Electrical Permit in Honolulu, Hawaii
Permit required
Yes, a permit is required
Before any electrical work beyond the listed exemptions, including meter replacement or upgrade, rewiring and new circuits.
Issued byCity and County of Honolulu Department of Planning and Permitting (DPP), Building Division
By Mario Bailey, verified against official sources
Quick answer
ROH 18-3.1(a)(2) requires a building permit for 'Any electrical work', issued and inspected by DPP's own Building Division (no state electrical permit). Exemptions are narrow: cord-and-plug appliances, low-voltage communication and sound systems in one- and two-family dwellings, and repair work by a licensed electrical contractor valued at $2,500 or less in a 12-month period that does not involve service entrance equipment. DPP's FAQ adds that all electrical work must be done by a state-licensed contractor, so a homeowner cannot pull an electrical permit as owner-builder.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before any electrical work beyond the listed exemptions, including meter replacement or upgrade, rewiring and new circuits.
What an electrical permit costs in Honolulu
How to apply in Honolulu
In Honolulu, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- For Honolulu, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- For Honolulu, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City and County of Honolulu Department of Planning and Permitting (DPP), Building Division sets the exact checklist for Honolulu.
Where to apply in Honolulu:
City and County of Honolulu Department of Planning and Permitting (DPP), Building Division
- 650 South King Street, 7th Floor, Honolulu, Hawaii 96813
- Phone: (808) 768-8000
- Email: dpp@honolulu.gov
Electrical Permit in Honolulu compared with nearby Hawaii localities
| Locality | Permit needed? | Threshold | What each Hawaii schedule says | Verified |
|---|---|---|---|---|
| Honolulu | Permit required | Any size | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... | |
| Hawaii County | It depends | Before any new wiring, circuit, service change or rewiring | ...Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0... |
Inspections and closing out your permit
In Honolulu, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- In Honolulu: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- In Honolulu: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- In Honolulu: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- In Honolulu: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- In Honolulu: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- In Honolulu: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- In Honolulu: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Honolulu permit portal or by phone at (808) 768-8000.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for Honolulu
- Confirm the requirement. Yes, a permit is required. Usually needed: Before any electrical work beyond the listed exemptions, including meter replacement or upgrade, rewiring and new circuits.
- Budget the fee. Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value. Official fee schedule.
- Apply. In Honolulu, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the Honolulu permit portal.
- Keep the office details handy. City and County of Honolulu Department of Planning and Permitting (DPP), Building Division. Phone: (808) 768-8000. Address: 650 South King Street, 7th Floor, Honolulu, Hawaii 96813.
- Plan for inspections. In Honolulu, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an electrical permit in Honolulu?
- ROH 18-3.1(a)(2) requires a building permit for 'Any electrical work', issued and inspected by DPP's own Building Division (no state electrical permit). Exemptions are narrow: cord-and-plug appliances, low-voltage communication and sound systems in one- and two-family dwellings, and repair work by a licensed electrical contractor valued at $2,500 or less in a 12-month period that does not involve service entrance equipment. DPP's FAQ adds that all electrical work must be done by a state-licensed contractor, so a homeowner cannot pull an electrical permit as owner-builder. Always confirm with the City and County of Honolulu Department of Planning and Permitting (DPP), Building Division before starting.
- How much does an electrical permit cost in Honolulu?
- Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value. See the official fee schedule for current amounts.
- Where do you apply for an electrical permit in Honolulu?
- You can apply through the Honolulu permit portal or contact the City and County of Honolulu Department of Planning and Permitting (DPP), Building Division directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in Honolulu?
- Under Hawaii law (HRS 444-2(7), 444-2.5, 444-9.1, 444-23(e)): Hawaii lets owners or lessees build or improve residential or farm buildings for their own use, or for use by their grandparents, parents, siblings, or children, without a contractor's license, as long as the building is not offered for sale or lease. The owner must register for the exemption with the county when applying for the building permit, supervise the work, hire licensed subcontractors for any licensed work, and use licensed electricians and plumbers for electrical and plumbing work unless the owner holds that license. Selling or leasing the structure within one year after final county inspection is treated as evidence it was built for sale, unless the permit valuation was under $10,000, the buyer is the owner's employee, or the Contractors License Board finds an unforeseen hardship. A violation carries a fine of up to $5,000 or 50% of the permitted construction value, whichever is greater, for a first offense, and bars the owner from the exemption for three years. Confirm how Honolulu applies this before you apply.
From the Library
What else needs a permit in Honolulu
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | interior remodeling that changes no room count, wall, window location, or electrical, plumbing or mechanical installation | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
| Deck Permit | Permit required | Any size | ...under ROH 18-6.2, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
| EV Charger Permit | Permit required | Any size | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
| Fence Permit | It depends | fence height at which a building permit is required; the exemption does not apply on a street corner or in a flood zone | ...under ROH 18-6.2, with a plan review fee of 20% of the permit fee (maximum $25,000)... |
| HVAC Permit | Permit required | Any size | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
| Patio Permit | It depends | uncovered walkways and outside paving within private property, not on a street corner or in a flood zone | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
| Plumbing Permit | Permit required | Any size | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
| Roof Replacement Permit | It depends | reroofing that does not adversely affect structural components, Group R-3 and U occupancies | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
| Shed Permit | It depends | aggregate floor area of one-story detached accessory storage buildings, tool sheds and playhouses | ...are valuation-based under ROH 18-6.2 (plus a 20% plan review fee, maximum $25,000... |
| Solar Permit | Permit required | Any size | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
| Water Heater Permit | Permit required | Any size | ...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)... |
Electrical Permit in other Hawaii localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Honolulu documents; the office above sets the local rules.
How this electrical permit page for Honolulu was verified. 2 official sources: honolulu.gov, hnldoc.ehawaii.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City and County of Honolulu Department of Planning and Permitting (DPP), Building Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Electrical Permit requirements across Hawaii localities