It depends
Sometimes, depending on the project
Before installing a new central air conditioning/HVAC system or changing out existing mechanical equipment in unincorporated Hernando County (a window unit using an existing outlet, or repair of existing equipment, is exempt)
Quick answer
Hernando County's Building Division fee schedule lists separate permit fees for a Mechanical A/C changeout and a new mechanical A/C system, consistent with the Development Services FAQ listing mechanical work among projects that require a permit. The county's Items Not Requiring a Building Permit document exempts installing a window air conditioner that uses an existing electrical outlet, and repairing existing mechanical equipment. This describes unincorporated Hernando County; the City of Brooksville operates its own building department.
- Typical threshold
- A window air conditioning unit using an existing electrical outlet, and repair of existing mechanical equipment, do not require a building permit; installing a new central/ducted system or changing out equipment does
- Issued by
- Building Division
- Phone
- (352) 754-4050
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
HVAC contractors usually pull this permit as part of the job. If you have not picked one yet, compare a few quotes before you commit.
Compare HVAC contractor quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
What an HVAC permit costs in Hernando County
- Fee schedule in force
- Official scheduleRead .
Mechanical A/C Changeout Only: $140.00;
Mechanical A/C New System: $140.00, per Resolution No. 2026-037 (effective March 3, 2026).
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How Hernando County compares in Florida
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Alachua County | Permit required | Any size |
| Brevard County | Permit required | Any size |
| Broward County | Permit required | Any size |
| Charlotte County | Permit required | Any size |
| Clay County | Permit required | Any size |
| Collier County | Permit required | This is a self-issuing permit available on the portal, unless any of the criteria listed below apply. If they do, the permit will follow the standard permitting and plan review process: Greater than 5 tons (single family); Located on the roof of a building; Adding concrete slab; Changing size of equipment; Moving location of equipment; Any changes to duct work; Adding a new mini-split; If owner-builder; In a trailer or manufactured home; If commercial building; If multi-family building. |
| Hernando Countythis page | It depends | A window air conditioning unit using an existing electrical outlet, and repair of existing mechanical equipment, do not require a building permit; installing a new central/ducted system or changing out equipment does |
How to apply in Hernando County
General guide, not specific to this office
What an HVAC permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an HVAC permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Building Division
- 789 Providence Boulevard, Brooksville, FL 34601
- Phone: (352) 754-4050
- Email: bldg@hernandocounty.us
Your HVAC Permit checklist for Hernando County
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: A window air conditioning unit using an existing electrical outlet, and repair of existing mechanical equipment, do not require a building permit; installing a new central/ducted system or changing out equipment does. Read the rule where we read it: hernandocounty.us: building.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Hernando County permit portal.
- Keep the office details handy. Building Division. Phone: (352) 754-4050. Email: bldg@hernandocounty.us. Address: 789 Providence Boulevard, Brooksville, FL 34601.
Compiled from the official sources on this page. Last checked .
Permitting activity in Hernando County
In 2025, Hernando County authorized permits for 1,975 new residential housing units (1,734 single-family, 241 in multi-family buildings), valued at $528M, down from 2,505 the year before. That works out to about 8.9 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 221,701.
What else needs a permit in Hernando County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Any size | Deck: $140.00, per the Building Division fee schedule (Resolution No. 2026-037, effective March 3, 2026) |
| Electrical Permit | Permit required | Any size | Electric, Other: $165.00 |
| Fence Permit | Permit required | Fence permits are required in all commercial, industrial, and residential zoning districts; agricultural zoning districts (AG, AR, AR1, AR2, PDP(RUR)) are exempt from the Fence Ordinance | See schedule |
| Patio Permit | It depends | Sand-set pavers that are not part of a pool or spa deck do not require a building permit; other patio construction methods are not separately addressed by name | A concrete patio slab appears to fall under the schedule's Slab permit ($180.00); the schedule has the rest |
| Plumbing Permit | Permit required | Any size | Plumbing, Other (Res): $115.00, per Resolution No. 2026-037 (effective March 3, 2026) |
| Pool Permit | It depends | Manufactured pools less than 24 inches deep are exempt from a building permit | Swimming Pool, Above Ground: $140.00 |
| Roof Replacement Permit | Permit required | Roof repairs covering less than 100 square feet of existing roof are exempt from a building permit; this exemption does not extend to a full roof replacement | Roofing, Residential: $190.00, per Resolution No. 2026-037 (effective March 3, 2026) |
| Shed Permit | It depends | Sheds with impervious roof coverings of 120 square feet or less do not require a Zoning permit, provided other county regulations (setbacks, floodplain rules, one detached accessory building per parcel, etc.) are met | Or less (Non-Commercial, Site Built or 1 Piece/Pre-Fab) - Building: $140.00, per Resolution No. 2026-037 (effective March 3, 2026) |
| Solar Permit | Permit required | Any size | Photovoltaic System (Res): $180.00 |
Frequently asked questions
- Do you need an HVAC permit in Hernando County?
- It depends on the project. A window air conditioning unit using an existing electrical outlet, and repair of existing mechanical equipment, do not require a building permit; installing a new central/ducted system or changing out equipment does. If you are unsure how that applies to your project, call the Building Division at (352) 754-4050 before you start.
- How much does an HVAC permit cost in Hernando County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the Building Division at (352) 754-4050.
- Where do you apply for an HVAC permit in Hernando County?
- You can apply through the Hernando County permit portal or contact the Building Division directly. The links are listed on this page.
- Can a homeowner pull an HVAC permit themselves in Hernando County?
- Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Hernando County applies this before you apply.
From the Library
HVAC Permit in other Florida localities
Everything above, sourced
How this HVAC permit page for Hernando County was verified. 2 official sources: hernandocounty.us, hernandocounty.us; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Building Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page