Maryland / Prince George's County
Solar Permit in Prince George's County, Maryland
Permit required
Yes, a permit is required
Before installing any residential rooftop or ground-mounted solar photovoltaic system or battery storage system, and before installing a solar heating system.
Quick answer
Solar installations require permits in Prince George's County with no published size or capacity exemption, and DPIE prices both roof-mounted and ground-mounted residential solar as building permits with a separate electrical permit on top. The county runs standard residential rooftop solar and energy storage through SolarAPP+, an automated plan review that checks compliance against the 2021 ICC codes and the county's Subtitle 4 building amendments before the applicant files the permit in Momentum. Solar heating systems are treated the same way and take Mechanical, Building and Electrical permits together. Every solar installation, residential or commercial and regardless of cost, must additionally be inspected and certified by a county-approved Third-Party Inspector who is not affiliated with the installing contractor.
- Issued by
- Prince George's County Department of Permitting, Inspections and Enforcement (DPIE)
- Phone
- 301-636-2000
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your Maryland Home Improvement Commission (MHIC) license active, and under which business name? Verify it on www.dllr.state.md.us.
Maryland's owner-builder rule (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Prince George's County
- Fee schedule in force
- Official scheduleRead .
- Published in
- DPIE Fee Schedule, effective October 16, 2026:
- "Solar Panels (Roof-mounted) - Residential", minimum permit fee $158, "Total Fee = Administrative Fee $66 + Building Permit Fee ($0.03 per watt or $158, whichever is greater) + $5 M-NCPPC. Plus Technology Fee 10%";
- "Solar Panels (Ground-mounted) - Residential", same $158 minimum and per-watt formula but adding a $53 Grading Fee and a $112 U&O fee.
- A separate "Electrical Permit Fee - Solar PV System - (Group of 100 Panels)" of $95 applies, plus the $66 administrative fee and the 10% technology fee.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How Prince George's County compares in Maryland
No Maryland jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Anne Arundel County | Permit required | See schedule |
| Baltimore County | Permit required | Building Permit Fee Schedule effective 07/01/26: Solar Power System, Residential (Roof and Ground Mounted) $100.00; the schedule has the rest |
| Howard County | Permit required | $50 per structure for a residential roof- or ground-mounted solar collector (Miscellaneous Structures Accessory permit, FY2027 fee schedule) |
| Montgomery County | Permit required | $261.18 flat for rooftop solar panels, with a reduced $130.59 fee for rooftop solar panel refer-backs; the schedule has the rest |
| Prince George's Countythis page | Permit required | DPIE Fee Schedule, effective October 16, 2026: "Solar Panels (Roof-mounted) - Residential", minimum permit fee $158; the schedule has the rest |
How to apply in Prince George's County
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Prince George's County Department of Permitting, Inspections and Enforcement (DPIE)
- 9400 Peppercorn Place, Largo, MD 20774
- Phone: 301-636-2000
- Email: dpiebprd@co.pg.md.us
Your Solar Permit checklist for Prince George's County
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: princegeorgescountymd.gov: permitting inspections and enforcement.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Prince George's County permit portal.
- Keep the office details handy. Prince George's County Department of Permitting, Inspections and Enforcement (DPIE). Phone: 301-636-2000. Email: dpiebprd@co.pg.md.us. Address: 9400 Peppercorn Place, Largo, MD 20774.
Compiled from the official sources on this page. Last checked .
Permitting activity in Prince George's County
In 2025, Prince George's County authorized permits for 2,090 new residential housing units (1,530 single-family, 560 in multi-family buildings), valued at $616M, up from 1,473 the year before. That works out to about 2.2 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 970,374.
What else needs a permit in Prince George's County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Any size | See schedule |
| Electrical Permit | Permit required | Any size | See schedule |
| Fence Permit | It depends | fence height above grade, with a permit required at any height on a corner lot, in a historic or protected area, or in the 100-year floodplain | See schedule |
| HVAC Permit | It depends | Before installing or replacing a furnace, boiler, heat pump, central air conditioner... | See schedule |
| Patio Permit | It depends | area of an at-grade patio, with a permit required at any size if stairs or ramps are built due to elevation change | See schedule |
| Plumbing Permit | It depends | Before installing new plumbing or natural gas piping, before replacing a water heater... | See schedule |
| Pool Permit | It depends | prefabricated pools accessory to one- and two-family dwellings that are installed entirely above ground, hold no more than 5,000 gallons, and have a four-foot fence around the pool perimeter | DPIE Fee Schedule, effective October 16, 2026: "Swimming Pool (In-ground) - Residential", minimum permit fee $297; the schedule has the rest |
| Roof Replacement Permit | It depends | Before replacing roof sheathing or plywood, or doing any roof work that involves... | See schedule |
| Shed Permit | It depends | floor space of a one-story detached accessory structure, and only one such exempt structure is allowed per property | See schedule |
Frequently asked questions
- Do you need a solar permit in Prince George's County?
- Yes, before installing any residential rooftop or ground-mounted solar photovoltaic system or battery storage system, and before installing a solar heating system. If you are unsure how that applies to your project, call the permit office at 301-636-2000 before you start.
- How much does a solar permit cost in Prince George's County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 17 Nov 2026. For the figure on your own project, call the permit office at 301-636-2000.
- Where do you apply for a solar permit in Prince George's County?
- You can apply through the Prince George's County permit portal or contact the Prince George's County Department of Permitting, Inspections and Enforcement (DPIE) directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Prince George's County?
- Under Maryland law (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505): It depends on the trade and the county. Plumbing: state law exempts an individual who personally provides plumbing services in their own residence, but homeowners may not make final connections between the residence and public or private water supply or disposal systems, and Baltimore County plus the WSSC-area counties are largely carved out of the state plumbing title. Electrical: the Maryland Electricians Act prohibits providing electrical services for compensation without a license; it has no express homeowner exemption, so uncompensated work on one's own home falls outside the licensing prohibition, but each county decides whether it will issue an electrical permit to an unlicensed homeowner. Building permits are issued by local jurisdictions, which set their own owner-applicant rules. Confirm how Prince George's County applies this before you apply.
From the Library
Solar Permit in other Maryland localities
Everything above, sourced
How this solar permit page for Prince George's County was verified. 2 official sources: princegeorgescountymd.gov, princegeorgescountymd.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Prince George's County Department of Permitting, Inspections and Enforcement (DPIE). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page