Florida / Hernando County

Plumbing Permit in Hernando County, Florida

Permit required

Yes, a permit is required

Before installing, altering, or replacing a plumbing system in unincorporated Hernando County

Quick answer

Hernando County's Development Services FAQ lists plumbing work among the projects that require a permit, and the Building Division's fee schedule includes a Plumbing, Other (Res) line item. The county exempts replacing an existing faucet, sink, or toilet, and changing out a water heater of the same type in the same location. This describes unincorporated Hernando County; the City of Brooksville operates its own building department.

Issued by
Building Division
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

Plumbing permits are usually pulled by the plumber doing the job. If you are still choosing one, compare a few quotes first.

Compare plumber quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What a plumbing permit costs in Hernando County

Fee schedule in force
Official scheduleRead .

Plumbing, Other (Res): $115.00, per Resolution No. 2026-037 (effective March 3, 2026).

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Hernando County compares in Florida

JurisdictionPermit needed?Threshold
Alachua CountyPermit requiredAny size
Brevard CountyIt dependsPermits are required for the installation or replacement of water, sewer, or gas piping and systems; this does not include changing like-for-like water heaters or fixtures such as sinks.
Broward CountyPermit requiredAny size
Charlotte CountyPermit requiredAny size
Clay CountyPermit requiredAny size
Collier CountyPermit requiredPermits shall not be required for the following: ... Plumbing: 1. Repair work performed by licensed plumbing contractors that does not exceed $1,500.00 in value of materials and labor. [Followed by 16 specific exempted repairs/replacements, e.g. faucets, water closets, sinks, garbage disposals, dishwashers, and like-for-like electric water heaters up to 52-gallon capacity.]
Hernando Countythis pagePermit requiredAny size

How to apply in Hernando County

General guide, not specific to this office

What a plumbing permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a plumbing permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Building Division

Permitting activity in Hernando County

In 2025, Hernando County authorized permits for 1,975 new residential housing units (1,734 single-family, 241 in multi-family buildings), valued at $528M, down from 2,505 the year before. That works out to about 8.9 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 221,701.

What else needs a permit in Hernando County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeDeck: $140.00, per the Building Division fee schedule (Resolution No. 2026-037, effective March 3, 2026)
Electrical PermitPermit requiredAny sizeElectric, Other: $165.00
Fence PermitPermit requiredFence permits are required in all commercial, industrial, and residential zoning districts; agricultural zoning districts (AG, AR, AR1, AR2, PDP(RUR)) are exempt from the Fence OrdinanceSee schedule
HVAC PermitIt dependsA window air conditioning unit using an existing electrical outlet, and repair of existing mechanical equipment, do not require a building permit; installing a new central/ducted system or changing out equipment doesMechanical A/C Changeout Only: $140.00
Patio PermitIt dependsSand-set pavers that are not part of a pool or spa deck do not require a building permit; other patio construction methods are not separately addressed by nameA concrete patio slab appears to fall under the schedule's Slab permit ($180.00); the schedule has the rest
Pool PermitIt dependsManufactured pools less than 24 inches deep are exempt from a building permitSwimming Pool, Above Ground: $140.00
Roof Replacement PermitPermit requiredRoof repairs covering less than 100 square feet of existing roof are exempt from a building permit; this exemption does not extend to a full roof replacementRoofing, Residential: $190.00, per Resolution No. 2026-037 (effective March 3, 2026)
Shed PermitIt dependsSheds with impervious roof coverings of 120 square feet or less do not require a Zoning permit, provided other county regulations (setbacks, floodplain rules, one detached accessory building per parcel, etc.) are metOr less (Non-Commercial, Site Built or 1 Piece/Pre-Fab) - Building: $140.00, per Resolution No. 2026-037 (effective March 3, 2026)
Solar PermitPermit requiredAny sizePhotovoltaic System (Res): $180.00

Frequently asked questions

Do you need a plumbing permit in Hernando County?
Yes, before installing, altering, or replacing a plumbing system in unincorporated Hernando County. If you are unsure how that applies to your project, call the Building Division at (352) 754-4050 before you start.
How much does a plumbing permit cost in Hernando County?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the Building Division at (352) 754-4050.
Where do you apply for a plumbing permit in Hernando County?
You can apply through the Hernando County permit portal or contact the Building Division directly. The links are listed on this page.
Can a homeowner pull a plumbing permit themselves in Hernando County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Hernando County applies this before you apply.

From the Library

Plumbing Permit in other Florida localities

Everything above, sourced

How this plumbing permit page for Hernando County was verified. 2 official sources: hernandocounty.us, hernandocounty.us; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Building Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project