Hawaii / Honolulu

Plumbing Permit in Honolulu, Hawaii

Permit required

Yes, a permit is required

Before installing, altering or replacing plumbing, gas or drainage piping, fixtures, gas appliances or water heating equipment, beyond small licensed repairs.

Confirmed on official page Verified

Issued byCity and County of Honolulu Department of Planning and Permitting (DPP), Building Division

By Mario Bailey, verified against official sources

Quick answer

ROH 18-3.1(a)(3) requires a building permit to install, remove, alter, repair or replace any plumbing, fire sprinkler, gas or drainage piping work, or any fixture, gas appliance, or water heating or treating equipment. The one homeowner-relevant exemption is plumbing repair or like-for-like replacement of valves, pipes or fixtures by a licensed plumbing contractor valued at $2,500 or less in a 12-month period. Plumbing inspection is done by DPP's own plumbing inspectors.

Who is pulling this permit?

Hire it out

Sponsored

Plumbing permits are usually pulled by the plumber doing the job. If you are still choosing one, compare a few quotes first.

Compare plumber quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before installing, altering or replacing plumbing, gas or drainage piping, fixtures, gas appliances or water heating equipment, beyond small licensed repairs.

What a plumbing permit costs in Honolulu

Line item
plumbing permitBy formulaValuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Honolulu

In Honolulu, you apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.

What most plumbing permit applications include:

  • For Honolulu, a permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
  • For Honolulu, the application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
  • Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
  • Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
  • Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).

General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. City and County of Honolulu Department of Planning and Permitting (DPP), Building Division sets the exact checklist for Honolulu.

Where to apply in Honolulu:

City and County of Honolulu Department of Planning and Permitting (DPP), Building Division

  • 650 South King Street, 7th Floor, Honolulu, Hawaii 96813
  • Phone: (808) 768-8000
  • Email: dpp@honolulu.gov

Plumbing Permit in Honolulu compared with nearby Hawaii localities

LocalityPermit needed?ThresholdWhat each Hawaii schedule saysVerified
HonoluluPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Hawaii CountyIt dependsBefore replacing or rearranging any pipe or valve, adding fixtures, or any gas, water......Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...

Inspections and closing out your permit

In Honolulu, plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.

  1. In Honolulu: piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
  2. In Honolulu: rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
  3. In Honolulu: rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
  4. In Honolulu: the water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
  5. In Honolulu: the framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
  6. In Honolulu: at the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
  7. In Honolulu: final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Honolulu permit portal or by phone at (808) 768-8000.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a plumbing permit in Honolulu?
ROH 18-3.1(a)(3) requires a building permit to install, remove, alter, repair or replace any plumbing, fire sprinkler, gas or drainage piping work, or any fixture, gas appliance, or water heating or treating equipment. The one homeowner-relevant exemption is plumbing repair or like-for-like replacement of valves, pipes or fixtures by a licensed plumbing contractor valued at $2,500 or less in a 12-month period. Plumbing inspection is done by DPP's own plumbing inspectors. Always confirm with the City and County of Honolulu Department of Planning and Permitting (DPP), Building Division before starting.
How much does a plumbing permit cost in Honolulu?
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value. See the official fee schedule for current amounts.
Where do you apply for a plumbing permit in Honolulu?
You can apply through the Honolulu permit portal or contact the City and County of Honolulu Department of Planning and Permitting (DPP), Building Division directly. The links are listed on this page.
Can a homeowner pull a plumbing permit themselves in Honolulu?
Under Hawaii law (HRS 444-2(7), 444-2.5, 444-9.1, 444-23(e)): Hawaii lets owners or lessees build or improve residential or farm buildings for their own use, or for use by their grandparents, parents, siblings, or children, without a contractor's license, as long as the building is not offered for sale or lease. The owner must register for the exemption with the county when applying for the building permit, supervise the work, hire licensed subcontractors for any licensed work, and use licensed electricians and plumbers for electrical and plumbing work unless the owner holds that license. Selling or leasing the structure within one year after final county inspection is treated as evidence it was built for sale, unless the permit valuation was under $10,000, the buyer is the owner's employee, or the Contractors License Board finds an unforeseen hardship. A violation carries a fine of up to $5,000 or 50% of the permitted construction value, whichever is greater, for a first offense, and bars the owner from the exemption for three years. Confirm how Honolulu applies this before you apply.

From the Library

What else needs a permit in Honolulu

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsinterior remodeling that changes no room count, wall, window location, or electrical, plumbing or mechanical installation...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Deck PermitPermit requiredAny size...under ROH 18-6.2, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Electrical PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
EV Charger PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Fence PermitIt dependsfence height at which a building permit is required; the exemption does not apply on a street corner or in a flood zone...under ROH 18-6.2, with a plan review fee of 20% of the permit fee (maximum $25,000)...
HVAC PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Patio PermitIt dependsuncovered walkways and outside paving within private property, not on a street corner or in a flood zone...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Roof Replacement PermitIt dependsreroofing that does not adversely affect structural components, Group R-3 and U occupancies...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Shed PermitIt dependsaggregate floor area of one-story detached accessory storage buildings, tool sheds and playhouses...are valuation-based under ROH 18-6.2 (plus a 20% plan review fee, maximum $25,000...
Solar PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Water Heater PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...

Plumbing Permit in other Hawaii localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Honolulu documents; the office above sets the local rules.

How this plumbing permit page for Honolulu was verified. 2 official sources: honolulu.gov, hnldoc.ehawaii.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City and County of Honolulu Department of Planning and Permitting (DPP), Building Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page