Maryland / Prince George's County

Solar Permit in Prince George's County, Maryland

Permit required

Yes, a permit is required

Before installing any residential rooftop or ground-mounted solar photovoltaic system or battery storage system, and before installing a solar heating system.

Confirmed on official page Verified Prince George's County Department of Permitting, Inspections and Enforcement (DPIE)

By Mario Bailey, verified against official sources

Quick answer

Solar installations require permits in Prince George's County with no published size or capacity exemption, and DPIE prices both roof-mounted and ground-mounted residential solar as building permits with a separate electrical permit on top. The county runs standard residential rooftop solar and energy storage through SolarAPP+, an automated plan review that checks compliance against the 2021 ICC codes and the county's Subtitle 4 building amendments before the applicant files the permit in Momentum. Solar heating systems are treated the same way and take Mechanical, Building and Electrical permits together. Every solar installation, residential or commercial and regardless of cost, must additionally be inspected and certified by a county-approved Third-Party Inspector who is not affiliated with the installing contractor.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing any residential rooftop or ground-mounted solar photovoltaic system or battery storage system, and before installing a solar heating system.

What a solar permit costs in Prince George's County

Line item
solar permitBy formulaDPIE Fee Schedule, effective March 2, 2025: "Solar Panels (Roof-mounted) - Residential", minimum permit fee $158, "Total Fee = Administrative Fee $66 + Building Permit Fee ($0.03 per watt or $158, whichever is greater) + $5 M-NCPPC. Plus Technology Fee 10%"; "Solar Panels (Ground-mounted) - Residential", same $158 minimum and per-watt formula but adding a $53 Grading Fee and a $112 U&O fee. A separate "Electrical Permit Fee - Solar PV System - (Group of 100 Panels)" of $95 applies, plus the $66 administrative fee and the 10% technology fee.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Prince George's County compares in Maryland

No Maryland jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Baltimore CountyPermit requiredBuilding Permit Fee Schedule effective 07/01/26: Solar Power System...
Howard CountyPermit required$50 per structure for a residential roof- or ground-mounted solar collector...
Montgomery CountyPermit required$261.18 flat for rooftop solar panels, with a reduced $130.59 fee for rooftop...
Prince George's Countythis pagePermit requiredDPIE Fee Schedule, effective March 2, 2025: "Solar Panels (Roof-mounted) -...

How to apply in Prince George's County

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Prince George's County Department of Permitting, Inspections and Enforcement (DPIE) sets the exact checklist for Prince George's County.

Where to apply in Prince George's County:

Prince George's County Department of Permitting, Inspections and Enforcement (DPIE)

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Prince George's County permit portal or by phone at 301-636-2000.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Prince George's County?
Solar installations require permits in Prince George's County with no published size or capacity exemption, and DPIE prices both roof-mounted and ground-mounted residential solar as building permits with a separate electrical permit on top. The county runs standard residential rooftop solar and energy storage through SolarAPP+, an automated plan review that checks compliance against the 2021 ICC codes and the county's Subtitle 4 building amendments before the applicant files the permit in Momentum. Solar heating systems are treated the same way and take Mechanical, Building and Electrical permits together. Every solar installation, residential or commercial and regardless of cost, must additionally be inspected and certified by a county-approved Third-Party Inspector who is not affiliated with the installing contractor. Always confirm with the Prince George's County Department of Permitting, Inspections and Enforcement (DPIE) before starting.
How much does a solar permit cost in Prince George's County?
DPIE Fee Schedule, effective March 2, 2025: "Solar Panels (Roof-mounted) - Residential", minimum permit fee $158, "Total Fee = Administrative Fee $66 + Building Permit Fee ($0.03 per watt or $158, whichever is greater) + $5 M-NCPPC. Plus Technology Fee 10%"; "Solar Panels (Ground-mounted) - Residential", same $158 minimum and per-watt formula but adding a $53 Grading Fee and a $112 U&O fee. A separate "Electrical Permit Fee - Solar PV System - (Group of 100 Panels)" of $95 applies, plus the $66 administrative fee and the 10% technology fee. See the official fee schedule for current amounts.
Where do you apply for a solar permit in Prince George's County?
You can apply through the Prince George's County permit portal or contact the Prince George's County Department of Permitting, Inspections and Enforcement (DPIE) directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Prince George's County?
Under Maryland law (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505): It depends on the trade and the county. Plumbing: state law exempts an individual who personally provides plumbing services in their own residence, but homeowners may not make final connections between the residence and public or private water supply or disposal systems, and Baltimore County plus the WSSC-area counties are largely carved out of the state plumbing title. Electrical: the Maryland Electricians Act prohibits providing electrical services for compensation without a license; it has no express homeowner exemption, so uncompensated work on one's own home falls outside the licensing prohibition, but each county decides whether it will issue an electrical permit to an unlicensed homeowner. Building permits are issued by local jurisdictions, which set their own owner-applicant rules. Confirm how Prince George's County applies this before you apply.

From the Library

What else needs a permit in Prince George's County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedDPIE Fee Schedule, effective March 2, 2025, line item "Deck or Pergola", minimum permit...
Electrical PermitPermit requiredNot specifiedDPIE Fee Schedule, effective March 2, 2025, prices electrical work by item: "Electrical...
Fence PermitIt dependsfence height above grade, with a permit required at any height on a corner lot, in a historic or protected area, or in the 100-year floodplainDPIE Fee Schedule, effective March 2, 2025, line item "Fence - Residential", minimum...
HVAC PermitIt dependsNot specifiedDPIE Fee Schedule, effective March 2, 2025, line item "Mechanical Permit -...
Patio PermitIt dependsarea of an at-grade patio, with a permit required at any size if stairs or ramps are built due to elevation changeDPIE Fee Schedule, effective March 2, 2025, line item "Patio - Residential > 500 Sq Ft"...
Plumbing PermitIt dependsNot specifiedThe DPIE Fee Schedule effective March 2, 2025 carries no residential plumbing permit...
Pool PermitIt dependsprefabricated pools accessory to one- and two-family dwellings that are installed entirely above ground, hold no more than 5,000 gallons, and have a four-foot fence around the pool perimeterDPIE Fee Schedule, effective March 2, 2025: "Swimming Pool (In-ground) - Residential"...
Roof Replacement PermitIt dependsNot specifiedDPIE Fee Schedule, effective March 2, 2025, routes the line item "Roofing - Shingles &...
Shed PermitIt dependsfloor space of a one-story detached accessory structure, and only one such exempt structure is allowed per propertyDPIE Fee Schedule, effective March 2, 2025, line item "Shed > 150 Sq Ft", $1.17 per SF:...

Solar Permit in other Maryland localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Prince George's County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Prince George's County Department of Permitting, Inspections and Enforcement (DPIE). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Solar Permit requirements across Maryland localities

Permit required
Get quotes