Maryland / Montgomery County

Patio Permit in Montgomery County, Maryland

No permit needed

No permit is typically required

Ground-level patios are exempt; permit required only if patio includes a roof or cover structure

Confirmed on official page Verified

Issued byMontgomery County Department of Permitting Services

By Mario Bailey, verified against official sources

Median to issue
20 days
6,440 records
Typical job value
$26,000
declared valuation

Quick answer

Ground-level patios made of concrete or pavers do not require a building permit in Montgomery County. A permit is required if the patio includes a permanent roof or cover structure. Stormwater management requirements may still apply given Montgomery County impervious surface limits. Contact DPS at 240-777-0311 to confirm requirements for your project.

Usually no permit is needed here. Hiring the work out anyway?

Hire it out

Sponsored

If a contractor builds your patio, they usually handle any required permit as part of the job. Compare a few bids before you commit.

Compare patio contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Ground-level patios are exempt; permit required only if patio includes a roof or cover structure

What your patio permit must meet in Maryland

Maryland adopts the 2021 IRC as the uniform statewide residential code, but its amendment list keeps only two of the model code's optional appendices in force, and the model code's prescriptive patio-cover appendix is not one of them.

  • The statewide baseline is the 2021 International Residential Code, incorporated by reference in the Maryland Building Performance Standards (COMAR 09.12.51.04).
  • Maryland replaced the model code's appendix list with a shorter one adopting only Appendix AF (Radon Control Methods) and Appendix AQ (Tiny Houses); the patio-cover appendix (Appendix AH) is not adopted statewide, so a prescriptive patio-cover path exists only where a local jurisdiction separately adopts it (COMAR 09.12.51.04.C).

Based on 2021 IRC, adopted via COMAR 09.12.51 Maryland Building Performance Standards; Appendix AH not carried into the state appendix list. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.

What a patio permit costs in Montgomery County

Line item
patio permitBy formulaNo fee for a ground-level concrete or paver patio since no permit is required; a patio with a permanent roof or cover needs a building permit, see the FY27 DPS residential construction fee schedule for the applicable structure fee.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Montgomery County compares in Maryland

No Maryland jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Howard CountyNo permit neededPatios file under miscellaneous accessory structures per the county's...
Montgomery Countythis pageNo permit neededNo fee for a ground-level concrete or paver patio since no permit is required
Prince George's CountyIt dependsDPIE Fee Schedule, effective March 2, 2025, line item "Patio - Residential >...

How to apply in Montgomery County

In Montgomery County, applying for a patio permit means submitting a site plan and framing plans for a roofed patio cover, since a cover is treated as its own permitted structure regardless of size. A plain concrete or paver patio slab at or near grade is, by contrast, often exempt from that same building permit requirement.

What most patio permit applications include:

  • Filing a permit application with the local building department, which only the property owner or an authorized agent may sign, since a patio cover is treated as its own permitted structure regardless of size (IRC R105.1).
  • For Montgomery County, a scaled site plan showing the new patio cover's size and location relative to the house and other existing structures, with dimensioned distances to all property lines so required setbacks can be verified before the permit is approved (IRC R106.2).
  • Construction documents such as a framing plan and elevation, showing rafter or beam sizes and spacing, the distance between supporting posts, and the method of attachment to the house, drawn with enough clarity for the building official to confirm the work will conform to the code (IRC R106.1).
  • For the roof structure itself, plans showing compliance with the patio cover appendix's structural limits, such as adequate footing sizes for the applied post loads, since a shallow slab on grade may substitute for a deeper footing only in limited cases up to about 750 pounds of load per post (IRC Appendix AH, Section AH105.2).
  • By contrast, an at grade concrete or paver patio that is not attached to the dwelling and stays within the code's small flatwork thresholds, similar to a sidewalk, driveway, or low deck under 200 square feet and 30 inches high, commonly needs no building permit at all, so none of the plan review steps above apply (IRC R105.2).

General submittal guidance from 2021 International Residential Code (IRC), Sections R105 and R106, with Appendix AH Patio Covers (named Appendix H in the 2012, 2015, and 2018 editions). Source. Montgomery County Department of Permitting Services sets the exact checklist for Montgomery County.

Where to apply in Montgomery County:

Montgomery County Department of Permitting Services

  • 2425 Reedie Drive 7th Floor Wheaton MD 20902
  • Phone: 240-777-0311

Patio Permit in Montgomery County compared with nearby Maryland localities

LocalityPermit needed?ThresholdWhat each Maryland schedule saysVerified
Montgomery CountyNo permit neededNot specifiedNo fee for a ground-level concrete or paver patio since no permit is required
Baltimore CountyNot confirmedNot specifiedNot published
Howard CountyNo permit neededNot specifiedPatios file under miscellaneous accessory structures per the county's residential permit...
Prince George's CountyIt dependsarea of an at-grade patio, with a permit required at any size if stairs or ramps are built due to elevation changeDPIE Fee Schedule, effective March 2, 2025, line item "Patio - Residential > 500 Sq Ft"...

Inspections and closing out your permit

In Montgomery County, a permitted patio cover follows the same footing, frame, and final inspection sequence used for any small accessory structure, since the posts and roof framing have to be checked before they are covered and again once the work is done. An at grade patio slab that qualifies as exempt flatwork usually needs no building inspection at all, because inspections only attach to work that required a permit in the first place.

