Georgia / DeKalb County

Pool Permit in DeKalb County, Georgia

It depends

Sometimes, depending on the project

Before excavating or installing an in ground, on ground or above ground pool, except a prefabricated pool less than 24 inches deep set entirely above ground. Written Board of Health approval has to be in hand before the building permit issues.

Confirmed on official page Verified DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division

By Mario Bailey, verified against official sources

Quick answer

An in ground or permanent above ground pool needs a DeKalb building permit plus a separate electrical permit, and the building permit only issues after written approval from the DeKalb County Board of Health. Sec. 7-30(d)(1)(F) is the one carve out: prefabricated pools less than 24 inches deep installed entirely above ground need no permit. Required inspections run initial environmental, footing, swim basket, electrical rough, electrical final and building final, in that order, and skipping one triggers an immediate stop work order.

Typical threshold: prefabricated pools installed entirely above ground.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before excavating or installing an in ground, on ground or above ground pool, except a prefabricated pool less than 24 inches deep set entirely above ground. Written Board of Health approval has to be in hand before the building permit issues.

What a pool permit costs in DeKalb County

Line item
pool permitBy formulaBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum Permit Fee; $50 Certificate of Occupancy or Certificate of Completion). Some commercial projects require Fire Review & Inspection Fees ($100 Fire Life Safety Review; $100 Fire Site Review; $100 Fire Inspection). Please note that additional fees may apply depending on the type of permit being submitted." DeKalb does not currently publish a full building permit fee schedule online; the fee schedule address printed on the application form no longer resolves to any fee document. The separate electrical permit is priced on the Electrical Permit Application (revised 07/09/2025) at "SWIMMING POOLS NO. AT $50.00", with "Fee Schedule: MINIMUM FEE $120 Additional $200 for Fire Alarm Systems (Fire Review & Inspection Fee)" governing the electrical permit as a whole.

How DeKalb County compares in Georgia

JurisdictionPermit needed?Threshold
AtlantaPermit requiredNot specified
Cobb CountyPermit requiredNot specified
DeKalb Countythis pageIt dependsprefabricated pools installed entirely above ground
Gwinnett CountyIt dependsprefabricated pools installed entirely above ground that also hold no more than 5,000 gallons

Closest pool permit thresholds outside Georgia

Jurisdictions we cover whose limit sits nearest DeKalb County's 24 inches in depth.

How to apply in DeKalb County

A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.

What most pool permit applications include:

  • Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
  • The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
  • For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
  • A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
  • Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
  • The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).

General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division sets the exact checklist for DeKalb County.

Where to apply in DeKalb County:

DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division

Inspections and closing out your permit

Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.

  1. Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
  2. A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
  3. A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
  4. A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
  5. At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the DeKalb County permit portal or by phone at 404-371-2155 (option 3).

Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a pool permit in DeKalb County?
An in ground or permanent above ground pool needs a DeKalb building permit plus a separate electrical permit, and the building permit only issues after written approval from the DeKalb County Board of Health. Sec. 7-30(d)(1)(F) is the one carve out: prefabricated pools less than 24 inches deep installed entirely above ground need no permit. Required inspections run initial environmental, footing, swim basket, electrical rough, electrical final and building final, in that order, and skipping one triggers an immediate stop work order. Prefabricated pools installed entirely above ground. Always confirm with the office before starting.
How much does a pool permit cost in DeKalb County?
Building Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum Permit Fee; $50 Certificate of Occupancy or Certificate of Completion). Some commercial projects require Fire Review & Inspection Fees ($100 Fire Life Safety Review; $100 Fire Site Review; $100 Fire Inspection). Please note that additional fees may apply depending on the type of permit being submitted." DeKalb does not currently publish a full building permit fee schedule online; the fee schedule address printed on the application form no longer resolves to any fee document. The separate electrical permit is priced on the Electrical Permit Application (revised 07/09/2025) at "SWIMMING POOLS NO. AT $50.00", with "Fee Schedule: MINIMUM FEE $120 Additional $200 for Fire Alarm Systems (Fire Review & Inspection Fee)" governing the electrical permit as a whole. Contact the office for current amounts.
Where do you apply for a pool permit in DeKalb County?
You can apply through the DeKalb County permit portal or contact the DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division directly. The links are listed on this page.
Can a homeowner pull a pool permit themselves in DeKalb County?
Under Georgia law (O.C.G.A. 43-41-17(h); O.C.G.A. 43-14-13(d); O.C.G.A. 43-14-14): Georgia's contractor licensing law has a true owner builder exemption at O.C.G.A. 43-41-17(h), not 43-41-17(b). A property owner may construct a building on land the owner owns and act as his or her own contractor, personally providing direct supervision and management, but only if the finished building is intended solely for occupancy by the owner and the owner's family, firm, or corporation, is not for use by the general public, and is not offered for sale or lease. If the owner sold or transferred a self-built structure within the prior 24 months, measured from that structure's certificate of occupancy, the law presumes the new project was not really for personal occupancy and the exemption is unavailable without a license. The owner may not delegate supervision to any unlicensed person, and all work must still comply with county or municipal permitting and inspection requirements. For trade work, O.C.G.A. 43-14-13(d) separately allows an individual to install, alter, or repair plumbing, heating and air conditioning fixtures, and electrical or low-voltage wiring in a residential dwelling the individual owns or occupies, again in conformity with the codes and any local permit and inspection rules. Unlicensed trade work outside these exemptions is a misdemeanor punishable by up to a $1,000 fine or six months imprisonment or both (O.C.G.A. 43-14-14). Confirm how DeKalb County applies this before you apply.

From the Library

What else needs a permit in DeKalb County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Electrical PermitPermit requiredNot specifiedElectrical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE $120...
Fence PermitIt dependsheight of the fenceBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
HVAC PermitPermit requiredNot specifiedMechanical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE $120.
Patio PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Plumbing PermitPermit requiredNot specifiedPlumbing Permit Application: "Fee Schedule: MINIMUM FEE $120 Additional $200 for Fire...
Roof Replacement PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Shed PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Solar PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...

Pool Permit in other Georgia localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not DeKalb County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page