Pool Permit in Montgomery County, Maryland
Permit required
Yes, a permit is required
Before constructing altering or enlarging any residential swimming pool
Issued byMontgomery County Department of Permitting Services
By Mario Bailey, verified against official sources
- Permit fee
- $360.68
- from the published schedule
- Median to issue
- 35 days
- 107 records
- Typical job value
- $95,000
- declared valuation
Quick answer
A building permit and an electrical permit are both required for any residential swimming pool construction, alteration, or enlargement in Montgomery County. Homeowners may apply in their own name but a contractor on the permit must hold an MHIC license. Pools installed after January 1, 1990 must have a barrier at least 60 inches tall.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Pool builders handle the permit and its safety requirements as part of the job. Comparing a few bids before you sign is the useful next step.
Compare pool builder quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before constructing altering or enlarging any residential swimming pool
What your pool permit must meet in Maryland
Maryland regulates residential swimming pools and spas under a dedicated statewide code, the Maryland Swimming Pool and Spa Standards, rather than through the IRC used for the rest of the house. That chapter currently incorporates the 2024 International Swimming Pool and Spa Code.
- The state runs a dedicated pool and spa code: the 2024 International Swimming Pool and Spa Code (ISPSC) is incorporated by reference in the Maryland Swimming Pool and Spa Standards (COMAR 09.12.56.03).
- The Standards apply to every pool or spa whose building-permit application is received by a local jurisdiction on or after December 31, 2023 (COMAR 09.12.56.02).
- Residential (non-public) pools must be surrounded by a barrier that complies with the ISPSC barrier provisions, Sections 305.2.1 through 305.7 (COMAR 09.12.56.05).
Based on 2024 ISPSC, adopted via COMAR 09.12.56 Maryland Swimming Pool and Spa Standards. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.
What a pool permit costs in Montgomery County
How Montgomery County compares in Maryland
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Baltimore County | It depends | above-ground pool surface area, where the water depth is 24 inches or more; in-ground pools require a permit at any size |
| Howard County | Permit required | Not specified |
| Montgomery Countythis page | Permit required | Not specified |
| Prince George's County | It depends | prefabricated pools accessory to one- and two-family dwellings that are installed entirely above ground, hold no more than 5,000 gallons, and have a four-foot fence around the pool perimeter |
How to apply in Montgomery County
In Montgomery County, a residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.
What most pool permit applications include:
- Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
- For Montgomery County, the site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
- For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
- For Montgomery County, a barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
- Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
- For Montgomery County, the electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).
General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. Montgomery County Department of Permitting Services sets the exact checklist for Montgomery County.
Where to apply in Montgomery County:
Montgomery County Department of Permitting Services
- 2425 Reedie Drive 7th Floor Wheaton MD 20902
- Phone: 240-777-0311
Pool Permit in Montgomery County compared with nearby Maryland localities
| Locality | Permit needed? | Threshold | What each Maryland schedule says | Verified |
|---|---|---|---|---|
| Montgomery County | Permit required | Not specified | $360.68 for a private in-ground swimming pool including its fence per... | |
| Baltimore County | It depends | above-ground pool surface area, where the water depth is 24 inches or more; in-ground pools require a permit at any size | Building Permit Fee Schedule effective 07/01/26: Swimming Pool, Residential, Above... | |
| Howard County | Permit required | Not specified | $100 for above-ground pools | |
| Prince George's County | It depends | prefabricated pools accessory to one- and two-family dwellings that are installed entirely above ground, hold no more than 5,000 gallons, and have a four-foot fence around the pool perimeter | DPIE Fee Schedule, effective March 2, 2025: "Swimming Pool (In-ground) - Residential"... |
Inspections and closing out your permit
In Montgomery County, pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
- In Montgomery County: before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
- In Montgomery County: a bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
- In Montgomery County: a temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
- In Montgomery County: a pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
- In Montgomery County: at final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Montgomery County permit portal or by phone at 240-777-0311.
Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Pool Permit checklist for Montgomery County
- Confirm the requirement. Yes, a permit is required. Usually needed: Before constructing altering or enlarging any residential swimming pool.
- Budget the fee. $360.68 for a private in-ground swimming pool including its fence per DPS-Fees-ResConst-FY27.pdf effective 2026-07-01; pool electrical equipment needs a separate electrical permit. Official fee schedule.
- Apply. In Montgomery County, a residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect. Start at the Montgomery County permit portal.
- Keep the office details handy. Montgomery County Department of Permitting Services. Phone: 240-777-0311. Address: 2425 Reedie Drive 7th Floor Wheaton MD 20902.
- Plan for inspections. In Montgomery County, pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
Compiled from the official sources on this page. Last checked .
Real Pool Permit data in Montgomery County
- Median to issue
- 35 days
- 107 records
- Typical job value
- $95,000
- declared valuation
Across 107 recent pool permit records in Montgomery County: median project value $95,000; they typically took 35 days to issue.
Medians of real issued-permit records, not a quote.
Data as of . Source: Montgomery County residential building permits (open data).
First-time inspection pass rates in Montgomery County
Measured from Montgomery County's own inspection event log: how often each inspection type passes on the first visit.
