Texas / El Paso

Solar Permit in El Paso, Texas

Permit required

Yes, a permit is required

Before installing solar panels, solar shingles, or a solar heating system inside the City of El Paso

Quick answer

The City of El Paso issues a dedicated solar permit: its Citizen Access portal carries "Building/Solar Panel/NA/NA" as its own Building record type, and the adopted FY 2026 fee schedule prices solar under building, electrical, mechanical, and plumbing headings. Solar shingles are billed on a separate building-permit line from solar panels, which are billed as an electrical item. Because a photovoltaic install is electrical work, the city's rule that only a contractor registered with the City may be issued a trade permit applies. These rules apply inside El Paso city limits only.

Issued by
City of El Paso Planning and Inspections Department (One Stop Shop)
From an official source Verified

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?

Texas's owner-builder rule (Tex. Occupations Code 1305.003(a)(6), 1301.051; Tex. Local Government Code 233.157(c)) sets what you may do on your own home without hiring anyone. Read the statute.

What a solar permit costs in El Paso

Fee schedule in force
Official scheduleRead .
  • FY 2027 Schedule C Departmental Fee List, Planning & Inspections, prices solar across four trades: Building Permits Solar Shingle per 100 sq. ft., $14 per sq. ft. plus base fee;
  • Electrical Permits Solar panels, $14 each, and Solar heating systems, $24, each plus the electrical base fee;
  • Mechanical Solar Systems (excluding duct work), $36 plus base fee;
  • Plumbing Solar panels, $13.76 each, and Solar heating systems, $24.35, plus base fee.
  • All are plus applicable technology fee.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How El Paso compares in Texas

No Texas jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
ArlingtonPermit requiredSee schedule
AustinPermit requiredSolar permits carry a $53.56 intake fee plus a $169.83 auxiliary power electrical permit base fee (an Austin Energy fee); the schedule has the rest
Corpus ChristiPermit requiredResidential construction is $0.461 per square foot with a $146.41 minimum (excluding mechanical, electrical and plumbing); the schedule has the rest
DallasPermit requiredSee schedule
El Pasothis pagePermit requiredSee schedule
Fort WorthPermit requiredThe Schedule of Mechanical Fees, Table 1-H, carries a "Solar energy system" line of $62.14, which is the thermal/mechanical side
HoustonPermit requiredSolar panel permit fee is $91.06 plus the $33.56 administrative fee; the schedule has the rest

How to apply in El Paso

General guide, not specific to this office

What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

City of El Paso Planning and Inspections Department (One Stop Shop)

Permitting activity in El Paso

In 2025, El Paso authorized permits for 1,722 new residential housing units (1,466 single-family, 256 in multi-family buildings), valued at $376M, down from 1,887 the year before. That works out to about 2.5 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 681,534.

What else needs a permit in El Paso

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Electrical PermitPermit requiredReplacing a switch, receptacle, fuse, fan, light fixture, or similar equipment without altering the mechanical, electrical, or plumbing system is exempt.See schedule
Fence PermitIt dependsMasonry walls and fences are measured against 42 inches in height; chain link fences are measured against a separate and higher trigger of 6 feet in height. The material determines which of the two applies.See schedule
HVAC PermitPermit requiredAny sizeSee schedule
Patio PermitIt dependsConcrete work more than 30 inches above grade, or concrete that will support a structure, requires a permit; a detached patio cover is permitted under the city's porches and canopies entry.See schedule
Plumbing PermitPermit requiredAny sizeSee schedule
Pool PermitIt dependsPools and ponds over 24 inches of depth require a permit, as do above ground pools containing 5,000 gallons of water or more.See schedule
Roof Replacement PermitIt dependsThe 25 percent is a share of the residential roof covering being replaced, measured across the roof rather than as an area in square feet or a count of squares.FY 2027 Schedule C Departmental Fee List, Planning & Inspections, Building Permit line Roofing Permit: $118 plus applicable technology fee
Shed PermitIt dependsThe exemption covers accessory storage buildings or structures of less than 200 square feet of floor area, and is limited to one such accessory structure per site.The closest Planning & Inspections building-permit lines are Permit which require only one inspection, $110 plus applicable technology fee

Frequently asked questions

Do you need a solar permit in El Paso?
Yes, before installing solar panels, solar shingles, or a solar heating system inside the City of El Paso. If you are unsure how that applies to your project, call the permit office at 915-212-0104 before you start.
How much does a solar permit cost in El Paso?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the permit office at 915-212-0104.
Where do you apply for a solar permit in El Paso?
You can apply through the El Paso permit portal or contact the City of El Paso Planning and Inspections Department (One Stop Shop) directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in El Paso?
Under Texas law (Tex. Occupations Code 1305.003(a)(6), 1301.051; Tex. Local Government Code 233.157(c)): Texas licenses individual construction trades rather than general contractors, so no state statute requires a license to act as your own general contractor on your own house. For electrical work, the state licensing law does not apply to work performed in or on a dwelling by a person who owns and resides in it, but only where no municipal ordinance specifically regulates that work, so city electrical licensing and permit rules still control inside city limits (Occupations Code 1305.003(a)(6)). For plumbing, a property owner does not need a state license to perform plumbing in the owner's homestead (Occupations Code 1301.051). In opt-in counties' unincorporated areas, an individual who builds their own house or acts as their own contractor is exempt from the Class C misdemeanor penalty for inspection notice failures if they intend to use the home as their primary residence (Local Government Code 233.157(c)). None of these exemptions waive local permit or inspection requirements where they apply. Confirm how El Paso applies this before you apply.

From the Library

Solar Permit in other Texas localities

Everything above, sourced

How this solar permit page for El Paso was verified. 2 official sources: elpasotexas.gov, elpasotexas.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of El Paso Planning and Inspections Department (One Stop Shop). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required