Quick answer
Hawaii has no statewide crime or fine for building without a permit. Building permits are issued and enforced by the four counties, and state law gives each county the power to make and enforce ordinances on the inspection of buildings and to fix the penalty for breaking them as a misdemeanor, petty misdemeanor, or violation.
Source: HRS 46-1.5(14)(A)(iii), 46-1.5(14)(D), 46-1.5(24)(A)-(B). Details and the official text are cited below.
What Hawaii law says
Hawaii has no statewide crime or fine for building without a permit. Building permits are issued and enforced by the four counties, and state law gives each county the power to make and enforce ordinances on the inspection of buildings and to fix the penalty for breaking them as a misdemeanor, petty misdemeanor, or violation. Counties may also impose civil fines on top of any criminal penalty, but only after giving the violator reasonable notice and a request to correct or stop the violation. Unpaid civil fines can be added to county taxes and fees, recorded as a lien on the owner's real property, and used to hold up other county permits. The dollar amounts and any daily accrual are set in each county's own building code ordinance.
Cited from HRS 46-1.5(14)(A)(iii), 46-1.5(14)(D), 46-1.5(24)(A)-(B): official text. Localities enforce these rules and may add their own fees and procedures on top.
Can you get a permit after the work is done?
No Hawaii statute sets an after-the-fact or as-built permit process or a fee multiplier for unpermitted work; that is left to each county's building code ordinance. What state law does govern is how county civil fines behave once a violation is cited: fines can accrue daily, and after an appeal the county agency reviews the fines that built up, taking into account how long the violation lasted and any effort the owner made to correct it. Correcting the violation (in practice, permitting or removing the work under county rules) is what stops the accrual.
Cited from HRS 46-1.5(24)(D)-(E): official text.
The typical path, whatever your locality calls it: stop any ongoing work, contact the permit office before they contact you, apply for the permit describing what was actually built, and expect the office to require opening up or inspecting concealed work. Voluntarily coming forward generally goes better than waiting for a complaint or a sale to surface it.
What Hawaii permit offices charge when work starts first
The statute above sets the ceiling; the bill comes from the local office. One Hawaii jurisdiction we cover publishes a specific surcharge for work started before the permit, quoted here from the fee schedule or permit page we verified, each linked to the page that carries the citation.
-
Work begun without a permit pays $1,000 plus the fee, or double the fee, whichever is greater (5-7-3(d)).
Hawaii County · from the bathroom remodel permit page · last checked
Jurisdictions not listed either publish no surcharge clause or publish one we could not quote from an official schedule; their permit pages state what we could verify.
Who can pull the permit
Hawaii lets owners or lessees build or improve residential or farm buildings for their own use, or for use by their grandparents, parents, siblings, or children, without a contractor's license, as long as the building is not offered for sale or lease. The owner must register for the exemption with the county when applying for the building permit, supervise the work, hire licensed subcontractors for any licensed work, and use licensed electricians and plumbers for electrical and plumbing work unless the owner holds that license. Selling or leasing the structure within one year after final county inspection is treated as evidence it was built for sale, unless the permit valuation was under $10,000, the buyer is the owner's employee, or the Contractors License Board finds an unforeseen hardship. A violation carries a fine of up to $5,000 or 50% of the permitted construction value, whichever is greater, for a first offense, and bars the owner from the exemption for three years.
Cited from HRS 444-2(7), 444-2.5, 444-9.1, 444-23(e): official text.
Common questions about unpermitted work in Hawaii
- What is the penalty for building without a permit in Hawaii?
- Hawaii has no statewide crime or fine for building without a permit. Building permits are issued and enforced by the four counties, and state law gives each county the power to make and enforce ordinances on the inspection of buildings and to fix the penalty for breaking them as a misdemeanor, petty misdemeanor, or violation. (HRS 46-1.5(14)(A)(iii), 46-1.5(14)(D), 46-1.5(24)(A)-(B))
- Can you get a permit after the work is done in Hawaii?
- No Hawaii statute sets an after-the-fact or as-built permit process or a fee multiplier for unpermitted work; that is left to each county's building code ordinance. What state law does govern is how county civil fines behave once a violation is cited: fines can accrue daily, and after an appeal the county agency reviews the fines that built up, taking into account how long the violation lasted and any effort the owner made to correct it. (HRS 46-1.5(24)(D)-(E))
- Who can pull a permit in Hawaii?
- Hawaii lets owners or lessees build or improve residential or farm buildings for their own use, or for use by their grandparents, parents, siblings, or children, without a contractor's license, as long as the building is not offered for sale or lease. The owner must register for the exemption with the county when applying for the building permit, supervise the work, hire licensed subcontractors for any licensed work, and use licensed electricians and plumbers for electrical and plumbing work unless the owner holds that license. (HRS 444-2(7), 444-2.5, 444-9.1, 444-23(e))
Was a permit needed in the first place?
Not every project needs one. Across the 2 Hawaii jurisdictions we have verified, 0 answered rules need no permit at all and 14 turn on a size or scope condition the jurisdiction publishes. If the work falls under one of those, the question changes from penalties to paperwork.
What you can build without a permit in Hawaii, jurisdiction by jurisdiction
Related situations in Hawaii
- A stop work order was posted: what it means and how to lift it
- How to find out if a permit was pulled, or report work with none
- A wall was removed without a permit
- Selling a house with unpermitted work
- Buying a house with unpermitted work
How Hawaii compares: building without a permit, state by state.
See which parts of the work needed a permit, then send us the details
Permit help
Want help getting unpermitted work approved?
Tell us where your project stands. Where we have a vetted local pro who handles permits in Hawaii, we connect you; otherwise we reply with the exact steps and office links for your situation. Free to ask; no obligation.
PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
Your local permit office
Enforcement, after-the-fact fees, and the exact fix-it process are local. We cover these Hawaii permit offices:
Official sources
This page summarizes state law from the official sources listed above, with a last checked date. It is not legal advice. Penalties and procedures are applied by local offices and courts case by case; for anything contested or high stakes, confirm with your permit office or a licensed professional in Hawaii.