Solar Permit in Aurora, Colorado
Permit required
Yes, a permit is required
Before installing any solar photovoltaic or solar hot water system.
By Mario Bailey, verified against official sources
Quick answer
A solar PV system always requires a permit in Aurora, with no kilowatt or roof-area exception, and solar hot water systems are treated the same way. Both take a plan submittal and draw framing and electrical inspections. Aurora's Solar Photovoltaic Systems submittal guide requires a three-line electrical diagram plus a structural analysis of the existing roof system where it is not pre-engineered wood trusses.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before installing any solar photovoltaic or solar hot water system.
What a solar permit costs in Aurora
How Aurora compares in Colorado
No Colorado jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Aurorathis page | Permit required | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised... |
| Denver | Permit required | $50 flat permit fee for the solar photovoltaic portion of a project with no... |
| Jefferson County | Permit required | Solar permit fees are capped at $500 for residential systems, per the county... |
How to apply in Aurora
A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.
What most solar permit applications include:
- Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
- The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
- Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
- The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
- The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
- Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
- Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).
General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Aurora Building Division, Development Services Department (Building Permit Center) sets the exact checklist for Aurora.
Where to apply in Aurora:
City of Aurora Building Division, Development Services Department (Building Permit Center)
- 15151 E. Alameda Parkway, Suite 2400, Aurora, CO 80012
- Phone: 303-739-7420
- Email: permitcounter@auroragov.org
Inspections and closing out your permit
Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
- Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
- The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
- PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
- Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
- At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
- Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Aurora permit portal or by phone at 303-739-7420.
Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Solar Permit checklist for Aurora
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing any solar photovoltaic or solar hot water system.
- Budget the fee. On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)") the line item "Residential Solar PV System" is listed at "$500", "Commercial Solar PV System" at "$1000" and "Energy Storage System" at "$191". So a house PV permit is a flat $500.00 and a battery adds $191.00. City use tax on materials is collected separately: "The flat fee process has no effect on the calculation and collection of city use taxes.". Official fee schedule.
- Apply. A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit. Start at the Aurora permit portal.
- Keep the office details handy. City of Aurora Building Division, Development Services Department (Building Permit Center). Phone: 303-739-7420. Address: 15151 E. Alameda Parkway, Suite 2400, Aurora, CO 80012.
- Plan for inspections. Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a solar permit in Aurora?
- A solar PV system always requires a permit in Aurora, with no kilowatt or roof-area exception, and solar hot water systems are treated the same way. Both take a plan submittal and draw framing and electrical inspections. Aurora's Solar Photovoltaic Systems submittal guide requires a three-line electrical diagram plus a structural analysis of the existing roof system where it is not pre-engineered wood trusses. Always confirm with the City of Aurora Building Division, Development Services Department (Building Permit Center) before starting.
- How much does a solar permit cost in Aurora?
- On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)") the line item "Residential Solar PV System" is listed at "$500", "Commercial Solar PV System" at "$1000" and "Energy Storage System" at "$191". So a house PV permit is a flat $500.00 and a battery adds $191.00. City use tax on materials is collected separately: "The flat fee process has no effect on the calculation and collection of city use taxes.". See the official fee schedule for current amounts.
- Where do you apply for a solar permit in Aurora?
- You can apply through the Aurora permit portal or contact the City of Aurora Building Division, Development Services Department (Building Permit Center) directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Aurora?
- Under Colorado law (C.R.S. 12-115-116(2); C.R.S. 12-115-120(11)(c); C.R.S. 12-155-118(2); C.R.S. 12-155-120(11)(c)): Colorado's state electrical law has a homeowner exception: under C.R.S. 12-115-116(2), you do not need an electrician's license to do electrical work on your own property or residence, as long as all the work, other than maintenance or repair of existing systems, is inspected under the state law. The exception does not apply if the property is intended for sale or resale by someone in the construction or remodeling business, is rental property, or is generally open to the public. A homeowner performing work on the homeowner's home is a qualified applicant who may pull the state electrical permit under C.R.S. 12-115-120(11)(c), and plumbing mirrors this: C.R.S. 12-155-118(2) allows unlicensed plumbing work on your own property or residence with the same carve-outs, and C.R.S. 12-155-120(11)(c) lets a homeowner pull the state plumbing permit. The State Electrical and Plumbing Boards at DORA require that the homeowner personally perform the work, that it be inspected before cover and again at completion, and that it meet the National Electrical Code or the adopted plumbing codes. Colorado has no statewide general contractor license: Title 12 licenses electricians and plumbers at the state level, and general building contractors are licensed, if at all, by the individual city or county. Confirm how Aurora applies this before you apply.
From the Library
What else needs a permit in Aurora
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | deck height above grade at which a permit is required regardless of whether the deck is attached to the house | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Electrical Permit | It depends | Not specified | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Fence Permit | It depends | fence height at which a building permit is required | There is no fence line item on the 2026 flat-rate schedule (Form #A175, footer... |
| HVAC Permit | It depends | Not specified | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Patio Permit | It depends | height above grade of an uncovered concrete patio at which a permit is required | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Plumbing Permit | It depends | Not specified | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Pool Permit | It depends | pool depth at which a building permit is required | There is no swimming pool or spa line item on the 2026 flat-rate schedule (Form #A175... |
| Roof Replacement Permit | Permit required | Not specified | On the 2026 flat-rate schedule (Form #A175, footer "Flat-Rate Fee (Revised 08/2026)")... |
| Shed Permit | It depends | shed floor area at which a building permit is required | There is no storage-shed line item on the 2026 flat-rate schedule (Form #A175, footer... |
Solar Permit in other Colorado localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Aurora documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with City of Aurora Building Division, Development Services Department (Building Permit Center). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Solar Permit requirements across Colorado localities