A building permit is required for all residential swimming pools in Atlanta. Architectural, structural, and site plans must be submitted to the Office of Buildings. Effective June 25, 2025, per Ordinance 25-O-1341, applicants whose projects may affect trees must schedule and complete an arborist meeting before submitting the permit application. Applications are submitted online through the Accela Citizen portal.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Atlanta, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before constructing any residential swimming pool

What pool permit costs in Atlanta

Atlanta does not publish a fee for this permit type in a schedule we can verify. Ask City of Atlanta Office of Buildings how the fee is calculated for your project.

How to apply in Atlanta

A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.

What most pool permit applications include:

  • Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
  • The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
  • For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
  • A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
  • Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
  • The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).

General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. City of Atlanta Office of Buildings sets the exact checklist for Atlanta.

Where to apply in Atlanta:

City of Atlanta Office of Buildings

Inspections and closing out your permit

Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.

  1. Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
  2. A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
  3. A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
  4. A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
  5. At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Atlanta permit portal or by phone at 404-330-6906.

Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Atlanta

In 2024, Atlanta authorized permits for 8,109 new residential housing units (791 single-family, 7,318 in multi-family buildings), valued at $1.4B, up from7,621 the year before. That works out to about 17.2 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 471,266.

About Atlanta

Atlanta has about 259,122 housing units. The median home is valued at $420,600, against a median household income of $81,938. About 46% of homes are owner-occupied, and the typical home was built around 1987.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a pool permit in Atlanta?
A building permit is required for all residential swimming pools in Atlanta. Architectural, structural, and site plans must be submitted to the Office of Buildings. Effective June 25, 2025, per Ordinance 25-O-1341, applicants whose projects may affect trees must schedule and complete an arborist meeting before submitting the permit application. Applications are submitted online through the Accela Citizen portal. Always confirm with the City of Atlanta Office of Buildings before starting.
How much does a pool permit cost in Atlanta?
Fees are set by Atlanta and are not published here. Contact the office for current amounts.
Where do you apply for a pool permit in Atlanta?
You can apply through the Atlanta permit portal or contact the City of Atlanta Office of Buildings directly. The links are listed on this page.

From the Library

What else needs a permit in Atlanta

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?Threshold
Deck PermitPermit requiredNot specified
Electrical PermitPermit requiredNot specified
Fence PermitPermit requiredNot specified
HVAC PermitPermit requiredNot specified
Plumbing PermitPermit requiredNot specified
Roof Replacement PermitPermit requiredNot specified
Shed PermitPermit requiredNot specified
Solar PermitPermit requiredNot specified

Pool Permit in other Georgia localities

Official sources

Verified by a person against the sources above on 2026-06-18, not confirmed with City of Atlanta Office of Buildings. Rules change; confirm before you build. How we verify.

Last checked: 2026-06-18Report an error on this page

Compare Pool Permit requirements across Georgia localities