Quick answer
A building permit must be obtained before constructing any residential pool, spa, or contained body of water exceeding 18 inches in depth or 8 feet in width in unincorporated Maricopa County. Permits for the pool barrier must also be issued before the barrier is installed, before plastering, and before filling the pool. Fast Track processing is available for custom and standard plan pools.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help
Tell us where your project stands. Free to ask; no obligation.
Where we have a vetted local pro who handles permits in Maricopa County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
When a permit is usually needed
Before constructing any outdoor pool spa or contained body of water over 18 inches deep or 8 feet wide
What your pool permit must meet in Arizona
Arizona has a statewide law requiring a compliant physical barrier around residential swimming pools and spas, independent of whichever local building code applies to the rest of a project.
- The barrier requirement applies to any pool or contained body of water at least 18 inches deep and wider than 8 feet, under A.R.S. 36-1681.
- The pool must be entirely enclosed by at least a 5 foot wall, fence, or other barrier measured on its exterior side, under A.R.S. 36-1681.
- The barrier cannot have openings large enough for a 4 inch diameter sphere to pass through, under A.R.S. 36-1681.
- Pool gates must be self-closing and self-latching, with the latch mounted at least 54 inches above the ground, under A.R.S. 36-1681.
Based on A.R.S. 36-1681 (Pool enclosures; requirements; exceptions; enforcement). Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.
What pool permit costs in Maricopa County
In-ground pools are valued at $200 per perimeter foot with the Table 1-A fee applied to that valuation; an above-ground pool or spa is a flat $75, per the Summary of the Fee Schedule.
How Maricopa County compares in Arizona
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Chandler | It depends | A prefabricated swimming pool less than 18 inches deep is exempt from a building permit; any pool or spa (in-ground or prefabricated) 18 inches deep or greater requires a permit, and a compliant safety barrier is required regardless of depth once a permit-triggering pool exists. |
| Gilbert | Permit required | Non-permanent wading pools of rubber or plastic holding no more than 18 inches of water are excepted from the pool enclosure regulations. |
| Maricopa Countythis page | Permit required | Not specified |
| Mesa | Permit required | Not specified |
| Peoria | Permit required | Prefabricated above-ground pools accessory to a dwelling holding not more than 5,000 gallons are exempt from a pool permit, but the required barrier must still be permitted. |
| Phoenix | Permit required | Not specified |
| Scottsdale | Permit required | Not specified |
How to apply in Maricopa County
A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.
What most pool permit applications include:
- Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
- The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
- For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
- A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
- Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
- The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).
General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. Maricopa County Planning and Development Department sets the exact checklist for Maricopa County.
Where to apply in Maricopa County:
Maricopa County Planning and Development Department
- 301 West Jefferson Street Phoenix AZ 85003
- Phone: 602-506-3301
Inspections and closing out your permit
Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
- Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
- A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
- A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
- A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
- At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Maricopa County permit portal or by phone at 602-506-3301.
Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Pool Permit checklist for Maricopa County
- Confirm the requirement. Yes, a permit is required. Usually needed: Before constructing any outdoor pool spa or contained body of water over 18 inches deep or 8 feet wide.
- Budget the fee. In-ground pools are valued at $200 per perimeter foot with the Table 1-A fee applied to that valuation; an above-ground pool or spa is a flat $75, per the Summary of the Fee Schedule. Official fee schedule.
- Apply. A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect. Start at the Maricopa County permit portal.
- Keep the office details handy. Maricopa County Planning and Development Department. Phone: 602-506-3301. Address: 301 West Jefferson Street Phoenix AZ 85003.
- Plan for inspections. Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
Compiled from the official sources on this page. Last checked 2026-06-18.
The checklist stays on this page either way. We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Permitting activity in Maricopa County
In 2024, Maricopa County authorized permits for 36,380 new residential housing units (21,667 single-family, 14,713 in multi-family buildings), valued at $9.1B, down from38,292 the year before. That works out to about 7.8 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 4,673,096.
About Maricopa County
Maricopa County has about 1,850,862 housing units. The median home is valued at $414,700, against a median household income of $85,518. About 65% of homes are owner-occupied, and the typical home was built around 1992.
Source: U.S. Census Bureau, American Community Survey 2023 5-year.
Frequently asked questions
- Do you need a pool permit in Maricopa County?
- A building permit must be obtained before constructing any residential pool, spa, or contained body of water exceeding 18 inches in depth or 8 feet in width in unincorporated Maricopa County. Permits for the pool barrier must also be issued before the barrier is installed, before plastering, and before filling the pool. Fast Track processing is available for custom and standard plan pools. Always confirm with the Maricopa County Planning and Development Department before starting.
- How much does a pool permit cost in Maricopa County?
- In-ground pools are valued at $200 per perimeter foot with the Table 1-A fee applied to that valuation; an above-ground pool or spa is a flat $75, per the Summary of the Fee Schedule. See the official fee schedule for current amounts.
- Where do you apply for a pool permit in Maricopa County?
- You can apply through the Maricopa County permit portal or contact the Maricopa County Planning and Development Department directly. The links are listed on this page.
From the Library
What else needs a permit in Maricopa County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Not specified | No deck-specific line item, valuation-based building permit fee under Table 1-A with a... |
| Electrical Permit | Permit required | Not specified | Flat rate by residential service size, $50 for 1-200 amps, $75 for 201-400 amps, $120 o... |
| Fence Permit | It depends | any fence over 1 foot in height requires at minimum a drainage clearance permit; fences over 6 feet require a building permit and zoning clearance | Valuation-based: fence material valued per lineal foot from $3 (barbed wire) to $18 (ir... |
| HVAC Permit | Permit required | Not specified | Flat fee of $50 for mechanical work under the Minor Self Service flat rate schedule, pe... |
| Patio Permit | It depends | attached patio cover or patio enclosure connected to the house requires a building permit; ground-level open patio slab does not | No flat patio fee; |
| Plumbing Permit | Permit required | Not specified | Flat fee of $50 to install or replace plumbing equipment, fixtures, or devices under Mi... |
| Roof Replacement Permit | It depends | re-roofing is exempt unless in a wildfire hazard zone or structural changes are involved | No permit or fee for a like-kind reroof using the same material as the original roofing... |
| Shed Permit | It depends | structures under 200 sq ft with no electrical plumbing or mechanical are exempt from a building permit; all others require a permit | Non-habitable accessory buildings are valued as a private garage with the Table 1-A fee... |
| Solar Permit | Permit required | Not specified | Roof-mounted residential solar is printed at $300 ($150 inspection plus $140 plan revie... |
Pool Permit in other Arizona localities
Official sources
Verified by a person against the sources above on 2026-06-18, not confirmed with Maricopa County Planning and Development Department. Rules change; confirm before you build. How we verify.
Last checked: 2026-06-18Report an error on this page
Compare
Pool Permit across Arizona