Georgia / DeKalb County

Electrical Permit in DeKalb County, Georgia

Permit required

Yes, a permit is required

Before any new wiring, service change, panel change, added circuit or fixture installation, and before power is restored to a residence that has been disconnected for six months or more.

Confirmed on official page Verified DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division

By Mario Bailey, verified against official sources

Quick answer

An electrical permit is required in unincorporated DeKalb County and has to be submitted by a licensed electrical contractor. Sec. 7-30(a) requires a permit before construction, alteration or repair of an electrical system other than ordinary repairs, and the county's own exemptions in Sec. 7-30(d)(2) reach only lamp replacement, plugging approved portable equipment into existing receptacles, radio and television transmitting equipment, and temporary testing systems. DeKalb is unusual in also requiring a reinspection permit before power is restored to any building disconnected for six months or more.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before any new wiring, service change, panel change, added circuit or fixture installation, and before power is restored to a residence that has been disconnected for six months or more.

What an electrical permit costs in DeKalb County

Line item
electrical permitBy formulaElectrical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE $120 Additional $200 for Fire Alarm Systems (Fire Review & Inspection Fee)" Per item charges include a 200 amp service at $16.00, a panel change at $50.00, residential outlets, switches and lights at $2.00 each, a water heater or clothes dryer circuit at $8.00 each, swimming pools at $50.00 and spas, hot tubs and jacuzzis at $25.00. Electrical re-inspection fees are $25.00 for the first, $50.00 for the second and $100.00 for the third and after.

How DeKalb County compares in Georgia

No Georgia jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
AtlantaPermit requiredNot published
Cobb CountyPermit requiredElectrical work is billed as an $80 trade permit under the Cobb County...
DeKalb Countythis pagePermit requiredElectrical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE...
Gwinnett CountyIt dependsPlanning and Development Fee Schedule, "Building Permit Fees (Effective July...

How to apply in DeKalb County

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division sets the exact checklist for DeKalb County.

Where to apply in DeKalb County:

DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the DeKalb County permit portal or by phone at 404-371-2155 (option 3).

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in DeKalb County?
An electrical permit is required in unincorporated DeKalb County and has to be submitted by a licensed electrical contractor. Sec. 7-30(a) requires a permit before construction, alteration or repair of an electrical system other than ordinary repairs, and the county's own exemptions in Sec. 7-30(d)(2) reach only lamp replacement, plugging approved portable equipment into existing receptacles, radio and television transmitting equipment, and temporary testing systems. DeKalb is unusual in also requiring a reinspection permit before power is restored to any building disconnected for six months or more. Always confirm with the DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division before starting.
How much does an electrical permit cost in DeKalb County?
Electrical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE $120 Additional $200 for Fire Alarm Systems (Fire Review & Inspection Fee)" Per item charges include a 200 amp service at $16.00, a panel change at $50.00, residential outlets, switches and lights at $2.00 each, a water heater or clothes dryer circuit at $8.00 each, swimming pools at $50.00 and spas, hot tubs and jacuzzis at $25.00. Electrical re-inspection fees are $25.00 for the first, $50.00 for the second and $100.00 for the third and after. Contact the office for current amounts.
Where do you apply for an electrical permit in DeKalb County?
You can apply through the DeKalb County permit portal or contact the DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in DeKalb County?
Under Georgia law (O.C.G.A. 43-41-17(h); O.C.G.A. 43-14-13(d); O.C.G.A. 43-14-14): Georgia's contractor licensing law has a true owner builder exemption at O.C.G.A. 43-41-17(h), not 43-41-17(b). A property owner may construct a building on land the owner owns and act as his or her own contractor, personally providing direct supervision and management, but only if the finished building is intended solely for occupancy by the owner and the owner's family, firm, or corporation, is not for use by the general public, and is not offered for sale or lease. If the owner sold or transferred a self-built structure within the prior 24 months, measured from that structure's certificate of occupancy, the law presumes the new project was not really for personal occupancy and the exemption is unavailable without a license. The owner may not delegate supervision to any unlicensed person, and all work must still comply with county or municipal permitting and inspection requirements. For trade work, O.C.G.A. 43-14-13(d) separately allows an individual to install, alter, or repair plumbing, heating and air conditioning fixtures, and electrical or low-voltage wiring in a residential dwelling the individual owns or occupies, again in conformity with the codes and any local permit and inspection rules. Unlicensed trade work outside these exemptions is a misdemeanor punishable by up to a $1,000 fine or six months imprisonment or both (O.C.G.A. 43-14-14). Confirm how DeKalb County applies this before you apply.

From the Library

What else needs a permit in DeKalb County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Fence PermitIt dependsheight of the fenceBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
HVAC PermitPermit requiredNot specifiedMechanical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE $120.
Patio PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Plumbing PermitPermit requiredNot specifiedPlumbing Permit Application: "Fee Schedule: MINIMUM FEE $120 Additional $200 for Fire...
Pool PermitIt dependsprefabricated pools installed entirely above groundBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Roof Replacement PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Shed PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Solar PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...

Electrical Permit in other Georgia localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not DeKalb County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across Georgia localities

Look up an existing DeKalb County permit record