Sometimes, depending on the project

Before installing an in-ground pool, before installing an above-ground pool that is 24 inches or deeper or holds more than 5,000 gallons or is not prefabricated, and before filling in or removing an existing pool.

Confirmed on official page Verified Prince George's County Department of Permitting, Inspections and Enforcement (DPIE)

By Mario Bailey, verified against official sources

Quick answer

Prince George's County exempts only small prefabricated above-ground pools: those less than 24 inches deep, no more than 5,000 gallons, installed entirely above ground and surrounded by a four-foot fence. Every other residential pool needs a Building Permit, an Electrical Permit that only a Master Electrician may submit, and a Restoration Bond applied for before the building permit is issued. DPIE also requires a barrier for all pools, citing Section 4-247 and R-327 of the County Building Code for a six-foot-high barrier around outdoor pools accessory to one-family detached dwellings, so a Fence Permit is normally filed with the pool permit. Filling in or removing an existing pool also requires a construction permit under DPIE Bulletin 2013-01.

Typical threshold: prefabricated pools accessory to one- and two-family dwellings that are installed entirely above ground, hold no more than 5,000 gallons, and have a four-foot fence around the pool perimeter.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing an in-ground pool, before installing an above-ground pool that is 24 inches or deeper or holds more than 5,000 gallons or is not prefabricated, and before filling in or removing an existing pool.

What your pool permit must meet in Maryland

Maryland regulates residential swimming pools and spas under a dedicated statewide code, the Maryland Swimming Pool and Spa Standards, rather than through the IRC used for the rest of the house. That chapter currently incorporates the 2024 International Swimming Pool and Spa Code.

  • The state runs a dedicated pool and spa code: the 2024 International Swimming Pool and Spa Code (ISPSC) is incorporated by reference in the Maryland Swimming Pool and Spa Standards (COMAR 09.12.56.03).
  • The Standards apply to every pool or spa whose building-permit application is received by a local jurisdiction on or after December 31, 2023 (COMAR 09.12.56.02).
  • Residential (non-public) pools must be surrounded by a barrier that complies with the ISPSC barrier provisions, Sections 305.2.1 through 305.7 (COMAR 09.12.56.05).

Based on 2024 ISPSC, adopted via COMAR 09.12.56 Maryland Swimming Pool and Spa Standards. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.

What a pool permit costs in Prince George's County

Line item
pool permitBy formulaDPIE Fee Schedule, effective March 2, 2025: "Swimming Pool (In-ground) - Residential", minimum permit fee $297, "Total Fee = Administrative Fee $66 + Building Permit Fee ($297) + $53 Grading Fee + $5 M-NCPPC. Plus Technology Fee 10%"; "Swimming Pool (Above-ground/Restoration) - Residential", minimum permit fee $132, same formula with a $132 building permit fee. A separate "Electrical Permit Fee - Swimming Pool" of $162 applies, plus the $66 administrative fee and the 10% technology fee.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Prince George's County compares in Maryland

JurisdictionPermit needed?Threshold
Baltimore CountyIt dependsabove-ground pool surface area, where the water depth is 24 inches or more; in-ground pools require a permit at any size
Howard CountyPermit requiredNot specified
Montgomery CountyPermit requiredNot specified
Prince George's Countythis pageIt dependsprefabricated pools accessory to one- and two-family dwellings that are installed entirely above ground, hold no more than 5,000 gallons, and have a four-foot fence around the pool perimeter

Closest pool permit thresholds outside Maryland

Jurisdictions we cover whose limit sits nearest Prince George's County's 24 inches in depth.

How to apply in Prince George's County

A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.

What most pool permit applications include:

  • Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
  • The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
  • For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
  • A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
  • Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
  • The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).

General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. Prince George's County Department of Permitting, Inspections and Enforcement (DPIE) sets the exact checklist for Prince George's County.

Where to apply in Prince George's County:

Prince George's County Department of Permitting, Inspections and Enforcement (DPIE)

Inspections and closing out your permit

Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.

  1. Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
  2. A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
  3. A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
  4. A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
  5. At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Prince George's County permit portal or by phone at 301-636-2000.

Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a pool permit in Prince George's County?
Prince George's County exempts only small prefabricated above-ground pools: those less than 24 inches deep, no more than 5,000 gallons, installed entirely above ground and surrounded by a four-foot fence. Every other residential pool needs a Building Permit, an Electrical Permit that only a Master Electrician may submit, and a Restoration Bond applied for before the building permit is issued. DPIE also requires a barrier for all pools, citing Section 4-247 and R-327 of the County Building Code for a six-foot-high barrier around outdoor pools accessory to one-family detached dwellings, so a Fence Permit is normally filed with the pool permit. Filling in or removing an existing pool also requires a construction permit under DPIE Bulletin 2013-01. Prefabricated pools accessory to one- and two-family dwellings that are installed entirely above ground, hold no more than 5,000 gallons, and have a four-foot fence around the pool perimeter. Always confirm with the office before starting.
How much does a pool permit cost in Prince George's County?
DPIE Fee Schedule, effective March 2, 2025: "Swimming Pool (In-ground) - Residential", minimum permit fee $297, "Total Fee = Administrative Fee $66 + Building Permit Fee ($297) + $53 Grading Fee + $5 M-NCPPC. Plus Technology Fee 10%"; "Swimming Pool (Above-ground/Restoration) - Residential", minimum permit fee $132, same formula with a $132 building permit fee. A separate "Electrical Permit Fee - Swimming Pool" of $162 applies, plus the $66 administrative fee and the 10% technology fee. See the official fee schedule for current amounts.
Where do you apply for a pool permit in Prince George's County?
You can apply through the Prince George's County permit portal or contact the Prince George's County Department of Permitting, Inspections and Enforcement (DPIE) directly. The links are listed on this page.
Can a homeowner pull a pool permit themselves in Prince George's County?
Under Maryland law (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505): It depends on the trade and the county. Plumbing: state law exempts an individual who personally provides plumbing services in their own residence, but homeowners may not make final connections between the residence and public or private water supply or disposal systems, and Baltimore County plus the WSSC-area counties are largely carved out of the state plumbing title. Electrical: the Maryland Electricians Act prohibits providing electrical services for compensation without a license; it has no express homeowner exemption, so uncompensated work on one's own home falls outside the licensing prohibition, but each county decides whether it will issue an electrical permit to an unlicensed homeowner. Building permits are issued by local jurisdictions, which set their own owner-applicant rules. Confirm how Prince George's County applies this before you apply.

From the Library

What else needs a permit in Prince George's County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedDPIE Fee Schedule, effective March 2, 2025, line item "Deck or Pergola", minimum permit...
Electrical PermitPermit requiredNot specifiedDPIE Fee Schedule, effective March 2, 2025, prices electrical work by item: "Electrical...
Fence PermitIt dependsfence height above grade, with a permit required at any height on a corner lot, in a historic or protected area, or in the 100-year floodplainDPIE Fee Schedule, effective March 2, 2025, line item "Fence - Residential", minimum...
HVAC PermitIt dependsNot specifiedDPIE Fee Schedule, effective March 2, 2025, line item "Mechanical Permit -...
Patio PermitIt dependsarea of an at-grade patio, with a permit required at any size if stairs or ramps are built due to elevation changeDPIE Fee Schedule, effective March 2, 2025, line item "Patio - Residential > 500 Sq Ft"...
Plumbing PermitIt dependsNot specifiedThe DPIE Fee Schedule effective March 2, 2025 carries no residential plumbing permit...
Roof Replacement PermitIt dependsNot specifiedDPIE Fee Schedule, effective March 2, 2025, routes the line item "Roofing - Shingles &...
Shed PermitIt dependsfloor space of a one-story detached accessory structure, and only one such exempt structure is allowed per propertyDPIE Fee Schedule, effective March 2, 2025, line item "Shed > 150 Sq Ft", $1.17 per SF:...
Solar PermitPermit requiredNot specifiedDPIE Fee Schedule, effective March 2, 2025: "Solar Panels (Roof-mounted) - Residential"...

Pool Permit in other Maryland localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Prince George's County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Prince George's County Department of Permitting, Inspections and Enforcement (DPIE). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Pool Permit requirements across Maryland localities

It depends
Get quotes