Hawaii / Hawaii County

Electrical Permit in Hawaii County, Hawaii

It depends

Sometimes, depending on the project

Before any new wiring, circuit, service change or rewiring; only like-for-like repairs and tamper-resistant receptacle swaps are exempt.

Confirmed on official page Verified

Issued byCounty of Hawaiʻi Department of Public Works, Building Division

By Mario Bailey, verified against official sources

Quick answer

Hawaiʻi County's Building Division issues electrical permits itself (there is no state electrical permit in Hawaiʻi), and a permit is required to erect, install, enlarge, alter, repair, remove, convert, or replace any electrical work. Exemptions are narrow: repairing a fixed motor, water heater or air conditioning control, replacing receptacles and switches with tamper-resistant ones, and maintenance by a licensed electrician that does not repair, replace or rearrange wiring. Permits go only to a licensed electrical contractor or to a homeowner who personally holds a Hawaiʻi electrician license.

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before any new wiring, circuit, service change or rewiring; only like-for-like repairs and tamper-resistant receptacle swaps are exempt.

What an electrical permit costs in Hawaii County

Line item
electrical permitBy formulaHawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Hawaii County

In Hawaii County, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • For Hawaii County, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • For Hawaii County, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. County of Hawaiʻi Department of Public Works, Building Division sets the exact checklist for Hawaii County.

Where to apply in Hawaii County:

County of Hawaiʻi Department of Public Works, Building Division

  • 101 Pauahi Street, Suite 7 (Aupuni Center), Hilo, HI 96720; West Hawaii office: 74-5044 Ane Keohokalole Highway, Bldg E1 1st Floor, Kailua-Kona, HI 96740, (808) 323-4720
  • Phone: (808) 961-8331
  • Email: cohbuild@hawaiicounty.gov

Electrical Permit in Hawaii County compared with nearby Hawaii localities

LocalityPermit needed?ThresholdWhat each Hawaii schedule saysVerified
Hawaii CountyIt dependsBefore any new wiring, circuit, service change or rewiring...Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
HonoluluPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...

Inspections and closing out your permit

In Hawaii County, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. In Hawaii County: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. In Hawaii County: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. In Hawaii County: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. In Hawaii County: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. In Hawaii County: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. In Hawaii County: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. In Hawaii County: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Hawaii County permit portal or by phone at (808) 961-8331.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in Hawaii County?
Hawaiʻi County's Building Division issues electrical permits itself (there is no state electrical permit in Hawaiʻi), and a permit is required to erect, install, enlarge, alter, repair, remove, convert, or replace any electrical work. Exemptions are narrow: repairing a fixed motor, water heater or air conditioning control, replacing receptacles and switches with tamper-resistant ones, and maintenance by a licensed electrician that does not repair, replace or rearrange wiring. Permits go only to a licensed electrical contractor or to a homeowner who personally holds a Hawaiʻi electrician license. Always confirm with the County of Hawaiʻi Department of Public Works, Building Division before starting.
How much does an electrical permit cost in Hawaii County?
Hawaiʻi County Code section 5-7-3(b), "PERMIT FEES" table (Chapter 5 Construction Administrative Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0 to $500 | $10"; $501 to $2,000 is $10 for the first $500 plus $1.50 for each additional $100; $2,001 to $25,000 is $32.50 for the first $2,000 plus $7.50 per additional $1,000; $25,001 to $50,000 is $205 for the first $25,000 plus $6 per additional $1,000; $50,001 and up is $355 for the first $50,000 plus $3 per additional $1,000. A plan review fee of twenty percent of the permit fee, minimum $50, is added (section 5-7-1). Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)). See the official fee schedule for current amounts.
Where do you apply for an electrical permit in Hawaii County?
You can apply through the Hawaii County permit portal or contact the County of Hawaiʻi Department of Public Works, Building Division directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Hawaii County?
Under Hawaii law (HRS 444-2(7), 444-2.5, 444-9.1, 444-23(e)): Hawaii lets owners or lessees build or improve residential or farm buildings for their own use, or for use by their grandparents, parents, siblings, or children, without a contractor's license, as long as the building is not offered for sale or lease. The owner must register for the exemption with the county when applying for the building permit, supervise the work, hire licensed subcontractors for any licensed work, and use licensed electricians and plumbers for electrical and plumbing work unless the owner holds that license. Selling or leasing the structure within one year after final county inspection is treated as evidence it was built for sale, unless the permit valuation was under $10,000, the buyer is the owner's employee, or the Contractors License Board finds an unforeseen hardship. A violation carries a fine of up to $5,000 or 50% of the permitted construction value, whichever is greater, for a first offense, and bars the owner from the exemption for three years. Confirm how Hawaii County applies this before you apply.

From the Library

What else needs a permit in Hawaii County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsWhen the remodel moves or replaces pipes or valves, adds wiring, or alters walls or......Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
Deck PermitIt dependsheight of a detached deck or platform; an attached deck is not exempt$10 per 100 sq. ft. or fraction thereof." Plan review fee of twenty percent of the...
EV Charger PermitPermit requiredAny size...Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
Fence PermitIt dependsheight of a fence; retaining walls follow a separate four foot rule...Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
HVAC PermitIt dependsBefore installing, removing, altering, repairing or converting any heating, ventilation......Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
Plumbing PermitIt dependsBefore replacing or rearranging any pipe or valve, adding fixtures, or any gas, water......Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
Pool PermitIt dependswater features and swimming pools at one and two-family dwellings...Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
Roof Replacement PermitIt dependsWhen the new roof uses a different material, or the work affects structural components...Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
Shed PermitIt dependsfloor area of a detached one-story accessory structure on residential zoned land; 1,000 sq ft on agricultural zoned land, 15 feet height limit, 10 feet from property line$10 per 100 sq. ft. or fraction thereof." Plan review fee of twenty percent of the...
Solar PermitPermit requiredAny size...Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...
Water Heater PermitPermit requiredAny size...Code, 2020, ord 20-61): fees are valuation-based under "General Construction": "$0...

Electrical Permit in other Hawaii localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Hawaii County documents; the office above sets the local rules.

How this electrical permit page for Hawaii County was verified. 2 official sources: hawaii-county-public-works-hawaiicountygis.hub.arcgis.com, hawaii-county-public-works-hawaiicountygis.hub.arcgis.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with County of Hawaiʻi Department of Public Works, Building Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across Hawaii localities

Electrical permit rules nationwide

It depends
Get quotes