Michigan / Grand Rapids

Plumbing Permit in Grand Rapids, Michigan

It depends

Sometimes, depending on the project

Before adding lines or pipes in walls and floors, adding or working on a water heater, or upgrading water service.

Confirmed on official page Verified City of Grand Rapids Development Center, Building Inspections Division

By Mario Bailey, verified against official sources

Quick answer

Grand Rapids requires a plumbing permit for plumbing work beyond fixture swaps, and names the exemption explicitly: replacing a faucet, sink, toilet or similar fixture does not need one. Work that does need a permit includes adding lines and pipes in walls and floors, adding or working on a water heater, and upgrading water services. There is a jurisdictional handoff to watch for: any underground plumbing work outside the building footprint requires a separate inspection permit issued by the Water System, and only a City-licensed contractor can perform that work. A homeowner of a single-family home may pull a plumbing permit for their primary residence at the Development Center, while properties with 2 or more units and landlord-owned rentals require a licensed and registered plumbing contractor.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before adding lines or pipes in walls and floors, adding or working on a water heater, or upgrading water service.

What a plumbing permit costs in Grand Rapids

Line item
plumbing permitBy formulaFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026, Plumbing Permit Fees: "Application (Includes 1 inspection) $52.00" plus per fixture fees, most of them $5.00 each, covering items such as "Water Closet/Toilet", "Lavatory", "Bath Tub-Shower", "Sink-Kitchen", "Floor Drain/Floor Sink/Trench Drain" and "Gas Piping per Opening". "Water Heater" is $21.00, and water distribution runs from "Water Distribution 3/4\" $6.00" up to "Distribution System Over 2\" $36.00". Working prior to permit adds an "Admin Fee (working prior to permit) $173.00".
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Grand Rapids compares in Michigan

No Michigan jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Ann ArborPermit requiredPlumbing Permit Fees (effective July 1, 2017): $15 base application fee...
DetroitIt dependsBSEED Fee Schedule effective January 1, 2024, modified 7/18/2025, PLUMBING...
Grand Rapidsthis pageIt dependsFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026...
Sterling HeightsPermit requiredPlumbing Permit Application 2026-2027: non-refundable application fee $55.00...

How to apply in Grand Rapids

You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.

What most plumbing permit applications include:

  • A permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
  • The application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
  • Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
  • Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
  • Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).

General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. City of Grand Rapids Development Center, Building Inspections Division sets the exact checklist for Grand Rapids.

Where to apply in Grand Rapids:

City of Grand Rapids Development Center, Building Inspections Division

  • Development Center, 1120 Monroe Ave. NW, 3rd Floor, Grand Rapids, Michigan 49503
  • Phone: 616-456-4100
  • Email: devcenter@grcity.us

Inspections and closing out your permit

Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.

  1. Piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
  2. Rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
  3. Rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
  4. The water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
  5. The framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
  6. At the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
  7. Final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Grand Rapids permit portal or by phone at 616-456-4100.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a plumbing permit in Grand Rapids?
Grand Rapids requires a plumbing permit for plumbing work beyond fixture swaps, and names the exemption explicitly: replacing a faucet, sink, toilet or similar fixture does not need one. Work that does need a permit includes adding lines and pipes in walls and floors, adding or working on a water heater, and upgrading water services. There is a jurisdictional handoff to watch for: any underground plumbing work outside the building footprint requires a separate inspection permit issued by the Water System, and only a City-licensed contractor can perform that work. A homeowner of a single-family home may pull a plumbing permit for their primary residence at the Development Center, while properties with 2 or more units and landlord-owned rentals require a licensed and registered plumbing contractor. Always confirm with the City of Grand Rapids Development Center, Building Inspections Division before starting.
How much does a plumbing permit cost in Grand Rapids?
FY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026, Plumbing Permit Fees: "Application (Includes 1 inspection) $52.00" plus per fixture fees, most of them $5.00 each, covering items such as "Water Closet/Toilet", "Lavatory", "Bath Tub-Shower", "Sink-Kitchen", "Floor Drain/Floor Sink/Trench Drain" and "Gas Piping per Opening". "Water Heater" is $21.00, and water distribution runs from "Water Distribution 3/4\" $6.00" up to "Distribution System Over 2\" $36.00". Working prior to permit adds an "Admin Fee (working prior to permit) $173.00". See the official fee schedule for current amounts.
How long does a plumbing permit take in Grand Rapids?
In Grand Rapids, a plumbing permit typically takes 1 to 2 business days. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a plumbing permit in Grand Rapids?
You can apply through the Grand Rapids permit portal or contact the City of Grand Rapids Development Center, Building Inspections Division directly. The links are listed on this page.
Can a homeowner pull a plumbing permit themselves in Grand Rapids?
Under Michigan law (MCL 339.2403(b), (c); MCL 339.2401(a)(iii), (b)(ii)(A); MCL 339.5737(3)(g); MCL 339.6107(2)(d); MCL 339.5819): Yes. A Michigan homeowner may pull the building permit and do the work on their own home without a residential builder license, because the licensing article both defines the trade to exclude them and exempts them outright. MCL 339.2401(a)(iii) says a residential builder is a person that erects a residential structure except for the person's own use and occupancy on the person's property, and MCL 339.2403(b) exempts an owner of property with reference to a structure on the property for the owner's own use and occupancy. Own use and occupancy is the condition, so the exemption does not cover building to sell, and MCL 339.2403(c) limits owners of rental property to maintenance and alteration of that property. The statute sets no cap on how many times a homeowner may use the exemption; the only frequency rule in the article catches purchase, substantial rehabilitation, and resale of the same structure more than twice in 1 calendar year, and MCL 339.2401(b)(ii)(A) exempts work for the person's own use and occupancy from even that. Homeowners can also pull their own trade permits: electrical work in a single family home and accompanying outbuildings owned and occupied or to be occupied by the person doing the work (MCL 339.5737(3)(g)), their own plumbing, building sewer, or private sewer in their single-family dwelling if a permit is secured (MCL 339.6107(2)(d)), and a heating or refrigerating system if the owner affirms in the permit application that they are or will become the owner and occupant (MCL 339.5819). Confirm how Grand Rapids applies this before you apply.

From the Library

What else needs a permit in Grand Rapids

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsfloor area at which a freestanding deck with supporting beams, joists or posts requires a building permit; a deck attached to or adjacent to a house requires one at any sizeFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026, Building...
Electrical PermitIt dependsNot specifiedFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026, Electrical...
Fence PermitPermit requiredNot specifiedFY 2027 Planning, Design and Development Fee Schedule, Planning Fees effective July 1...
HVAC PermitIt dependsNot specifiedFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026, Mechanical...
Pool PermitIt dependswater depth a pool, hot tub, spa or similar structure is capable of reachingFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026, Building...
Roof Replacement PermitPermit requiredNot specifiedFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026, Building...
Shed PermitPermit requiredNot specifiedFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026.
Solar PermitPermit requiredNot specifiedFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026, Electrical...

Plumbing Permit in other Michigan localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Grand Rapids documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Grand Rapids Development Center, Building Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page