Maryland / Baltimore County

Solar Permit in Baltimore County, Maryland

Permit required

Yes, a permit is required

Before any residential solar photovoltaic installation. The electrical permit is filed by a Baltimore County registered master electrician; the building permit is added once the array reaches 10 kW.

Confirmed on official page Verified Baltimore County Department of Permits, Approvals and Inspections (PAI)

By Mario Bailey, verified against official sources

Quick answer

Solar always needs a permit in Baltimore County, but which permit depends on system size. An electrical permit filed by a master electrician licensed and registered with Baltimore County is required for every solar installation, and a building permit is required on top of that once the panels total 10 kilowatts or more. Because a permit is required either way, the 10 kW figure changes the paperwork rather than the requirement itself. Residential energy storage systems installed inside a dwelling need a residential alteration building permit plus an electrical permit, while exterior or detached-accessory-structure storage needs no building permit.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before any residential solar photovoltaic installation. The electrical permit is filed by a Baltimore County registered master electrician; the building permit is added once the array reaches 10 kW.

What a solar permit costs in Baltimore County

Line item
solar permitBy formulaBuilding Permit Fee Schedule effective 07/01/26: Solar Power System, Residential (Roof and Ground Mounted) $100.00, plus the $75.00 residential permit application fee. Electrical Permit Fee Schedule effective 11/26/18: Solar Photovoltaic System, Residential $74.00.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Baltimore County compares in Maryland

No Maryland jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Baltimore Countythis pagePermit requiredBuilding Permit Fee Schedule effective 07/01/26: Solar Power System...
Howard CountyPermit required$50 per structure for a residential roof- or ground-mounted solar collector...
Montgomery CountyPermit required$261.18 flat for rooftop solar panels, with a reduced $130.59 fee for rooftop...
Prince George's CountyPermit requiredDPIE Fee Schedule, effective March 2, 2025: "Solar Panels (Roof-mounted) -...

How to apply in Baltimore County

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Baltimore County Department of Permits, Approvals and Inspections (PAI) sets the exact checklist for Baltimore County.

Where to apply in Baltimore County:

Baltimore County Department of Permits, Approvals and Inspections (PAI)

  • County Office Building, 111 West Chesapeake Avenue, Towson, Maryland 21204
  • Phone: 410-887-3900

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Baltimore County permit portal or by phone at 410-887-3900.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Baltimore County?
Solar always needs a permit in Baltimore County, but which permit depends on system size. An electrical permit filed by a master electrician licensed and registered with Baltimore County is required for every solar installation, and a building permit is required on top of that once the panels total 10 kilowatts or more. Because a permit is required either way, the 10 kW figure changes the paperwork rather than the requirement itself. Residential energy storage systems installed inside a dwelling need a residential alteration building permit plus an electrical permit, while exterior or detached-accessory-structure storage needs no building permit. Always confirm with the Baltimore County Department of Permits, Approvals and Inspections (PAI) before starting.
How much does a solar permit cost in Baltimore County?
Building Permit Fee Schedule effective 07/01/26: Solar Power System, Residential (Roof and Ground Mounted) $100.00, plus the $75.00 residential permit application fee. Electrical Permit Fee Schedule effective 11/26/18: Solar Photovoltaic System, Residential $74.00. See the official fee schedule for current amounts.
Where do you apply for a solar permit in Baltimore County?
You can apply through the Baltimore County permit portal or contact the Baltimore County Department of Permits, Approvals and Inspections (PAI) directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Baltimore County?
Under Maryland law (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505): It depends on the trade and the county. Plumbing: state law exempts an individual who personally provides plumbing services in their own residence, but homeowners may not make final connections between the residence and public or private water supply or disposal systems, and Baltimore County plus the WSSC-area counties are largely carved out of the state plumbing title. Electrical: the Maryland Electricians Act prohibits providing electrical services for compensation without a license; it has no express homeowner exemption, so uncompensated work on one's own home falls outside the licensing prohibition, but each county decides whether it will issue an electrical permit to an unlicensed homeowner. Building permits are issued by local jurisdictions, which set their own owner-applicant rules. Confirm how Baltimore County applies this before you apply.

From the Library

What else needs a permit in Baltimore County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsdeck floor area, with a permit also required for any deck more than 16 inches above the lowest gradeBuilding Permit Fee Schedule effective 07/01/26: Decks (Open Deck) (under 600 sf) $105.00
Electrical PermitIt dependsNot specifiedElectrical Permit Fee Schedule effective 11/26/18: Residential Service (each meter)...
Fence PermitIt dependsfence height measured vertical to ground, including a fence set on top of a wallBuilding Permit Fee Schedule effective 07/01/26 lists Fences, Residential: $35.00 +...
HVAC PermitIt dependsNot specifiedThe Building Permit Fee Schedule effective 07/01/26 prices Mechanical, HVAC System Only...
Plumbing PermitPermit requiredNot specifiedPlumbing Inspection Fee Schedule effective 11/26/18: Inspection, New, for 1st fixture...
Pool PermitIt dependsabove-ground pool surface area, where the water depth is 24 inches or more; in-ground pools require a permit at any sizeBuilding Permit Fee Schedule effective 07/01/26: Swimming Pool, Residential, Above...
Roof Replacement PermitIt dependsshare of the sheathing or deck being replaced in a roofing jobThe Building Permit Fee Schedule effective 07/01/26 publishes no roofing line item.
Shed PermitIt dependsaccessory structure floor areaBuilding Permit Fee Schedule effective 07/01/26: Accessory Structure, Under 1000 sf...

Solar Permit in other Maryland localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Baltimore County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Baltimore County Department of Permits, Approvals and Inspections (PAI). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page