Hawaii / Honolulu

Patio Permit in Honolulu, Hawaii

It depends

Sometimes, depending on the project

Before pouring or paving a patio on a street corner lot or in a flood zone, or before building any patio cover, roof or enclosure (a structure under ROH 18-3.1(a)(1)).

Confirmed on official page Verified

Issued byCity and County of Honolulu Department of Planning and Permitting (DPP), Building Division

By Mario Bailey, verified against official sources

Quick answer

Honolulu's permit exemptions, ROH 18-3.1(b)(6) as rewritten by Ordinance 23-13, list 'Walkways and outside paving that are within private property' among structures that need no building permit, provided they are not located on a street corner or in a flood zone. A ground-level uncovered patio therefore needs no permit on an ordinary lot, but the same paving on a corner lot or in a flood zone does. A covered patio is a structure and needs a building permit.

Typical threshold: uncovered walkways and outside paving within private property, not on a street corner or in a flood zone.

Who is pulling this permit?

Hire it out

Sponsored

If a contractor builds your patio, they usually handle any required permit as part of the job. Compare a few bids before you commit.

Compare patio contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before pouring or paving a patio on a street corner lot or in a flood zone, or before building any patio cover, roof or enclosure (a structure under ROH 18-3.1(a)(1)).

What a patio permit costs in Honolulu

Line item
patio permitBy formulaValuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Honolulu

In Honolulu, applying for a patio permit means submitting a site plan and framing plans for a roofed patio cover, since a cover is treated as its own permitted structure regardless of size. A plain concrete or paver patio slab at or near grade is, by contrast, often exempt from that same building permit requirement.

What most patio permit applications include:

  • Filing a permit application with the local building department, which only the property owner or an authorized agent may sign, since a patio cover is treated as its own permitted structure regardless of size (IRC R105.1).
  • For Honolulu, a scaled site plan showing the new patio cover's size and location relative to the house and other existing structures, with dimensioned distances to all property lines so required setbacks can be verified before the permit is approved (IRC R106.2).
  • Construction documents such as a framing plan and elevation, showing rafter or beam sizes and spacing, the distance between supporting posts, and the method of attachment to the house, drawn with enough clarity for the building official to confirm the work will conform to the code (IRC R106.1).
  • For the roof structure itself, plans showing compliance with the patio cover appendix's structural limits, such as adequate footing sizes for the applied post loads, since a shallow slab on grade may substitute for a deeper footing only in limited cases up to about 750 pounds of load per post (IRC Appendix AH, Section AH105.2).
  • By contrast, an at grade concrete or paver patio that is not attached to the dwelling and stays within the code's small flatwork thresholds, similar to a sidewalk, driveway, or low deck under 200 square feet and 30 inches high, commonly needs no building permit at all, so none of the plan review steps above apply (IRC R105.2).

General submittal guidance from 2021 International Residential Code (IRC), Sections R105 and R106, with Appendix AH Patio Covers (named Appendix H in the 2012, 2015, and 2018 editions). Source. City and County of Honolulu Department of Planning and Permitting (DPP), Building Division sets the exact checklist for Honolulu.

Where to apply in Honolulu:

City and County of Honolulu Department of Planning and Permitting (DPP), Building Division

  • 650 South King Street, 7th Floor, Honolulu, Hawaii 96813
  • Phone: (808) 768-8000
  • Email: dpp@honolulu.gov

Patio Permit in Honolulu compared with nearby Hawaii localities

LocalityPermit needed?ThresholdWhat each Hawaii schedule saysVerified
HonoluluIt dependsuncovered walkways and outside paving within private property, not on a street corner or in a flood zone...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Hawaii CountyNot confirmedNot confirmedNot published

Inspections and closing out your permit

In Honolulu, a permitted patio cover follows the same footing, frame, and final inspection sequence used for any small accessory structure, since the posts and roof framing have to be checked before they are covered and again once the work is done. An at grade patio slab that qualifies as exempt flatwork usually needs no building inspection at all, because inspections only attach to work that required a permit in the first place.

