Quick answer
Swimming pool and spa permits are submitted through Gilbert's One Stop Shop portal with a site plan, equipment location, electrical and gas diagrams, and structural details per the Miscellaneous Residential Checklist. Pools must be in side or rear yards at least 3 feet from property lines, and all pools must be enclosed by a 5 to 6 foot wall or fence whose openings reject a 4-inch sphere, with self-closing and self-latching gates, per Land Development Code 5.2.7. The residential swimming pool plan review goal is 3 working days.
Typical threshold: Non-permanent wading pools of rubber or plastic holding no more than 18 inches of water are excepted from the pool enclosure regulations.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help
Tell us where your project stands. Free to ask; no obligation.
Where we have a vetted local pro who handles permits in Gilbert, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
When a permit is usually needed
Before installing an in-ground or above-ground pool or spa
What your pool permit must meet in Arizona
Arizona has a statewide law requiring a compliant physical barrier around residential swimming pools and spas, independent of whichever local building code applies to the rest of a project.
- The barrier requirement applies to any pool or contained body of water at least 18 inches deep and wider than 8 feet, under A.R.S. 36-1681.
- The pool must be entirely enclosed by at least a 5 foot wall, fence, or other barrier measured on its exterior side, under A.R.S. 36-1681.
- The barrier cannot have openings large enough for a 4 inch diameter sphere to pass through, under A.R.S. 36-1681.
- Pool gates must be self-closing and self-latching, with the latch mounted at least 54 inches above the ground, under A.R.S. 36-1681.
Based on A.R.S. 36-1681 (Pool enclosures; requirements; exceptions; enforcement). Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.
What pool permit costs in Gilbert
Swimming pool permit fee $300 for permanent in-ground pools/spas and $140 for portable above-ground pools/spas (fee schedule revised 7/1/2026).
How Gilbert compares in Arizona
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Chandler | It depends | A prefabricated swimming pool less than 18 inches deep is exempt from a building permit; any pool or spa (in-ground or prefabricated) 18 inches deep or greater requires a permit, and a compliant safety barrier is required regardless of depth once a permit-triggering pool exists. |
| Gilbertthis page | Permit required | Non-permanent wading pools of rubber or plastic holding no more than 18 inches of water are excepted from the pool enclosure regulations. |
| Maricopa County | Permit required | Not specified |
| Mesa | Permit required | Not specified |
| Peoria | Permit required | Prefabricated above-ground pools accessory to a dwelling holding not more than 5,000 gallons are exempt from a pool permit, but the required barrier must still be permitted. |
| Phoenix | Permit required | Not specified |
| Scottsdale | Permit required | Not specified |
How to apply in Gilbert
A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.
What most pool permit applications include:
- Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
- The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
- For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
- A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
- Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
- The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).
General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. Development Services (Plan Review and Inspection Division) sets the exact checklist for Gilbert.
Where to apply in Gilbert:
Development Services (Plan Review and Inspection Division)
- 90 E. Civic Center Drive, Gilbert, AZ 85296
- Phone: (480) 503-6700
- Email: onestopshop@gilbertaz.gov
Inspections and closing out your permit
Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
- Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
- A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
- A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
- A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
- At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Gilbert permit portal or by phone at (480) 503-6700.
Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Pool Permit checklist for Gilbert
- Confirm the requirement. Yes, a permit is required. Typical threshold: Non-permanent wading pools of rubber or plastic holding no more than 18 inches of water are excepted from the pool enclosure regulations. Usually needed: Before installing an in-ground or above-ground pool or spa.
- Budget the fee. Swimming pool permit fee $300 for permanent in-ground pools/spas and $140 for portable above-ground pools/spas (fee schedule revised 7/1/2026). Official fee schedule.
- Apply. A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect. Start at the Gilbert permit portal.
- Keep the office details handy. Development Services (Plan Review and Inspection Division). Phone: (480) 503-6700. Address: 90 E. Civic Center Drive, Gilbert, AZ 85296.
- Plan for inspections. Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
Compiled from the official sources on this page. Last checked 2026-07-19.
The checklist stays on this page either way. We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Frequently asked questions
- Do you need a pool permit in Gilbert?