  1. In Montgomery County: a footing inspection once the excavation, forms, and any reinforcing steel are in place but before concrete is poured, confirming the posts supporting a patio cover will bear on adequate footings (IRC R109.1.1).
  2. In Montgomery County: a frame inspection after the rafters, beams, posts, and any required rough in work are in place but before the roof sheathing or covering material conceals them, since a solid patio cover roof cannot be signed off once it is covered without this check (IRC R109.1.4).
  3. In Montgomery County: a final inspection once all permitted work, including roofing and post anchorage, is complete, which the code requires before the structure may be used (IRC R109.1.6).
  4. In Montgomery County: an at grade concrete or paver patio that qualifies as exempt flatwork under the permit rules is not subject to any of these inspection stages, since the inspection sequence only attaches to work that required a permit in the first place (IRC R105.2).
  5. In Montgomery County: each inspection has to be requested by the permit holder rather than happening automatically, and the approved plans and permit card need to be on site and available when the inspector arrives (IRC R109.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Montgomery County permit portal or by phone at 240-777-0311.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.

First-time inspection pass rates in Montgomery County

Measured from Montgomery County's own inspection event log: how often each inspection type passes on the first visit.

  • FINAL: 72% pass first time (n=16,764)
  • FOOTING,PIERS, FOUNDATION: 85% pass first time (n=8,077)
  • FRAMING OR CLOSE IN-ADD&ALTER: 75% pass first time (n=8,057)
  • PERMIT NOTIFICATION SIGN: 77% pass first time (n=5,681)
  • INSULATION INSPECTION: 91% pass first time (n=5,502)

to . Source: Montgomery County permit inspections (open data). Full study.

Permitting activity in Montgomery County

In 2024, Montgomery County authorized permits for 3,656 new residential housing units (1,491 single-family, 2,165 in multi-family buildings), valued at $901M, up from 2,860 the year before. That works out to about 3.4 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 1,082,273.

About Montgomery County

Montgomery County has about 405,127 housing units. The median home is valued at $615,200, against a median household income of $128,733. About 65% of homes are owner-occupied, and the typical home was built around 1980.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a patio permit in Montgomery County?
Ground-level patios made of concrete or pavers do not require a building permit in Montgomery County. A permit is required if the patio includes a permanent roof or cover structure. Stormwater management requirements may still apply given Montgomery County impervious surface limits. Contact DPS at 240-777-0311 to confirm requirements for your project. Always confirm with the Montgomery County Department of Permitting Services before starting.
How much does a patio permit cost in Montgomery County?
No fee for a ground-level concrete or paver patio since no permit is required; a patio with a permanent roof or cover needs a building permit, see the FY27 DPS residential construction fee schedule for the applicable structure fee. See the official fee schedule for current amounts.
How long does a patio permit take in Montgomery County?
Across 6,440 recent residential permit records in Montgomery County, the median time to issue was 20 days. Individual projects vary with scope and office workload, so confirm with the office.
Where do you apply for a patio permit in Montgomery County?
You can apply through the Montgomery County permit portal or contact the Montgomery County Department of Permitting Services directly. The links are listed on this page.
Can a homeowner pull a patio permit themselves in Montgomery County?
Under Maryland law (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505): It depends on the trade and the county. Plumbing: state law exempts an individual who personally provides plumbing services in their own residence, but homeowners may not make final connections between the residence and public or private water supply or disposal systems, and Baltimore County plus the WSSC-area counties are largely carved out of the state plumbing title. Electrical: the Maryland Electricians Act prohibits providing electrical services for compensation without a license; it has no express homeowner exemption, so uncompensated work on one's own home falls outside the licensing prohibition, but each county decides whether it will issue an electrical permit to an unlicensed homeowner. Building permits are issued by local jurisdictions, which set their own owner-applicant rules. Confirm how Montgomery County applies this before you apply.

How the 20 days break down

Day 0

Application filed

Submitted through the permit portal, with the fee due at submission.

Day 1–19

Review

A correction request restarts this leg, which is the single largest reason a permit takes longer than the median.

Day 20

Permit issued

Median across 6,440residential permit records in the last 12 months. Half were faster, half slower.

After

Inspections

The sequence in the checklist above. Work that is covered up before its inspection generally has to be reopened.

From the Library

What else needs a permit in Montgomery County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsNot specifiedFiled as a residential Alteration Building Permit at $0.78 per sq ft of altered area...
Deck PermitPermit requiredNot specified$223.87 flat for an open unenclosed deck 500 sq ft or less, or $0.8830 per sq ft for...
Electrical PermitPermit requiredNot specified$111.94 minimum fee for a residential one or two family dwelling electrical permit...
EV Charger PermitIt dependsNot specified$62.19 for an Electrical Charging Station under Other Electrical Equipment, charged in...
Fence PermitPermit requiredNot specified$89.54 flat Fence Permit fee per DPS-Fees-ResConst-FY27.pdf effective 2026-07-01
HVAC PermitPermit requiredNot specifiedMechanical Permit minimum fee $80.84 for a residential one or two family dwelling...
Plumbing PermitPermit requiredNot specifiedNo county DPS fee for plumbing
Pool PermitPermit requiredNot specified$360.68 for a private in-ground swimming pool including its fence per...
Roof Replacement PermitNo permit neededNot specifiedNo fee for replacing only the roof covering since no permit is required
Shed PermitPermit requiredNot specifiedPriced as an Accessory Building: $136.80 flat for 200 sq ft or less, or $0.8830 per sq...
Solar PermitPermit requiredNot specified$261.18 flat for rooftop solar panels, with a reduced $130.59 fee for rooftop solar...
Water Heater PermitIt dependsNot specifiedNo county DPS fee

Patio Permit in other Maryland localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Montgomery County documents; the office above sets the local rules.

How this patio permit page for Montgomery County was verified. 2 official sources: montgomerycountymd.gov, montgomerycountymd.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Montgomery County Department of Permitting Services. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Patio Permit requirements across Maryland localities

Patio permit rules nationwide

Look up an existing Montgomery County permit record

No permit needed
Get quotes