

Confirmed on official page Verified City of Arlington Planning and Development Services Department, Building Inspections Division

By Mario Bailey, verified against official sources

Quick answer

Arlington permits residential solar separately under its own permit type, Solar Panel (SOLR). Since Senate Bill 1202 took effect on September 1, 2025, the city has published a defined minimum submittal package for home backup power installations, defined as electric generating facilities, energy storage facilities, standby systems and associated infrastructure for one- or two-family dwellings connected at 600 volts or less, and states that permits will not be processed for review until that package is complete. Required submittals include a scaled plan view of all roof-mounted PV showing the percentage of panel coverage to total roof area, pathways and ridge setbacks per 2021 IRC Section R324.6, attachment details, inverter and collector cut sheets listed by a Nationally Recognized Testing Laboratory, and an engineered or master-electrician-prepared three-line diagram. Standby generators are permitted differently, as a Residential Building Permit (RP) with work type Remodel/Alterations/Repairs.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing roof-mounted photovoltaic panels, battery storage, or a standby generator at a one- or two-family dwelling. The application is filed at ArlingtonPermits.com under permit type Solar Panel (SOLR), sub type Residential, work type New.

What a solar permit costs in Arlington

Line item
solar permitBy formulaPlanning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No. 26 - 151, Residential Construction: "Solar Panel* $325.00" and "Home Backup Power Installations (for third-party plan review and inspections) $300.00".
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Arlington compares in Texas

No Texas jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Arlingtonthis pagePermit requiredPlanning and Development Services Fee Schedule, Effective June 1, 2026...
AustinPermit requiredSolar permits carry a $32.47 intake fee plus a $111.66 auxiliary power...
Corpus ChristiPermit requiredThe FY 2026 Development Fee Schedule publishes no solar line item.
DallasPermit requiredNo solar-specific line
El PasoPermit requiredFY 2026 Schedule C Departmental Fee List, Planning & Inspections, prices solar...
Fort WorthPermit requiredThe Schedule of Mechanical Fees, Table 1-H, carries a "Solar energy system:...
HoustonPermit requiredSolar panel permit fee is $91.06 plus the $33.56 administrative fee, with plan...

How to apply in Arlington

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Arlington Planning and Development Services Department, Building Inspections Division sets the exact checklist for Arlington.

Where to apply in Arlington:

City of Arlington Planning and Development Services Department, Building Inspections Division

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Arlington permit portal or by phone at 817-459-6502.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Arlington?
Arlington permits residential solar separately under its own permit type, Solar Panel (SOLR). Since Senate Bill 1202 took effect on September 1, 2025, the city has published a defined minimum submittal package for home backup power installations, defined as electric generating facilities, energy storage facilities, standby systems and associated infrastructure for one- or two-family dwellings connected at 600 volts or less, and states that permits will not be processed for review until that package is complete. Required submittals include a scaled plan view of all roof-mounted PV showing the percentage of panel coverage to total roof area, pathways and ridge setbacks per 2021 IRC Section R324.6, attachment details, inverter and collector cut sheets listed by a Nationally Recognized Testing Laboratory, and an engineered or master-electrician-prepared three-line diagram. Standby generators are permitted differently, as a Residential Building Permit (RP) with work type Remodel/Alterations/Repairs. Always confirm with the City of Arlington Planning and Development Services Department, Building Inspections Division before starting.
How much does a solar permit cost in Arlington?
Planning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No. 26 - 151, Residential Construction: "Solar Panel* $325.00" and "Home Backup Power Installations (for third-party plan review and inspections) $300.00". See the official fee schedule for current amounts.
Where do you apply for a solar permit in Arlington?
You can apply through the Arlington permit portal or contact the City of Arlington Planning and Development Services Department, Building Inspections Division directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Arlington?
Under Texas law (Tex. Occupations Code 1305.003(a)(6), 1301.051; Tex. Local Government Code 233.157(c)): Texas licenses individual construction trades rather than general contractors, so no state statute requires a license to act as your own general contractor on your own house. For electrical work, the state licensing law does not apply to work performed in or on a dwelling by a person who owns and resides in it, but only where no municipal ordinance specifically regulates that work, so city electrical licensing and permit rules still control inside city limits (Occupations Code 1305.003(a)(6)). For plumbing, a property owner does not need a state license to perform plumbing in the owner's homestead (Occupations Code 1301.051). In opt-in counties' unincorporated areas, an individual who builds their own house or acts as their own contractor is exempt from the Class C misdemeanor penalty for inspection notice failures if they intend to use the home as their primary residence (Local Government Code 233.157(c)). None of these exemptions waive local permit or inspection requirements where they apply. Confirm how Arlington applies this before you apply.

From the Library

What else needs a permit in Arlington

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

Planning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No, for every permit type below. The fee column shows what differs by project.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsheight of an uncovered deck above grade at any point26 - 151, Residential Construction: "Patio Cover, Screened Porch, Gazebo & Decks*...
Electrical PermitPermit requiredNot specified26 - 151, Building Permit for Electrical: "Per Trade - Commercial and Residential New...
Fence PermitIt dependsshare of one side of an existing fence being repaired or replaced26 - 151, Residential Construction: "Fence, Residential Lot $50.00 each"
HVAC PermitPermit requiredNot specified26 - 151, Mechanical: "Per Trade - Commercial and Residential New Construction Permits...
Patio PermitIt dependsheight of an uncovered patio above grade at any point26 - 151, Residential Construction: "Patio Cover, Screened Porch, Gazebo & Decks*...
Plumbing PermitPermit requiredNot specified26 - 151, Plumbing Permits: "Per Trade - Commercial and Residential New Construction...
Pool PermitIt dependsdepth of a prefabricated inflatable swimming pool26 - 151, Residential Construction: "Swimming Pool - In-ground (1 & 2 Family) (Spa...
Roof Replacement PermitIt dependsarea of roof covering material being replaced26 - 151, Residential Construction: "Reroof* $325.00".
Shed PermitIt dependsfloor area of a one-story detached tool or storage shed26 - 151, Residential Construction: "Portable Storage/Accessory Building 320 sq.ft.

Solar Permit in other Texas localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Arlington documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Arlington Planning and Development Services Department, Building Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Solar Permit requirements across Texas localities

Look up an existing Arlington permit record

Permit required
Get quotes