Guide
How Much Is a Pool Permit? In-Ground Pool Fees in 27 Offices
What 27 building departments charge to permit a residential in-ground pool under their current schedules: from $75 to $3,821, middle of the range $313.17. Which fees include the electrical and plumbing permits and which leave them out, the add-ons for fences, heaters and screen enclosures, and how valuation-based offices price a pool.
An in-ground pool permit usually costs a few hundred dollars, but the number on the schedule often covers only part of the job. In the 27 offices below, the residential in-ground pool line runs from $75 to $3,821, and the middle of the range is $313.17. Some of those figures include the electrical and plumbing permits and every inspection; others are the building permit alone, with the electrical permit, the pool fence and the heater billed separately.
- Middle of 27 offices
- $313.17Residential in-ground pool line
- Lowest
- $75Oklahoma City, before its separate electrical and plumbing permits
- Highest
- $3,821Santa Clara County, plan check plus all trades
- Often extra
- Electrical, fence or barrier, heater, screen enclosure
- Valuation-based offices
- The fee follows the contract price
The next step: ask your pool builder for the permit total, every permit included, in writing. Which separate permits a pool tends to need is in our guide to why a pool permit is rarely one permit, and whether yours needs one at all is in our guide to when a pool needs a permit.
What 27 offices charge for an in-ground pool
Each row is the office’s line for a residential in-ground pool, as quoted on our page for that office, re-read against its schedule on November 11, 16 or 17, 2026, before state surcharges and levies (Florida, for example, adds 2.5% of the permit fee, at least $4.00). The middle column says what the figure covers, because that is where the real difference between offices lies.
| Office | What the fee covers | Fee, before state surcharges |
|---|---|---|
| Oklahoma City, OK | The pool permit; electrical and plumbing permits are separate | $75.00 |
| Jefferson County, CO | A zoning miscellaneous permit; the electrical permit for pool wiring is separate | $90.00 |
| Fort Worth, TX | The electrical “Swimming pools” line plus the $33.08 application and $16.87 technology fees; the schedule prints no building fee for a pool, so ask the city whether one is charged | $106.43 |
| Chandler, AZ | Flat residential pool permit; a spa is a separate $55 | $110.00 |
| Baltimore County, MD | The $100 building permit plus the $75 residential application fee; a pool fence is $35, the electrical permit $68, plumbing separate | $175.00 |
| Manatee County, FL | In-ground pool or spa permit | $244.00 |
| Howard County, MD | Private swimming pool, including fence and grading | $250.00 |
| Marion County, FL | Residential in-ground pool or spa | $250.00 |
| Town of Brookhaven, NY | In-ground pool fee; the schedule does not say whether its $100 application fee is added | $260.00 |
| Loudoun County, VA | Building and zoning permits outside an incorporated town; electrical and gas permits separate | $260.00 |
| St. Johns County, FL | $250 in-ground pool plus $16 permit issuance | $266.00 |
| Gilbert, AZ | Permanent in-ground pool or spa | $300.00 |
| Wake County, NC | All trades and two electrical grounding inspections | $300.00 |
| Santa Rosa County, FL | Residential in-ground pool, including an $85 site permit and $25 zoning review | $313.17 |
| El Paso, TX | $160 building plus $46 electrical and the $110 electrical base fee; the city’s technology fee is extra and not included | $316.00, plus the technology fee |
| Montgomery County, MD | Private in-ground pool including its fence; electrical permit separate | $360.68 |
| Cobb County, GA | $250 minimum, the $100 site plan review fee and the $15 technology fee | $365.00 |
| Leon County, FL | In-ground pool; a screen cage enclosure is $397.66 | $382.48 |
| San Antonio, TX | $414 residential pool fee plus 4% technology and 4% development services surcharges | $447.12 |
| Stafford County, VA | $229 review and $222 inspections, plus the county’s 2.75% technology fee; Virginia’s 2% state levy is extra | $463.40 |
| Hernando County, FL | $361 in-ground pool, plus the $93 technology fee and $15 unlicensed contractor surcharge the county applies to all building permits; a pool heater is $115 and a screen enclosure $140 | $469.00 |
| Fresno County, CA | Structural, plumbing and electrical included; gas heat adds $153.63 | $512.67 |
| Pinellas County, FL | Building, electric and plan review for a pool with deck worth up to $40,000, then $5.50 per $1,000 above | $550.00 |
| San Bernardino County, CA | Plan review and all inspections with a standard plan, plus the $57 intake processing fee ($805 otherwise) | $704.00 |
| Seminole County, FL | $860 residential pool plus the $75 administrative fee | $935.00 |
| Riverside County, CA | Residential pool or spa fixed fee; the schedule lists a pool final inspection at $338.60 as its own line | $999.30 |
| Santa Clara County, CA (unincorporated) | $1,890 plan check plus $1,931 inspection covering building, mechanical, electrical and plumbing | $3,821.00 |
Read the table by its middle column before its last one. Oklahoma City’s $75 and Santa Clara County’s $3,821 are not the same purchase: the first is one permit of three, the second is the whole set with plan check. Wake County ($300), Fresno County ($512.67) and San Bernardino County ($704) include every trade and are the clearest comparisons; Pinellas County ($550) includes building, electrical and plan review.
