Permit required

Quick answer

Cobb County Code Section 18-27 requires any contractor, owner, or authorized representative doing electrical construction to obtain a permit from the Development and Inspections Division before performing the work. The county's Building Permit Fee Schedule separately confirms Electrical as one of its named Trade permit categories.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Cobb County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before any electrical installation, repair, or replacement

What electrical permit costs in Cobb County

Electrical work is billed as an $80 trade permit under the Cobb County Building Permit Fee Schedule effective July 1, 2024, plus the $15 technology fee that applies to all permit types.

Official fee schedule

How to apply in Cobb County

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Cobb County Community Development Agency, Development and Inspections Division sets the exact checklist for Cobb County.

Where to apply in Cobb County:

Cobb County Community Development Agency, Development and Inspections Division

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Cobb County permit portal or by phone at (770) 528-2060.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a electrical permit in Cobb County?
Cobb County Code Section 18-27 requires any contractor, owner, or authorized representative doing electrical construction to obtain a permit from the Development and Inspections Division before performing the work. The county's Building Permit Fee Schedule separately confirms Electrical as one of its named Trade permit categories. Always confirm with the Cobb County Community Development Agency, Development and Inspections Division before starting.
How much does a electrical permit cost in Cobb County?
Electrical work is billed as an $80 trade permit under the Cobb County Building Permit Fee Schedule effective July 1, 2024, plus the $15 technology fee that applies to all permit types. See the official fee schedule for current amounts.
Where do you apply for a electrical permit in Cobb County?
You can apply through the Cobb County permit portal or contact the Cobb County Community Development Agency, Development and Inspections Division directly. The links are listed on this page.

From the Library

What else needs a permit in Cobb County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedDecks are subject to a $100 site plan review fee in addition to the tiered residential...
HVAC PermitPermit requiredNot specifiedHVAC and mechanical work is billed as an $80 trade permit under the Cobb County Buildin...
Plumbing PermitPermit requiredNot specifiedPlumbing work is billed as an $80 trade permit under the Cobb County Building Permit Fe...
Pool PermitPermit requiredNot specifiedPool permits carry a $250 minimum fee under the Cobb County Building Permit Fee Schedul...
Shed PermitPermit requiredNot specifiedAccessory structures are subject to a $100 site plan review fee in addition to the tier...
Solar PermitPermit requiredNot specifiedFee follows the small residential construction cost table, $80 base for cost up to $15,...

Electrical Permit in other Georgia localities

Official sources

Verified by a person against the sources above on 2026-07-06, not confirmed with Cobb County Community Development Agency, Development and Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: 2026-07-06Report an error on this page

Compare Electrical Permit requirements across Georgia localities