Permit required

Quick answer

Cobb County Code Section 18-27 requires any contractor, owner, or authorized representative doing plumbing construction to obtain a permit from the Development and Inspections Division before performing the work. The county's Building Permit Fee Schedule separately confirms Plumbing as one of its named Trade permit categories.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Cobb County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before any plumbing installation, repair, or replacement

What plumbing permit costs in Cobb County

Plumbing work is billed as an $80 trade permit under the Cobb County Building Permit Fee Schedule effective July 1, 2024, plus the $15 technology fee that applies to all permit types.

Official fee schedule

How to apply in Cobb County

You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.

What most plumbing permit applications include:

  • A permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
  • The application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
  • Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
  • Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
  • Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).

General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. Cobb County Community Development Agency, Development and Inspections Division sets the exact checklist for Cobb County.

Where to apply in Cobb County:

Cobb County Community Development Agency, Development and Inspections Division

Inspections and closing out your permit

Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.

  1. Piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
  2. Rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
  3. Rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
  4. The water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
  5. The framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
  6. At the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
  7. Final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Cobb County permit portal or by phone at (770) 528-2060.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a plumbing permit in Cobb County?
Cobb County Code Section 18-27 requires any contractor, owner, or authorized representative doing plumbing construction to obtain a permit from the Development and Inspections Division before performing the work. The county's Building Permit Fee Schedule separately confirms Plumbing as one of its named Trade permit categories. Always confirm with the Cobb County Community Development Agency, Development and Inspections Division before starting.
How much does a plumbing permit cost in Cobb County?
Plumbing work is billed as an $80 trade permit under the Cobb County Building Permit Fee Schedule effective July 1, 2024, plus the $15 technology fee that applies to all permit types. See the official fee schedule for current amounts.
Where do you apply for a plumbing permit in Cobb County?
You can apply through the Cobb County permit portal or contact the Cobb County Community Development Agency, Development and Inspections Division directly. The links are listed on this page.

From the Library

What else needs a permit in Cobb County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedDecks are subject to a $100 site plan review fee in addition to the tiered residential...
Electrical PermitPermit requiredNot specifiedElectrical work is billed as an $80 trade permit under the Cobb County Building Permit...
HVAC PermitPermit requiredNot specifiedHVAC and mechanical work is billed as an $80 trade permit under the Cobb County Buildin...
Pool PermitPermit requiredNot specifiedPool permits carry a $250 minimum fee under the Cobb County Building Permit Fee Schedul...
Shed PermitPermit requiredNot specifiedAccessory structures are subject to a $100 site plan review fee in addition to the tier...
Solar PermitPermit requiredNot specifiedFee follows the small residential construction cost table, $80 base for cost up to $15,...

Plumbing Permit in other Georgia localities

Official sources

Verified by a person against the sources above on 2026-07-06, not confirmed with Cobb County Community Development Agency, Development and Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: 2026-07-06Report an error on this page

Compare Plumbing Permit requirements across Georgia localities