Solar Permit in Honolulu, Hawaii
Permit required
Yes, a permit is required
Before installing solar PV (with or without a battery) or a solar water heater.
Quick answer
Solar PV is electrical work, and ROH 18-3.1(a)(2) requires a building permit for 'Any electrical work'; a solar water heater is water heating equipment under 18-3.1(a)(3). DPP runs solar through HNL Build: single-family and detached-duplex PV, PV with battery, and solar water heating qualify for an instant online Quick Permit when the property is outside a flood zone and has no advisory or violation, otherwise a building permit with plans is needed. DPP also offers an expedited clean-energy process for qualifying systems up to 20 kW.
- Issued by
- City and County of Honolulu Department of Planning and Permitting (DPP), Building Division
- Phone
- (808) 768-8000
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your Contractors License Board (Department of Commerce and Consumer Affairs, Professional and Vocational Licensing Division) license active, and under which business name? Verify it on mypvl.dcca.hawaii.gov.
Hawaii's owner-builder rule (HRS 444-2(7), 444-2.5, 444-9.1, 444-23(e)) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Honolulu
- Fee basis
- Project valuation
- Fee schedule in force
- Official scheduleRead .
- No per-item schedule is published for this project.
- ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500;
- $8 + $2.50 per $100 or fraction thereof from $500.01 to $1,000;
- $12 + $2.20 per $100 or fraction thereof from $1,000.01 to $20,000;
- $82 + $18 per $1,000 or fraction thereof from $20,000.01 to $50,000;
- $286 + $14 per $1,000 or fraction thereof from $50,000.01 to $100,000, with lower rates per $1,000 for larger projects.
- When plans are required, a plan review fee of 20 percent of the tentative building permit fee, not greater than $25,000, is added (ROH 18-6.1(a)).
- Work started before the permit is obtained is charged triple fees (ROH 18-6.2(d)).
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in Honolulu
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
City and County of Honolulu Department of Planning and Permitting (DPP), Building Division
- 650 South King Street, 7th Floor, Honolulu, Hawaii 96813
- Phone: (808) 768-8000
- Email: dpp@honolulu.gov
Solar Permit in Honolulu compared with nearby Hawaii localities
| Locality | Permit needed? | Threshold | What each Hawaii schedule says | Verified |
|---|---|---|---|---|
| Honolulu | Permit required | Any size | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 | |
| Hawaii County | Permit required | Any size | See schedule |
Your Solar Permit checklist for Honolulu
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: honolulu.gov: building permits home.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Honolulu permit portal.
- Keep the office details handy. City and County of Honolulu Department of Planning and Permitting (DPP), Building Division. Phone: (808) 768-8000. Email: dpp@honolulu.gov. Address: 650 South King Street, 7th Floor, Honolulu, Hawaii 96813.
Compiled from the official sources on this page. Last checked .
Permitting activity in Honolulu
In 2025, Honolulu authorized permits for 1,446 new residential housing units (607 single-family, 839 in multi-family buildings), valued at $465M, down from 1,638 the year before. That works out to about 2.3 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 622,271.
What else needs a permit in Honolulu
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | interior remodeling that changes no room count, wall, window location, or electrical, plumbing or mechanical installation | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| Deck Permit | Permit required | Any size | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| Electrical Permit | Permit required | Any size | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| EV Charger Permit | Permit required | Any size | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| Fence Permit | It depends | fence height at which a building permit is required; the exemption does not apply on a street corner or in a flood zone | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| HVAC Permit | Permit required | Any size | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| Patio Permit | It depends | uncovered walkways and outside paving within private property, not on a street corner or in a flood zone | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| Plumbing Permit | Permit required | Any size | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| Roof Replacement Permit | It depends | reroofing that does not adversely affect structural components, Group R-3 and U occupancies | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| Shed Permit | It depends | aggregate floor area of one-story detached accessory storage buildings, tool sheds and playhouses | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
| Water Heater Permit | Permit required | Any size | ROH Chapter 18 Table No. 18-A prices the building permit from the total estimated valuation of work: $20 for $0.01 to $500 |
Frequently asked questions
- Do you need a solar permit in Honolulu?
- Yes, before installing solar PV (with or without a battery) or a solar water heater. If you are unsure how that applies to your project, call the permit office at (808) 768-8000 before you start.
- How much does a solar permit cost in Honolulu?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 17 Nov 2026. For the figure on your own project, call the permit office at (808) 768-8000.
- Where do you apply for a solar permit in Honolulu?
- You can apply through the Honolulu permit portal or contact the City and County of Honolulu Department of Planning and Permitting (DPP), Building Division directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Honolulu?
- Under Hawaii law (HRS 444-2(7), 444-2.5, 444-9.1, 444-23(e)): Hawaii lets owners or lessees build or improve residential or farm buildings for their own use, or for use by their grandparents, parents, siblings, or children, without a contractor's license, as long as the building is not offered for sale or lease. The owner must register for the exemption with the county when applying for the building permit, supervise the work, hire licensed subcontractors for any licensed work, and use licensed electricians and plumbers for electrical and plumbing work unless the owner holds that license. Selling or leasing the structure within one year after final county inspection is treated as evidence it was built for sale, unless the permit valuation was under $10,000, the buyer is the owner's employee, or the Contractors License Board finds an unforeseen hardship. A violation carries a fine of up to $5,000 or 50% of the permitted construction value, whichever is greater, for a first offense, and bars the owner from the exemption for three years. Confirm how Honolulu applies this before you apply.
From the Library
Solar Permit in other Hawaii localities
Everything above, sourced
How this solar permit page for Honolulu was verified. 2 official sources: honolulu.gov, honolulu.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City and County of Honolulu Department of Planning and Permitting (DPP), Building Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page