Plumbing Permit in Aurora, Colorado
It depends
Sometimes, depending on the project
Before replacing a water heater, before modifying the plumbing system, and before any work that touches in-wall piping or installs new piping. Swapping a sink, toilet, faucet or countertop without touching the piping needs no permit.
By Mario Bailey, verified against official sources
Quick answer
Aurora requires a plumbing permit for modifications to the plumbing system and always for a water heater replacement, with a set of published fixture-swap exemptions: toilets and sinks need no permit unless piping is installed or moved or in-wall pipes are touched, sewer line repairs need none unless new piping is installed, and water line repairs need none if the repair is considered minor. Homeowners may replace their own water heater and are then responsible for meeting code and passing inspection. New lawn sprinkler and irrigation systems take their own permit and an Aurora Water inspection.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before replacing a water heater, before modifying the plumbing system, and before any work that touches in-wall piping or installs new piping. Swapping a sink, toilet, faucet or countertop without touching the piping needs no permit.
What a plumbing permit costs in Aurora
How Aurora compares in Colorado
No Colorado jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Aurorathis page | It depends | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised... |
| Denver | Permit required | Valuation-based fee per CPD Table 1 with a $20 minimum |
| Jefferson County | Permit required | Plumbing permits not tied to an active building permit bill on the countywide... |
How to apply in Aurora
You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.
What most plumbing permit applications include:
- A permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
- The application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
- Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
- Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
- Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).
General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. City of Aurora Building Division, Development Services Department (Building Permit Center) sets the exact checklist for Aurora.
Where to apply in Aurora:
City of Aurora Building Division, Development Services Department (Building Permit Center)
- 15151 E. Alameda Parkway, Suite 2400, Aurora, CO 80012
- Phone: 303-739-7420
- Email: permitcounter@auroragov.org
Inspections and closing out your permit
Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.
- Piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
- Rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
- Rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
- The water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
- The framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
- At the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
- Final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Aurora permit portal or by phone at 303-739-7420.
Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Plumbing Permit checklist for Aurora
- Confirm the requirement. Sometimes, depending on the project. Usually needed: Before replacing a water heater, before modifying the plumbing system, and before any work that touches in-wall piping or installs new piping. Swapping a sink, toilet, faucet or countertop without touching the piping needs no permit.
- Budget the fee. On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)"), "Water Heater Replacement" and "Gas Pipe Installation or Modification" sit under the price heading "$99 EACH"; "Tankless Water Heater" under "$287 EACH"; "Furnace and Water Heater Replacement" at "$292"; and "Furnace, Air Conditioner and Water Heater Replacement" under "$336 EACH". City use tax on materials is collected separately: "The flat fee process has no effect on the calculation and collection of city use taxes.". Official fee schedule.
- Apply. You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit. Start at the Aurora permit portal.
- Keep the office details handy. City of Aurora Building Division, Development Services Department (Building Permit Center). Phone: 303-739-7420. Address: 15151 E. Alameda Parkway, Suite 2400, Aurora, CO 80012.
- Plan for inspections. Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a plumbing permit in Aurora?
- Aurora requires a plumbing permit for modifications to the plumbing system and always for a water heater replacement, with a set of published fixture-swap exemptions: toilets and sinks need no permit unless piping is installed or moved or in-wall pipes are touched, sewer line repairs need none unless new piping is installed, and water line repairs need none if the repair is considered minor. Homeowners may replace their own water heater and are then responsible for meeting code and passing inspection. New lawn sprinkler and irrigation systems take their own permit and an Aurora Water inspection. Always confirm with the City of Aurora Building Division, Development Services Department (Building Permit Center) before starting.
- How much does a plumbing permit cost in Aurora?
- On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)"), "Water Heater Replacement" and "Gas Pipe Installation or Modification" sit under the price heading "$99 EACH"; "Tankless Water Heater" under "$287 EACH"; "Furnace and Water Heater Replacement" at "$292"; and "Furnace, Air Conditioner and Water Heater Replacement" under "$336 EACH". City use tax on materials is collected separately: "The flat fee process has no effect on the calculation and collection of city use taxes.". See the official fee schedule for current amounts.
- Where do you apply for a plumbing permit in Aurora?
- You can apply through the Aurora permit portal or contact the City of Aurora Building Division, Development Services Department (Building Permit Center) directly. The links are listed on this page.
- Can a homeowner pull a plumbing permit themselves in Aurora?
- Under Colorado law (C.R.S. 12-115-116(2); C.R.S. 12-115-120(11)(c); C.R.S. 12-155-118(2); C.R.S. 12-155-120(11)(c)): Colorado's state electrical law has a homeowner exception: under C.R.S. 12-115-116(2), you do not need an electrician's license to do electrical work on your own property or residence, as long as all the work, other than maintenance or repair of existing systems, is inspected under the state law. The exception does not apply if the property is intended for sale or resale by someone in the construction or remodeling business, is rental property, or is generally open to the public. A homeowner performing work on the homeowner's home is a qualified applicant who may pull the state electrical permit under C.R.S. 12-115-120(11)(c), and plumbing mirrors this: C.R.S. 12-155-118(2) allows unlicensed plumbing work on your own property or residence with the same carve-outs, and C.R.S. 12-155-120(11)(c) lets a homeowner pull the state plumbing permit. The State Electrical and Plumbing Boards at DORA require that the homeowner personally perform the work, that it be inspected before cover and again at completion, and that it meet the National Electrical Code or the adopted plumbing codes. Colorado has no statewide general contractor license: Title 12 licenses electricians and plumbers at the state level, and general building contractors are licensed, if at all, by the individual city or county. Confirm how Aurora applies this before you apply.
From the Library
What else needs a permit in Aurora
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | deck height above grade at which a permit is required regardless of whether the deck is attached to the house | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Electrical Permit | It depends | Not specified | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Fence Permit | It depends | fence height at which a building permit is required | There is no fence line item on the 2026 flat-rate schedule (Form #A175, footer... |
| HVAC Permit | It depends | Not specified | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Patio Permit | It depends | height above grade of an uncovered concrete patio at which a permit is required | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Pool Permit | It depends | pool depth at which a building permit is required | There is no swimming pool or spa line item on the 2026 flat-rate schedule (Form #A175... |
| Roof Replacement Permit | Permit required | Not specified | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Shed Permit | It depends | shed floor area at which a building permit is required | There is no storage-shed line item on the 2026 flat-rate schedule (Form #A175, footer... |
| Solar Permit | Permit required | Not specified | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
Plumbing Permit in other Colorado localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Aurora documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with City of Aurora Building Division, Development Services Department (Building Permit Center). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Plumbing Permit requirements across Colorado localities
Permit office
City of Aurora Building Division, Development Services Department (Building Permit Center)
303-739-7420Permit portal