- Swimming pool and spa permits are submitted through Gilbert's One Stop Shop portal with a site plan, equipment location, electrical and gas diagrams, and structural details per the Miscellaneous Residential Checklist. Pools must be in side or rear yards at least 3 feet from property lines, and all pools must be enclosed by a 5 to 6 foot wall or fence whose openings reject a 4-inch sphere, with self-closing and self-latching gates, per Land Development Code 5.2.7. The residential swimming pool plan review goal is 3 working days. Always confirm with the Development Services (Plan Review and Inspection Division) before starting.
- How much does a pool permit cost in Gilbert?
- Swimming pool permit fee $300 for permanent in-ground pools/spas and $140 for portable above-ground pools/spas (fee schedule revised 7/1/2026). See the official fee schedule for current amounts.
- How long does a pool permit take in Gilbert?
- Plan review goal 3 working days per review for residential swimming pools. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a pool permit in Gilbert?
- You can apply through the Gilbert permit portal or contact the Development Services (Plan Review and Inspection Division) directly. The links are listed on this page.
From the Library
What else needs a permit in Gilbert
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | Decks are not addressed in Gilbert's published amendments to the IRC R105.2 exemption list, so permit requirements follow the unamended 2018 IRC provisions, which Gilbert's own pages do not restate. | If a permit is required, valuation-based building permit fee, minimum $50; |
| Electrical Permit | Permit required | Exemptions include work by a serving utility and solar or like-for-like water heating appliance replacements installed by an Arizona licensed contractor under amended exemption 16. | Individual Electrical Permit, residential: $150 (fee schedule revised 7/1/2026). |
| Fence Permit | It depends | Gilbert's amended IRC R105.2 exempts only fences not over 3 feet high; the Town's pool barrier policy statement says internal fences over 3 feet in height require building permits and inspections. | Walls/Fences fee $180 as a separate single-family permit, or $120 when combined with a... |
| HVAC Permit | Permit required | Gilbert's amended IRC R105.2 mechanical exemption list includes a replacement-based exemption and cross-references the exemption for water heating appliance replacements by an Arizona licensed contractor. | Individual Mechanical Permit, residential: $150 (fee schedule revised 7/1/2026). |
| Patio Permit | It depends | Only one-story detached non-habitable accessory structures up to 200 square feet are exempt from permit; attached patio covers and larger structures require a building permit. | Valuation-based building permit fee, minimum $50; |
| Plumbing Permit | Permit required | Water softeners and like-for-like replacements of gas or electric water heating appliances (not tankless) installed by an Arizona licensed contractor are exempt from permit. | Individual Plumbing Permit, residential: $150 (fee schedule revised 7/1/2026). |
| Roof Replacement Permit | It depends | Re-roofing not requiring a structural change is exempt from permit; a re-roof that involves a structural change requires a building permit. | If a permit is required, valuation-based building permit fee, minimum $50; |
| Shed Permit | It depends | Structures less than 200 square feet do not require a permit; a permit is required at 200 square feet or larger, or if the shed has electrical or plumbing utilities or is connected to the house or another structure. | Valuation-based building permit fee, minimum $50 for work valued up to $1,100; |
| Solar Permit | It depends | Solar photovoltaic systems and solar hot water heating systems are exempt from permit when installed by an Arizona licensed contractor using equipment listed and labeled by a nationally recognized third-party testing agency. | No Town permit fee when the licensed-contractor exemption applies; |
Pool Permit in other Arizona localities
Official sources
- https://www.gilbertaz.gov/home/showpublisheddocument/1570/638212305002530000
- https://www.gilbertaz.gov/home/showpublisheddocument/35215/637775971989000000
- https://www.gilbertaz.gov/home/showpublisheddocument/5883/639184173264330000
- https://www.gilbertaz.gov/home/showpublisheddocument/41852/639104883108270000
- https://www.gilbertaz.gov/departments/development-services/one-stop-shop
- https://www.bountifulutah.gov/file/ee478521-f791-4cee-a755-2d923ff70257
- https://www.azleg.gov/ars/36/01681.htm
Verified by a person against the sources above on 2026-07-19, not confirmed with Development Services (Plan Review and Inspection Division). Rules change; confirm before you build. How we verify.
Last checked: 2026-07-19Report an error on this page
Compare
Pool Permit across Arizona