Georgia / DeKalb County

HVAC Permit in DeKalb County, Georgia

Permit required

Yes, a permit is required

Before installing, replacing or extending a heating, cooling or ventilation system, before duct work, and before running or altering a gas line. The gas pressure test has to be applied for by the licensed contractor.

Confirmed on official page Verified DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division

By Mario Bailey, verified against official sources

Quick answer

A mechanical permit is required for HVAC work in unincorporated DeKalb County and has to be submitted by a licensed mechanical contractor. Sec. 7-30(a) requires a permit before construction, alteration or repair of a mechanical or gas system other than ordinary repairs. The carve outs in Sec. 7-30(d)(4) are narrow and cover portable equipment, piping inside regulated heating or cooling equipment, replacement of a part that does not alter approval or make the unit unsafe, and small self contained refrigeration systems.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing, replacing or extending a heating, cooling or ventilation system, before duct work, and before running or altering a gas line. The gas pressure test has to be applied for by the licensed contractor.

What an HVAC permit costs in DeKalb County

Line item
HVAC permitBy formulaMechanical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE $120. Additional $200 for Fire Suppression Systems (Fire Review & Inspection Fee)" Per item charges include A/C and refrigeration appliances up to 10 tons at $25.00 each, 11 to 30 tons at $35.00, boilers and heating appliances up to 300,000 BTU input at $25.00 each, duct work installation per system at $25.00, gas line per connection at $25.00 and residential vent fans at $20.00. Mechanical re-inspection fees are $25.00 for the first, $50.00 for the second and $100.00 for the third.

How DeKalb County compares in Georgia

No Georgia jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
AtlantaPermit requiredNot published
Cobb CountyPermit requiredHVAC and mechanical work is billed as an $80 trade permit under the Cobb...
DeKalb Countythis pagePermit requiredMechanical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE...
Gwinnett CountyIt dependsPlanning and Development Fee Schedule, "Building Permit Fees (Effective July...

How to apply in DeKalb County

A residential HVAC (mechanical) permit application must identify the covered equipment and scope of work, since installing, altering, or replacing a heating or cooling system is regulated work that cannot start until the application is submitted and the permit issued. The equipment itself must be picked by a real sizing calculation rather than a rule of thumb.

What most HVAC permit applications include:

  • A mechanical permit is required before anyone may install, alter, repair, remove, convert, or replace a heating, ventilating, or air conditioning system regulated by the code, and the work may not begin until the application is submitted and the permit is issued (IRC R105.1).
  • The application identifies the specific equipment being installed, such as a furnace, heat pump, or air conditioner, since the unit must be installed according to its listing and the manufacturer's installation instructions (IRC M1401.1).
  • The proposed equipment location must leave the clearances needed to clean coils and replace filters, blowers, motors, and controls after installation (IRC M1401.2).
  • The application carries the equipment sizing basis: ACCA Manual J building loads and Manual S equipment selection, or another approved sizing method, not a rule of thumb (IRC M1401.3).
  • For a split system, the work covered by the permit includes refrigerant suction line insulation, since the piping is inspected against that standard once installed (IRC M1411.6).

General submittal guidance from International Residential Code (IRC), 2021 edition, Chapter 1 (Permits) and Chapter 14 (Heating and Cooling Equipment and Appliances). Source. DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division sets the exact checklist for DeKalb County.

Where to apply in DeKalb County:

DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division

Inspections and closing out your permit

Mechanical work gets a rough in inspection after the ductwork, refrigerant lines, and gas piping are in but before they are covered or concealed, followed by a final inspection that confirms the equipment operates correctly and its clearances, combustion air, and condensate disposal are in place. A straight equipment changeout with no new ductwork commonly gets a single final inspection instead of a separate rough in trip.

