Solar Permit in Little Rock, Arkansas
Permit required
Yes, a permit is required
Before installing roof-mounted or ground-mounted solar panels.
Issued byCity of Little Rock Planning and Development Department, Building Codes Division
By Mario Bailey, verified against official sources
Quick answer
Little Rock lists solar panels among its miscellaneous building permits, assessed on the building permit valuation schedule, and the City's inspection list has a solar panel final inspection. Connecting the system is electrical work, which needs a City electrical permit pulled by a licensed master electrician.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
Arkansas's owner-builder rule (Ark. Code 17-25-513(1), (2); 17-38-302(1); 17-28-101(9); 17-28-102(b); 17-28-305(b)(2); 17-25-101(a)(2)) sets what you may do on your own home without hiring anyone. Read the statute.
When a permit is usually needed
Before installing roof-mounted or ground-mounted solar panels.
What a solar permit costs in Little Rock
How to apply in Little Rock
In Little Rock, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.
What most solar permit applications include:
- Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
- For Little Rock, the plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
- Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
- For Little Rock, the site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
- For Little Rock, the one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
- Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
- Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).
General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Little Rock Planning and Development Department, Building Codes Division sets the exact checklist for Little Rock.
Where to apply in Little Rock:
City of Little Rock Planning and Development Department, Building Codes Division
- 723 West Markham Street, Little Rock, AR 72201
- Phone: (501) 371-4832
- Email: Permits@littlerock.gov
Inspections and closing out your permit
In Little Rock, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
- In Little Rock: where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
- In Little Rock: the inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
- In Little Rock: pV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
- In Little Rock: bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
- In Little Rock: at the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
- In Little Rock: utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Little Rock permit portal or by phone at (501) 371-4832.
Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Solar Permit checklist for Little Rock
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing roof-mounted or ground-mounted solar panels.
- Budget the fee. Solar panels are a miscellaneous permit assessed on the building permit valuation schedule (Sec. 8-31(c)(1)n.), $51.50 minimum building permit fee, plus an electrical permit (minimum fee for electrical work $50.00; for example "Miscellaneous. Special circuits [...]" $18.54 per item). Little Rock Code Sec. 8-31(c), as amended through Ord. No. 22,703 (December 16, 2025), read on Municode. Official fee schedule.
- Apply. In Little Rock, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit. Start at the Little Rock permit portal.
- Keep the office details handy. City of Little Rock Planning and Development Department, Building Codes Division. Phone: (501) 371-4832. Address: 723 West Markham Street, Little Rock, AR 72201.
- Plan for inspections. In Little Rock, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a solar permit in Little Rock?
- Little Rock lists solar panels among its miscellaneous building permits, assessed on the building permit valuation schedule, and the City's inspection list has a solar panel final inspection. Connecting the system is electrical work, which needs a City electrical permit pulled by a licensed master electrician. Always confirm with the City of Little Rock Planning and Development Department, Building Codes Division before starting.
- How much does a solar permit cost in Little Rock?
- Solar panels are a miscellaneous permit assessed on the building permit valuation schedule (Sec. 8-31(c)(1)n.), $51.50 minimum building permit fee, plus an electrical permit (minimum fee for electrical work $50.00; for example "Miscellaneous. Special circuits [...]" $18.54 per item). Little Rock Code Sec. 8-31(c), as amended through Ord. No. 22,703 (December 16, 2025), read on Municode. See the official fee schedule for current amounts.
- Where do you apply for a solar permit in Little Rock?
- You can apply through the Little Rock permit portal or contact the City of Little Rock Planning and Development Department, Building Codes Division directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Little Rock?
- Under Arkansas law (Ark. Code 17-25-513(1), (2); 17-38-302(1); 17-28-101(9); 17-28-102(b); 17-28-305(b)(2); 17-25-101(a)(2)): Yes. A person building his or her own residence does not need a residential building contractor license unless they build more than one residence in a calendar year, and the owner of a single family residence may act as his or her own home improvement contractor (17-25-513(1)-(2)). Plumbing work done by a property owner in a building the owner owns and occupies as his or her home is exempt from plumber licensing unless a local ordinance requires a license (17-38-302(1)). The electrical licensing law does not require an individual to hold a license to do electrical work on his or her primary residence, defined as an unattached single-family dwelling, unless other state law or a local ordinance requires it, and a city or county may require the owner to show technical competency first (17-28-102(b), 17-28-305(b)(2)). These are licensing exemptions, not permit exemptions: the owner still needs whatever local permits apply. No state owner-builder disclosure form or resale restriction was found. Confirm how Little Rock applies this before you apply.
From the Library
What else needs a permit in Little Rock
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Painting, floor coverings, cosmetic changes and fixture trap or supply-line swaps are exempt; moving plumbing, any electrical work or work over $5,000 needs permits | Building permit (if required) on the valuation schedule with a $51.50 minimum |
| Deck Permit | Permit required | Any size | ...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus... |
| Electrical Permit | Permit required | Any size | Repair/alteration/addition items, for example openings 1 to 20, $12.36 |
| EV Charger Permit | Permit required | Any size | ...special equipment, outdoor lighting or any circuits not already covered"... |
| Fence Permit | It depends | Height of a residential fence | ...subsection 8-3 l(c)(l)a." (the building permit valuation schedule), with a $51.50... |
| HVAC Permit | Permit required | Any size | ...for replacements, repairs, alterations and additions by total valuation: "$500.00... |
| Patio Permit | It depends | Value of the work, including material and labor | ...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus... |
| Plumbing Permit | It depends | Clearing stoppages, temporary leak clamps, replacing a fixture trap or supply lines, and like-for-like gas appliance hookups are exempt; new or altered piping needs a permit | Repair/alteration items: "Each plumbing fixture outlet or appliance" $6.18 |
| Pool Permit | Permit required | Any size | ...8-31(c)(l)a., but minimum fee shall be fee of fifty-one and 50/100 dollars... |
| Roof Replacement Permit | No permit needed | Exempt | Not published |
| Shed Permit | It depends | Floor area of a one-story detached tool or storage shed, playhouse or similar accessory structure | ...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus... |
| Water Heater Permit | Permit required | Any size | Plumbing permit line item "Water heater .....$17.51" (minimum plumbing permit $50.00) |
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Little Rock documents; the office above sets the local rules.
How this solar permit page for Little Rock was verified. 2 official sources: littlerock.gov, library.municode.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Little Rock Planning and Development Department, Building Codes Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page