Plumbing Permit in Little Rock, Arkansas
It depends
Sometimes, depending on the project
Before installing plumbing or gas piping, or changing an existing system.
Issued byCity of Little Rock Planning and Development Department, Building Codes Division
By Mario Bailey, verified against official sources
Quick answer
Little Rock requires a City permit to install plumbing or gas piping, or to make any change to an existing plumbing or gas system. No permit is needed to clear stoppages, put a temporary clamp on a leak, replace a fixture trap or fixture supply lines, replace a clothes washer where no rough-in is required, or connect a range, dryer, space heater or similar gas appliance to an existing cutoff valve without altering the piping. A qualified homeowner may pull a homeowner's permit for the one-family home he or she owns and lives in.
Typical threshold: Clearing stoppages, temporary leak clamps, replacing a fixture trap or supply lines, and like-for-like gas appliance hookups are exempt; new or altered piping needs a permit.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Plumbing permits are usually pulled by the plumber doing the job. If you are still choosing one, compare a few quotes first.
Compare plumber quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before installing plumbing or gas piping, or changing an existing system.
What a plumbing permit costs in Little Rock
How to apply in Little Rock
In Little Rock, you apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.
What most plumbing permit applications include:
- For Little Rock, a permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
- For Little Rock, the application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
- Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
- Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
- Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).
General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. City of Little Rock Planning and Development Department, Building Codes Division sets the exact checklist for Little Rock.
Where to apply in Little Rock:
City of Little Rock Planning and Development Department, Building Codes Division
- 723 West Markham Street, Little Rock, AR 72201
- Phone: (501) 371-4832
- Email: Permits@littlerock.gov
Inspections and closing out your permit
In Little Rock, plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.
- In Little Rock: piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
- In Little Rock: rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
- In Little Rock: rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
- In Little Rock: the water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
- In Little Rock: the framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
- In Little Rock: at the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
- In Little Rock: final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Little Rock permit portal or by phone at (501) 371-4832.
Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Plumbing Permit checklist for Little Rock
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: Clearing stoppages, temporary leak clamps, replacing a fixture trap or supply lines, and like-for-like gas appliance hookups are exempt; new or altered piping needs a permit. Usually needed: Before installing plumbing or gas piping, or changing an existing system.
- Budget the fee. Repair/alteration items: "Each plumbing fixture outlet or appliance" $6.18; "Water service" $30.90; "Water housepiping" $30.90; "Gas housepiping" $30.90; "Water heater" $17.51; "Inspection" $25.75; new one- and two-family dwellings $0.10 per square foot under roof; "Minimum fee for any permit for plumbing work shall be fifty dollars ($50.00)." Work without a permit pays three times the permit fee. Little Rock Code Sec. 8-31(c), as amended through Ord. No. 22,703 (December 16, 2025), read on Municode. Official fee schedule.
- Apply. In Little Rock, you apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit. Start at the Little Rock permit portal.
- Keep the office details handy. City of Little Rock Planning and Development Department, Building Codes Division. Phone: (501) 371-4832. Address: 723 West Markham Street, Little Rock, AR 72201.
- Plan for inspections. In Little Rock, plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a plumbing permit in Little Rock?
- Little Rock requires a City permit to install plumbing or gas piping, or to make any change to an existing plumbing or gas system. No permit is needed to clear stoppages, put a temporary clamp on a leak, replace a fixture trap or fixture supply lines, replace a clothes washer where no rough-in is required, or connect a range, dryer, space heater or similar gas appliance to an existing cutoff valve without altering the piping. A qualified homeowner may pull a homeowner's permit for the one-family home he or she owns and lives in. Clearing stoppages, temporary leak clamps, replacing a fixture trap or supply lines, and like-for-like gas appliance hookups are exempt; new or altered piping needs a permit. Always confirm with the office before starting.
- How much does a plumbing permit cost in Little Rock?
- Repair/alteration items: "Each plumbing fixture outlet or appliance" $6.18; "Water service" $30.90; "Water housepiping" $30.90; "Gas housepiping" $30.90; "Water heater" $17.51; "Inspection" $25.75; new one- and two-family dwellings $0.10 per square foot under roof; "Minimum fee for any permit for plumbing work shall be fifty dollars ($50.00)." Work without a permit pays three times the permit fee. Little Rock Code Sec. 8-31(c), as amended through Ord. No. 22,703 (December 16, 2025), read on Municode. See the official fee schedule for current amounts.
- Where do you apply for a plumbing permit in Little Rock?
- You can apply through the Little Rock permit portal or contact the City of Little Rock Planning and Development Department, Building Codes Division directly. The links are listed on this page.
- Can a homeowner pull a plumbing permit themselves in Little Rock?
- Under Arkansas law (Ark. Code 17-25-513(1), (2); 17-38-302(1); 17-28-101(9); 17-28-102(b); 17-28-305(b)(2); 17-25-101(a)(2)): Yes. A person building his or her own residence does not need a residential building contractor license unless they build more than one residence in a calendar year, and the owner of a single family residence may act as his or her own home improvement contractor (17-25-513(1)-(2)). Plumbing work done by a property owner in a building the owner owns and occupies as his or her home is exempt from plumber licensing unless a local ordinance requires a license (17-38-302(1)). The electrical licensing law does not require an individual to hold a license to do electrical work on his or her primary residence, defined as an unattached single-family dwelling, unless other state law or a local ordinance requires it, and a city or county may require the owner to show technical competency first (17-28-102(b), 17-28-305(b)(2)). These are licensing exemptions, not permit exemptions: the owner still needs whatever local permits apply. No state owner-builder disclosure form or resale restriction was found. Confirm how Little Rock applies this before you apply.
From the Library
What else needs a permit in Little Rock
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Painting, floor coverings, cosmetic changes and fixture trap or supply-line swaps are exempt; moving plumbing, any electrical work or work over $5,000 needs permits | Building permit (if required) on the valuation schedule with a $51.50 minimum |
| Deck Permit | Permit required | Any size | ...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus... |
| Electrical Permit | Permit required | Any size | Repair/alteration/addition items, for example openings 1 to 20, $12.36 |
| EV Charger Permit | Permit required | Any size | ...special equipment, outdoor lighting or any circuits not already covered"... |
| Fence Permit | It depends | Height of a residential fence | ...subsection 8-3 l(c)(l)a." (the building permit valuation schedule), with a $51.50... |
| HVAC Permit | Permit required | Any size | ...for replacements, repairs, alterations and additions by total valuation: "$500.00... |
| Patio Permit | It depends | Value of the work, including material and labor | ...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus... |
| Pool Permit | Permit required | Any size | ...8-31(c)(l)a., but minimum fee shall be fee of fifty-one and 50/100 dollars... |
| Roof Replacement Permit | No permit needed | Exempt | Not published |
| Shed Permit | It depends | Floor area of a one-story detached tool or storage shed, playhouse or similar accessory structure | ...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus... |
| Solar Permit | Permit required | Any size | ...assessed on the building permit valuation schedule (Sec. 8-31(c)(1)n.), $51.50... |
| Water Heater Permit | Permit required | Any size | Plumbing permit line item "Water heater .....$17.51" (minimum plumbing permit $50.00) |
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Little Rock documents; the office above sets the local rules.
How this plumbing permit page for Little Rock was verified. 2 official sources: littlerock.gov, library.municode.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Little Rock Planning and Development Department, Building Codes Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page