Where the fee follows the pool’s price
Some offices have no pool line and price the pool from its construction value, so the fee rises with the contract:
- Town of Hempstead, NY: $200 for the first $1,000 of estimated cost, then $18 for each additional $1,000 or fraction. That is $180 for every $10,000 of pool.
- Worcester, MA: $12 per $1,000 of construction value or fraction, $100 minimum, plus $85 on the electrical side for an in-ground pool.
- Henrico County, VA: $100 for the first $5,000, then $6 per additional $1,000 or fraction, plus a 2% state levy, with the total capped at $693.60.
- Pinellas County, FL: the flat $550 covers a pool and deck worth up to $40,000; above that it adds $5.50 per $1,000.
- Los Angeles County, CA (unincorporated): the building portion comes from the county’s valuation table plus a $41.35 issuance fee, and the schedules add $137.95 for the barrier inspection, $121.52 for the electrical permit on a new residential in-ground pool and $24.47 for each pool drainage trap.
For these offices, the number to check on your application is the declared value: it should match your contract.
The add-ons the pool line leaves out
The schedules above show the companion charges a pool tends to bring with it. Count each one your office lists:
- The barrier. A pool fence or barrier can be its own permit or inspection: $35 in Baltimore County (on top of its $175), $137.95 for the barrier inspection in Los Angeles County. Howard and Montgomery counties fold the fence into the pool fee.
- The electrical permit, where the pool line does not include it: $68 in Baltimore County, $85 in Worcester, $121.52 in Los Angeles County.
- A heater. $115 for a pool heating system in Hernando County; gas heat adds $153.63 in Fresno County.
- A screen enclosure, common in Florida: $140 in Hernando County, $397.66 in Leon County.
- A spa priced on its own, as in Chandler ($55).
What the pool itself costs
We did not find a current national price for building an in-ground pool from a public source we could verify and cite for this guide, so we do not print one. Get at least two written quotes, and ask each builder to show the permit fees as their own line, so you can compare them with the table above.
Before you sign a pool contract
- Ask the builder to list every permit the job needs where you live (pool, electrical, plumbing or gas, barrier, enclosure) and the fee for each.
- If your office prices by value, check that the declared value on the application matches the contract.
- Ask who schedules the inspections, in what order, and what happens to the schedule if the barrier is not in place by the final.
- Keep the permit and the final inspection with your house papers. An unpermitted pool is one of the items a buyer’s lender and inspector look for.
Every jurisdiction we cover has a pool permit page with its rule, the fee as quoted, the office and the portal; start from the pool permit index.
Sources
- Santa Clara County, California, Building Fee Schedule FY 2026-2027 (effective July 18, 2026): in-ground pool plan check $1,890.00 and inspection $1,931.00, the inspection including building, mechanical, electrical and plumbing permit fees. (accessed )
- San Bernardino County Code 16.0204(i)(1), effective July 1, 2026: swimming pools accessory to single-family dwellings, $647.00 with a standard plan and $748.00 otherwise, including plan review and all inspections; a $57.00 intake processing fee applies to each pool permit. (accessed )
- Pinellas County, Florida, FY27 Adopted BDRS user fees, Combination Permits IV-J: $550.00 for building, electric and plans review for a pool with deck up to $40,000 in value, plus $5.50 per $1,000 above. (accessed )
- Wake County, North Carolina, permits and inspections fee schedule: in-ground residential pool $300, including all trades and two electrical grounding inspections. (accessed )
- Henrico County, Virginia, residential building permit fees: pools as existing-dwelling additions or alterations, $100 for the first $5,000 plus $6 per additional $1,000, plus a 2% state levy, capped at $693.60. (accessed )
- Los Angeles County Building and Safety fee schedules effective July 1, 2026: $137.95 barrier inspection, $121.52 electrical for a new residential in-ground pool, $24.47 per pool drainage trap. (accessed )
- Orange County, Florida, Fee Directory FY 2026-2027: the state surcharge of 2.5% of each permit fee under Florida Statutes 468.631 and 553.721, minimum $4.00. (accessed )
- Hernando County, Florida, Resolution No. 2026-037 (fees effective March 3, 2026): the technology fee of $93.00 and unlicensed contractor surcharge of $15.00 applied to all building permits. (accessed )
Get rule-change alerts
We catch permit rule and fee changes in our verification passes and post them to the rule tracker. Get them by email instead.
We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Look up your locality
- Florida permit pages rules by locality
- California permit pages rules by locality
- Texas permit pages rules by locality
- Maryland permit pages rules by locality
- Virginia permit pages rules by locality