Electrical Permit in Arlington, Texas

Permit required

Yes, a permit is required

Before installing any electrical equipment or making any alteration or addition to existing equipment on any building, structure or premises in Arlington, unless the wiring, apparatus or equipment operates at 24 volts or less.

Confirmed on official page Verified City of Arlington Planning and Development Services Department, Building Inspections Division

By Mario Bailey, verified against official sources

Quick answer

This is the Texas jurisdictional split in practice: electricians are licensed by the Texas Department of Licensing and Regulation, but the electrical permit itself is issued by the City of Arlington's Office of Electrical Inspection. The city's Electrical Chapter, which adopts the 2020 National Electrical Code, requires a permit before any electrical equipment is installed or any alteration or addition is made to existing equipment, with no permit required for wiring, apparatus or equipment of 24 volts or less. A separate permit is required for each separate building, store space or apartment. Permits are issued only to a registrant, so the contractor must hold an active City of Arlington business registration in addition to a state license.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing any electrical equipment or making any alteration or addition to existing equipment on any building, structure or premises in Arlington, unless the wiring, apparatus or equipment operates at 24 volts or less.

What an electrical permit costs in Arlington

Line item
electrical permitBy formulaPlanning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No. 26 - 151, Building Permit for Electrical: "Per Trade - Commercial and Residential New Construction Permits $100.00" where associated with a building permit. Not associated with a building permit: "Base permit fee $100.00" plus items such as "Services and sub panels; new, repair, replace (each) Up to and including 200 amps $35.00", "Over 200 amps and up to and including 400 amps $60.00", "Electrical Vehicle Charging Station 120 - 480 Volt $30.00 each", "Temporary pole $25.00", and "Hot-tubs, Spas, and Swimming Pools (above and below ground)- No Charge $0.00".
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Arlington compares in Texas

JurisdictionPermit needed?Threshold
Arlingtonthis pagePermit requiredNot specified
AustinPermit requiredNot specified
Corpus ChristiPermit requiredAn electrical permit is needed to replace a meter loop or panel, add receptacles or outlets, add circuits or lights, add a dryer plug, rewire a house, or add solar panels; communications cabling and low voltage work fall outside what the city permits at all.
DallasPermit requiredNot specified
El PasoPermit requiredReplacing a switch, receptacle, fuse, fan, light fixture, or similar equipment without altering the mechanical, electrical, or plumbing system is exempt.
Fort WorthPermit requiredNot specified
HoustonPermit requiredNot specified

How to apply in Arlington

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of Arlington Planning and Development Services Department, Building Inspections Division sets the exact checklist for Arlington.

Where to apply in Arlington:

City of Arlington Planning and Development Services Department, Building Inspections Division

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Arlington permit portal or by phone at 817-459-6502.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in Arlington?
This is the Texas jurisdictional split in practice: electricians are licensed by the Texas Department of Licensing and Regulation, but the electrical permit itself is issued by the City of Arlington's Office of Electrical Inspection. The city's Electrical Chapter, which adopts the 2020 National Electrical Code, requires a permit before any electrical equipment is installed or any alteration or addition is made to existing equipment, with no permit required for wiring, apparatus or equipment of 24 volts or less. A separate permit is required for each separate building, store space or apartment. Permits are issued only to a registrant, so the contractor must hold an active City of Arlington business registration in addition to a state license. Always confirm with the City of Arlington Planning and Development Services Department, Building Inspections Division before starting.
How much does an electrical permit cost in Arlington?
Planning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No. 26 - 151, Building Permit for Electrical: "Per Trade - Commercial and Residential New Construction Permits $100.00" where associated with a building permit. Not associated with a building permit: "Base permit fee $100.00" plus items such as "Services and sub panels; new, repair, replace (each) Up to and including 200 amps $35.00", "Over 200 amps and up to and including 400 amps $60.00", "Electrical Vehicle Charging Station 120 - 480 Volt $30.00 each", "Temporary pole $25.00", and "Hot-tubs, Spas, and Swimming Pools (above and below ground)- No Charge $0.00". See the official fee schedule for current amounts.
Where do you apply for an electrical permit in Arlington?
You can apply through the Arlington permit portal or contact the City of Arlington Planning and Development Services Department, Building Inspections Division directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Arlington?
Under Texas law (Tex. Occupations Code 1305.003(a)(6), 1301.051; Tex. Local Government Code 233.157(c)): Texas licenses individual construction trades rather than general contractors, so no state statute requires a license to act as your own general contractor on your own house. For electrical work, the state licensing law does not apply to work performed in or on a dwelling by a person who owns and resides in it, but only where no municipal ordinance specifically regulates that work, so city electrical licensing and permit rules still control inside city limits (Occupations Code 1305.003(a)(6)). For plumbing, a property owner does not need a state license to perform plumbing in the owner's homestead (Occupations Code 1301.051). In opt-in counties' unincorporated areas, an individual who builds their own house or acts as their own contractor is exempt from the Class C misdemeanor penalty for inspection notice failures if they intend to use the home as their primary residence (Local Government Code 233.157(c)). None of these exemptions waive local permit or inspection requirements where they apply. Confirm how Arlington applies this before you apply.

From the Library

What else needs a permit in Arlington

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

Planning and Development Services Fee Schedule, Effective June 1, 2026, Resolution No, for every permit type below. The fee column shows what differs by project.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsheight of an uncovered deck above grade at any point26 - 151, Residential Construction: "Patio Cover, Screened Porch, Gazebo & Decks*...
Fence PermitIt dependsshare of one side of an existing fence being repaired or replaced26 - 151, Residential Construction: "Fence, Residential Lot $50.00 each"
HVAC PermitPermit requiredNot specified26 - 151, Mechanical: "Per Trade - Commercial and Residential New Construction Permits...
Patio PermitIt dependsheight of an uncovered patio above grade at any point26 - 151, Residential Construction: "Patio Cover, Screened Porch, Gazebo & Decks*...
Plumbing PermitPermit requiredNot specified26 - 151, Plumbing Permits: "Per Trade - Commercial and Residential New Construction...
Pool PermitIt dependsdepth of a prefabricated inflatable swimming pool26 - 151, Residential Construction: "Swimming Pool - In-ground (1 & 2 Family) (Spa...
Roof Replacement PermitIt dependsarea of roof covering material being replaced26 - 151, Residential Construction: "Reroof* $325.00".
Shed PermitIt dependsfloor area of a one-story detached tool or storage shed26 - 151, Residential Construction: "Portable Storage/Accessory Building 320 sq.ft.
Solar PermitPermit requiredNot specified26 - 151, Residential Construction: "Solar Panel* $325.00" and "Home Backup Power...

Electrical Permit in other Texas localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Arlington documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Arlington Planning and Development Services Department, Building Inspections Division. Rules change; confirm before you build. How we verify.