- FINAL: 72% pass first time (n=16,764)
- FOOTING,PIERS, FOUNDATION: 85% pass first time (n=8,077)
- FRAMING OR CLOSE IN-ADD&ALTER: 75% pass first time (n=8,057)
- PERMIT NOTIFICATION SIGN: 77% pass first time (n=5,681)
- INSULATION INSPECTION: 91% pass first time (n=5,502)
to . Source: Montgomery County permit inspections (open data). Full study.
Permitting activity in Montgomery County
In 2024, Montgomery County authorized permits for 3,656 new residential housing units (1,491 single-family, 2,165 in multi-family buildings), valued at $901M, up from 2,860 the year before. That works out to about 3.4 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 1,082,273.
About Montgomery County
Montgomery County has about 405,127 housing units. The median home is valued at $615,200, against a median household income of $128,733. About 65% of homes are owner-occupied, and the typical home was built around 1980.
Source: U.S. Census Bureau, American Community Survey 2023 5-year.
Frequently asked questions
- Do you need a pool permit in Montgomery County?
- A building permit and an electrical permit are both required for any residential swimming pool construction, alteration, or enlargement in Montgomery County. Homeowners may apply in their own name but a contractor on the permit must hold an MHIC license. Pools installed after January 1, 1990 must have a barrier at least 60 inches tall. Always confirm with the Montgomery County Department of Permitting Services before starting.
- How much does a pool permit cost in Montgomery County?
- $360.68 for a private in-ground swimming pool including its fence per DPS-Fees-ResConst-FY27.pdf effective 2026-07-01; pool electrical equipment needs a separate electrical permit. See the official fee schedule for current amounts.
- How long does a pool permit take in Montgomery County?
- Across 107 recent pool permit records in Montgomery County, the median time to issue was 35 days. Individual projects vary with scope and office workload, so confirm with the office.
- Where do you apply for a pool permit in Montgomery County?
- You can apply through the Montgomery County permit portal or contact the Montgomery County Department of Permitting Services directly. The links are listed on this page.
- Can a homeowner pull a pool permit themselves in Montgomery County?
- Under Maryland law (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505): It depends on the trade and the county. Plumbing: state law exempts an individual who personally provides plumbing services in their own residence, but homeowners may not make final connections between the residence and public or private water supply or disposal systems, and Baltimore County plus the WSSC-area counties are largely carved out of the state plumbing title. Electrical: the Maryland Electricians Act prohibits providing electrical services for compensation without a license; it has no express homeowner exemption, so uncompensated work on one's own home falls outside the licensing prohibition, but each county decides whether it will issue an electrical permit to an unlicensed homeowner. Building permits are issued by local jurisdictions, which set their own owner-applicant rules. Confirm how Montgomery County applies this before you apply.
How the 35 days break down
Application filed
Submitted through the permit portal, with the fee due at submission.
Review
A correction request restarts this leg, which is the single largest reason a permit takes longer than the median.
Permit issued
Median across 107pool permit records in the last 12 months. Half were faster, half slower.
Inspections
The sequence in the checklist above. Work that is covered up before its inspection generally has to be reopened.
From the Library
What else needs a permit in Montgomery County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Not specified | Filed as a residential Alteration Building Permit at $0.78 per sq ft of altered area... |
| Deck Permit | Permit required | Not specified | $223.87 flat for an open unenclosed deck 500 sq ft or less, or $0.8830 per sq ft for... |
| Electrical Permit | Permit required | Not specified | $111.94 minimum fee for a residential one or two family dwelling electrical permit... |
| EV Charger Permit | It depends | Not specified | $62.19 for an Electrical Charging Station under Other Electrical Equipment, charged in... |
| Fence Permit | Permit required | Not specified | $89.54 flat Fence Permit fee per DPS-Fees-ResConst-FY27.pdf effective 2026-07-01 |
| HVAC Permit | Permit required | Not specified | Mechanical Permit minimum fee $80.84 for a residential one or two family dwelling... |
| Patio Permit | No permit needed | Not specified | No fee for a ground-level concrete or paver patio since no permit is required |
| Plumbing Permit | Permit required | Not specified | No county DPS fee for plumbing |
| Roof Replacement Permit | No permit needed | Not specified | No fee for replacing only the roof covering since no permit is required |
| Shed Permit | Permit required | Not specified | Priced as an Accessory Building: $136.80 flat for 200 sq ft or less, or $0.8830 per sq... |
| Solar Permit | Permit required | Not specified | $261.18 flat for rooftop solar panels, with a reduced $130.59 fee for rooftop solar... |
| Water Heater Permit | It depends | Not specified | No county DPS fee |
Pool Permit in other Maryland localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Montgomery County documents; the office above sets the local rules.
How this pool permit page for Montgomery County was verified. 2 official sources: montgomerycountymd.gov, montgomerycountymd.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Montgomery County Department of Permitting Services. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Maryland rule changes
- Howard County, MD raises shed and fence permit-exemption limits (CB24-2025)
CB24-2025 (Bill No. 24-2025) ·
- Montgomery County, MD FY27 permit fee schedules take effect
FY27 Fee Schedule (Council-approved FY27 Budget) ·