Solar Permit in Arlington, Texas

Permit required

Yes, a permit is required

Before installing roof-mounted photovoltaic panels, battery storage, or a standby generator at a one- or two-family dwelling. The application is filed at ArlingtonPermits.com under permit type Solar Panel (SOLR), sub type Residential, work type New.

Quick answer

Arlington permits residential solar separately under its own permit type, Solar Panel (SOLR). Since Senate Bill 1202 took effect on September 1, 2025, the city has published a defined minimum submittal package for home backup power installations, defined as electric generating facilities, energy storage facilities, standby systems and associated infrastructure for one- or two-family dwellings connected at 600 volts or less, and states that permits will not be processed for review until that package is complete. Required submittals include a scaled plan view of all roof-mounted PV showing the percentage of panel coverage to total roof area, pathways and ridge setbacks per 2021 IRC Section R324.6, attachment details, inverter and collector cut sheets listed by a Nationally Recognized Testing Laboratory, and an engineered or master-electrician-prepared three-line diagram. Standby generators are permitted differently, as a Residential Building Permit (RP) with work type Remodel/Alterations/Repairs.

Issued by
City of Arlington Planning and Development Services Department, Building Inspections Division
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?

Texas's owner-builder rule (Tex. Occupations Code 1305.003(a)(6), 1301.051; Tex. Local Government Code 233.157(c)) sets what you may do on your own home without hiring anyone. Read the statute.

What a solar permit costs in Arlington

Fee schedule in force
Official scheduleRead .
Published in
Planning and Development Services Fee Schedule, Effective October 1, 2026, Resolution No. 26 - 288, Residential Construction:

"Solar Panel* $325.00" and "Home Backup Power Installations (for third-party plan review and inspections) $300.00".

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Arlington compares in Texas

No Texas jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Arlingtonthis pagePermit requiredSee schedule
AustinPermit requiredSolar permits carry a $53.56 intake fee plus a $169.83 auxiliary power electrical permit base fee (an Austin Energy fee); the schedule has the rest
Corpus ChristiPermit requiredResidential construction is $0.461 per square foot with a $146.41 minimum (excluding mechanical, electrical and plumbing); the schedule has the rest
DallasPermit requiredSee schedule
El PasoPermit requiredSee schedule
Fort WorthPermit requiredThe Schedule of Mechanical Fees, Table 1-H, carries a "Solar energy system" line of $62.14, which is the thermal/mechanical side
HoustonPermit requiredSolar panel permit fee is $91.06 plus the $33.56 administrative fee; the schedule has the rest

How to apply in Arlington

General guide, not specific to this office

What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

City of Arlington Planning and Development Services Department, Building Inspections Division

Permitting activity in Arlington

In 2025, Arlington authorized permits for 1,576 new residential housing units (532 single-family, 1,044 in multi-family buildings), valued at $229M, down from 1,703 the year before. That works out to about 4 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 398,864.

What else needs a permit in Arlington

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsheight of an uncovered deck above grade at any pointSee schedule
Electrical PermitPermit requiredAny sizeSee schedule
Fence PermitIt dependsshare of one side of an existing fence being repaired or replacedSee schedule
HVAC PermitPermit requiredAny sizeSee schedule
Patio PermitIt dependsheight of an uncovered patio above grade at any pointSee schedule
Plumbing PermitPermit requiredAny sizeSee schedule
Pool PermitIt dependsdepth of a prefabricated inflatable swimming poolSee schedule
Roof Replacement PermitIt dependsarea of roof covering material being replacedPlanning and Development Services Fee Schedule, Effective October 1, 2026, Resolution No. 26 - 288, Residential Construction: "Reroof* $325.00"
Shed PermitIt dependsfloor area of a one-story detached tool or storage shedSee schedule

Frequently asked questions

Do you need a solar permit in Arlington?
Yes, before installing roof-mounted photovoltaic panels, battery storage, or a standby generator at a one- or two-family dwelling. The application is filed at ArlingtonPermits.com under permit type Solar Panel (SOLR), sub type Residential, work type New. If you are unsure how that applies to your project, call the permit office at 817-459-6502 before you start.
How much does a solar permit cost in Arlington?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the permit office at 817-459-6502.
Where do you apply for a solar permit in Arlington?
You can apply through the Arlington permit portal or contact the City of Arlington Planning and Development Services Department, Building Inspections Division directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Arlington?
Under Texas law (Tex. Occupations Code 1305.003(a)(6), 1301.051; Tex. Local Government Code 233.157(c)): Texas licenses individual construction trades rather than general contractors, so no state statute requires a license to act as your own general contractor on your own house. For electrical work, the state licensing law does not apply to work performed in or on a dwelling by a person who owns and resides in it, but only where no municipal ordinance specifically regulates that work, so city electrical licensing and permit rules still control inside city limits (Occupations Code 1305.003(a)(6)). For plumbing, a property owner does not need a state license to perform plumbing in the owner's homestead (Occupations Code 1301.051). In opt-in counties' unincorporated areas, an individual who builds their own house or acts as their own contractor is exempt from the Class C misdemeanor penalty for inspection notice failures if they intend to use the home as their primary residence (Local Government Code 233.157(c)). None of these exemptions waive local permit or inspection requirements where they apply. Confirm how Arlington applies this before you apply.

From the Library

Solar Permit in other Texas localities

Everything above, sourced

How this solar permit page for Arlington was verified. 2 official sources: arlingtontx.gov, arlingtontx.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Arlington Planning and Development Services Department, Building Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page