  1. Rough inspection of the mechanical and gas systems must be made before the work is covered or concealed, before fixtures or appliances are set or installed, and before the framing inspection (IRC R109.1.2).
  2. Where a cooling coil is added to an existing warm air furnace, the rough in confirms the coil is not installed upstream of the heat exchanger unless the furnace is listed for it, and that the blower can handle the added static pressure (IRC M1411.2).
  3. The rough in and final both confirm the appliance access opening and working space are large enough to service the unit (IRC M1305.1).
  4. At final inspection, the inspector verifies the equipment has adequate combustion air, with openings kept clear for the distance the code requires (IRC M1402.3).
  5. Final inspection also checks that the condensate line drains to an approved point of disposal with the required slope and does not create a nuisance (IRC M1411.3).
  6. For a straight equipment changeout with no new ductwork, many permit offices require only a single final inspection, while a new installation still gets a rough in inspection before the final (common local inspection practice).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the DeKalb County permit portal or by phone at 404-371-2155 (option 3).

Inspection sequence from International Residential Code (IRC), 2021 edition, Section R109 (Required Inspections) and Chapter 14 (Heating and Cooling Equipment and Appliances). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an HVAC permit in DeKalb County?
A mechanical permit is required for HVAC work in unincorporated DeKalb County and has to be submitted by a licensed mechanical contractor. Sec. 7-30(a) requires a permit before construction, alteration or repair of a mechanical or gas system other than ordinary repairs. The carve outs in Sec. 7-30(d)(4) are narrow and cover portable equipment, piping inside regulated heating or cooling equipment, replacement of a part that does not alter approval or make the unit unsafe, and small self contained refrigeration systems. Always confirm with the DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division before starting.
How much does an HVAC permit cost in DeKalb County?
Mechanical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE $120. Additional $200 for Fire Suppression Systems (Fire Review & Inspection Fee)" Per item charges include A/C and refrigeration appliances up to 10 tons at $25.00 each, 11 to 30 tons at $35.00, boilers and heating appliances up to 300,000 BTU input at $25.00 each, duct work installation per system at $25.00, gas line per connection at $25.00 and residential vent fans at $20.00. Mechanical re-inspection fees are $25.00 for the first, $50.00 for the second and $100.00 for the third. Contact the office for current amounts.
Where do you apply for an HVAC permit in DeKalb County?
You can apply through the DeKalb County permit portal or contact the DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division directly. The links are listed on this page.
Can a homeowner pull an HVAC permit themselves in DeKalb County?
Under Georgia law (O.C.G.A. 43-41-17(h); O.C.G.A. 43-14-13(d); O.C.G.A. 43-14-14): Georgia's contractor licensing law has a true owner builder exemption at O.C.G.A. 43-41-17(h), not 43-41-17(b). A property owner may construct a building on land the owner owns and act as his or her own contractor, personally providing direct supervision and management, but only if the finished building is intended solely for occupancy by the owner and the owner's family, firm, or corporation, is not for use by the general public, and is not offered for sale or lease. If the owner sold or transferred a self-built structure within the prior 24 months, measured from that structure's certificate of occupancy, the law presumes the new project was not really for personal occupancy and the exemption is unavailable without a license. The owner may not delegate supervision to any unlicensed person, and all work must still comply with county or municipal permitting and inspection requirements. For trade work, O.C.G.A. 43-14-13(d) separately allows an individual to install, alter, or repair plumbing, heating and air conditioning fixtures, and electrical or low-voltage wiring in a residential dwelling the individual owns or occupies, again in conformity with the codes and any local permit and inspection rules. Unlicensed trade work outside these exemptions is a misdemeanor punishable by up to a $1,000 fine or six months imprisonment or both (O.C.G.A. 43-14-14). Confirm how DeKalb County applies this before you apply.

From the Library

What else needs a permit in DeKalb County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Electrical PermitPermit requiredNot specifiedElectrical Permit Application (revised 07/09/2025): "Fee Schedule: MINIMUM FEE $120...
Fence PermitIt dependsheight of the fenceBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Patio PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Plumbing PermitPermit requiredNot specifiedPlumbing Permit Application: "Fee Schedule: MINIMUM FEE $120 Additional $200 for Fire...
Pool PermitIt dependsprefabricated pools installed entirely above groundBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Roof Replacement PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Shed PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...
Solar PermitPermit requiredNot specifiedBuilding Permit Application (revised 01/01/2025): "Total Minimum Fees $245 ($195 Minimum...

HVAC Permit in other Georgia localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not DeKalb County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with DeKalb County Department of Planning and Sustainability, Permits, Plan Review and Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare HVAC Permit requirements across Georgia localities

Look up an existing DeKalb County permit record

Permit required
Get quotes