  1. In Honolulu: a footing inspection once the excavation, forms, and any reinforcing steel are in place but before concrete is poured, confirming the posts supporting a patio cover will bear on adequate footings (IRC R109.1.1).
  2. In Honolulu: a frame inspection after the rafters, beams, posts, and any required rough in work are in place but before the roof sheathing or covering material conceals them, since a solid patio cover roof cannot be signed off once it is covered without this check (IRC R109.1.4).
  3. In Honolulu: a final inspection once all permitted work, including roofing and post anchorage, is complete, which the code requires before the structure may be used (IRC R109.1.6).
  4. In Honolulu: an at grade concrete or paver patio that qualifies as exempt flatwork under the permit rules is not subject to any of these inspection stages, since the inspection sequence only attaches to work that required a permit in the first place (IRC R105.2).
  5. In Honolulu: each inspection has to be requested by the permit holder rather than happening automatically, and the approved plans and permit card need to be on site and available when the inspector arrives (IRC R109.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Honolulu permit portal or by phone at (808) 768-8000.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a patio permit in Honolulu?
Honolulu's permit exemptions, ROH 18-3.1(b)(6) as rewritten by Ordinance 23-13, list 'Walkways and outside paving that are within private property' among structures that need no building permit, provided they are not located on a street corner or in a flood zone. A ground-level uncovered patio therefore needs no permit on an ordinary lot, but the same paving on a corner lot or in a flood zone does. A covered patio is a structure and needs a building permit. Uncovered walkways and outside paving within private property, not on a street corner or in a flood zone. Always confirm with the office before starting.
How much does a patio permit cost in Honolulu?
Valuation-based: ROH 18-6.2 permit fee on the fair market value of labor and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000) under ROH 18-6.1(a) only when plans are required. No per-item schedule is published; DPP's Fee Calculator computes the fee from the project value. See the official fee schedule for current amounts.
Where do you apply for a patio permit in Honolulu?
You can apply through the Honolulu permit portal or contact the City and County of Honolulu Department of Planning and Permitting (DPP), Building Division directly. The links are listed on this page.
Can a homeowner pull a patio permit themselves in Honolulu?
Under Hawaii law (HRS 444-2(7), 444-2.5, 444-9.1, 444-23(e)): Hawaii lets owners or lessees build or improve residential or farm buildings for their own use, or for use by their grandparents, parents, siblings, or children, without a contractor's license, as long as the building is not offered for sale or lease. The owner must register for the exemption with the county when applying for the building permit, supervise the work, hire licensed subcontractors for any licensed work, and use licensed electricians and plumbers for electrical and plumbing work unless the owner holds that license. Selling or leasing the structure within one year after final county inspection is treated as evidence it was built for sale, unless the permit valuation was under $10,000, the buyer is the owner's employee, or the Contractors License Board finds an unforeseen hardship. A violation carries a fine of up to $5,000 or 50% of the permitted construction value, whichever is greater, for a first offense, and bars the owner from the exemption for three years. Confirm how Honolulu applies this before you apply.

From the Library

What else needs a permit in Honolulu

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsinterior remodeling that changes no room count, wall, window location, or electrical, plumbing or mechanical installation...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Deck PermitPermit requiredAny size...under ROH 18-6.2, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Electrical PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
EV Charger PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Fence PermitIt dependsfence height at which a building permit is required; the exemption does not apply on a street corner or in a flood zone...under ROH 18-6.2, with a plan review fee of 20% of the permit fee (maximum $25,000)...
HVAC PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Plumbing PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Roof Replacement PermitIt dependsreroofing that does not adversely affect structural components, Group R-3 and U occupancies...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Shed PermitIt dependsaggregate floor area of one-story detached accessory storage buildings, tool sheds and playhouses...are valuation-based under ROH 18-6.2 (plus a 20% plan review fee, maximum $25,000...
Solar PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...
Water Heater PermitPermit requiredAny size...and materials, plus a plan review fee of 20% of the permit fee (maximum $25,000)...

Patio Permit in other Hawaii localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Honolulu documents; the office above sets the local rules.

How this patio permit page for Honolulu was verified. 2 official sources: honolulu.gov, hnldoc.ehawaii.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City and County of Honolulu Department of Planning and Permitting (DPP), Building Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Patio Permit requirements across Hawaii localities

Patio permit rules nationwide

It depends
Get quotes