Georgia / DeKalb County

Electrical Permit in DeKalb County, Georgia

Permit required

Yes, a permit is required

Before any new wiring, service change, panel change, added circuit or fixture installation, and before power is restored to a residence that has been disconnected for six months or more.

Quick answer

An electrical permit is required in unincorporated DeKalb County and has to be submitted by a licensed electrical contractor. Sec. 7-30(a) requires a permit before construction, alteration or repair of an electrical system other than ordinary repairs, and the county's own exemptions in Sec. 7-30(d)(2) reach only lamp replacement, plugging approved portable equipment into existing receptacles, radio and television transmitting equipment, and temporary testing systems. DeKalb is unusual in also requiring a reinspection permit before power is restored to any building disconnected for six months or more.

Issued by
DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What an electrical permit costs in DeKalb County

Fee schedule in force
Official scheduleRead .
Published in
DeKalb Development Services Fee Schedule (Last Update: 6/8/2026), Electrical Permit:

"Minimum Permit Fee: $100 ($20 Technology Fee is additional)".

Per item charges include a panel change at $50/per, residential outlets, switches and lights at $2.00, a water heater or clothes dryer at $8.00, swimming pools at $50.00 and spas, hot tubs and jacuzzi at $25.00.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How DeKalb County compares in Georgia

JurisdictionPermit needed?Threshold
AtlantaIt dependsOn existing single-family, two-family or duplex homes the city's exempt list covers repair or replacement of existing electrical outlets and existing electrical fixtures, and installation, repair or replacement of low voltage systems. The same list says repair work with a total valuation of less than $10,000.00 needs no permit or permit fee, while the city's help-line guidance says any electrical repair needs a permit, so ask the Trade Permits Division before relying on the repair exemption. Other electrical work needs a permit.
Cobb CountyPermit requiredAny size
DeKalb Countythis pagePermit requiredAny size
Gwinnett CountyIt dependsBefore erecting, installing, enlarging, altering, repairing, removing, converting or...

How to apply in DeKalb County

General guide, not specific to this office

What an electrical permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an electrical permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division

Permitting activity in DeKalb County

In 2025, DeKalb County authorized permits for 1,321 new residential housing units (805 single-family, 516 in multi-family buildings), valued at $420M, up from 1,238 the year before. That works out to about 1.7 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 774,394.

What else needs a permit in DeKalb County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeSee schedule
Fence PermitIt dependsheight of the fenceSee schedule
HVAC PermitPermit requiredAny sizeDeKalb Development Services Fee Schedule (Last Update: 6/8/2026), HVAC Permits: "Minimum Permit Fee: $100 ($20 Technology Fee is additional)"
Patio PermitPermit requiredAny sizeSee schedule
Plumbing PermitPermit requiredAny sizeDeKalb Development Services Fee Schedule (Last Update: 6/8/2026), Plumbing Permits: "Minimum Permit Fee: $100 ($20 Technology Fee is additional)"
Pool PermitIt dependsprefabricated pools installed entirely above groundDeKalb Development Services Fee Schedule (Last Update: 6/8/2026), Building Permit Fee Schedule: "Minimum Permit Fee: $175 ($20 Technology Fee is Additional)"
Roof Replacement PermitPermit requiredAny sizeSee schedule
Shed PermitPermit requiredAny sizeSee schedule
Solar PermitPermit requiredAny sizeDeKalb Development Services Fee Schedule (Last Update: 6/8/2026), Building Permit Fee Schedule: "Minimum Permit Fee: $175 ($20 Technology Fee is Additional)"

Frequently asked questions

Do you need an electrical permit in DeKalb County?
Yes, before any new wiring, service change, panel change, added circuit or fixture installation, and before power is restored to a residence that has been disconnected for six months or more. If you are unsure how that applies to your project, call the permit office at 404-371-2155 (option 3) before you start.
How much does an electrical permit cost in DeKalb County?
The fee wording from the official schedule is in the cost table on this page, as we read it on 11 Nov 2026. For the figure on your own project, call the permit office at 404-371-2155 (option 3).
Where do you apply for an electrical permit in DeKalb County?
You can apply through the DeKalb County permit portal or contact the DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in DeKalb County?
Under Georgia law (O.C.G.A. 43-41-17(h); O.C.G.A. 43-14-19(d)(1); O.C.G.A. 43-14-17(g) (chapter 43-14 as reenacted by SB 553, effective July 1, 2026)): Georgia's contractor licensing law has a true owner builder exemption at O.C.G.A. 43-41-17(h), not 43-41-17(b). A property owner may construct a building on land the owner owns and act as his or her own contractor, personally providing direct supervision and management, but only if the finished building is intended solely for occupancy by the owner and the owner's family, firm, or corporation, is not for use by the general public, and is not offered for sale or lease. If the owner sold or transferred a self-built structure within the prior 24 months, measured from that structure's certificate of occupancy, the law presumes the new project was not really for personal occupancy and the exemption is unavailable without a license. The owner may not delegate supervision to any unlicensed person, and all work must still comply with county or municipal permitting and inspection requirements. For trade work, O.C.G.A. 43-14-19(d)(1) separately allows an individual to install, alter, or repair plumbing, heating and air conditioning fixtures, and electrical or low-voltage wiring in a residential dwelling the individual owns or occupies, again in conformity with the codes and any local permit and inspection rules. Unlicensed trade work outside these exemptions is a misdemeanor punishable by up to a $1,000 fine or six months imprisonment or both (O.C.G.A. 43-14-17(g), as reenacted by SB 553, effective July 1, 2026). Confirm how DeKalb County applies this before you apply.

From the Library

Electrical Permit in other Georgia localities

Everything above, sourced

How this electrical permit page for DeKalb County was verified. 1 official source: dekalbcountyga.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page