Arkansas / Little Rock

Electrical Permit in Little Rock, Arkansas

Permit required

Yes, a permit is required

Before any electrical work, new or altered.

Confirmed on official page Verified

Issued byCity of Little Rock Planning and Development Department, Building Codes Division

By Mario Bailey, verified against official sources

Quick answer

Little Rock's electrical code says no person may install or perform any electrical work without a City electrical permit, and it publishes no exemptions. Permits are issued to state-licensed electricians; a homeowner may pull one for work on his or her own home only if he or she holds a current Arkansas master or journeyman electrician's license.

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before any electrical work, new or altered.

What an electrical permit costs in Little Rock

Line item
electrical permitBy formulaRepair/alteration/addition items, for example openings 1 to 20, $12.36; a load center up to 200 amps, $39.14; the first meter loop, $16.48; "Miscellaneous. Special circuits [...]" $18.54; "Inspection (each)" $25.75; new one- and two-family dwellings $0.10 per square foot under roof; "Minimum fee for permit for electrical work shall be fifty dollars ($50.00)". Work found without a permit pays three times the permit fee. Little Rock Code Sec. 8-31(c), as amended through Ord. No. 22,703 (December 16, 2025), read on Municode.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Little Rock

In Little Rock, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • For Little Rock, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • For Little Rock, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of Little Rock Planning and Development Department, Building Codes Division sets the exact checklist for Little Rock.

Where to apply in Little Rock:

City of Little Rock Planning and Development Department, Building Codes Division

Inspections and closing out your permit

In Little Rock, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. In Little Rock: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. In Little Rock: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. In Little Rock: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. In Little Rock: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. In Little Rock: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. In Little Rock: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. In Little Rock: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Little Rock permit portal or by phone at (501) 371-4832.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in Little Rock?
Little Rock's electrical code says no person may install or perform any electrical work without a City electrical permit, and it publishes no exemptions. Permits are issued to state-licensed electricians; a homeowner may pull one for work on his or her own home only if he or she holds a current Arkansas master or journeyman electrician's license. Always confirm with the City of Little Rock Planning and Development Department, Building Codes Division before starting.
How much does an electrical permit cost in Little Rock?
Repair/alteration/addition items, for example openings 1 to 20, $12.36; a load center up to 200 amps, $39.14; the first meter loop, $16.48; "Miscellaneous. Special circuits [...]" $18.54; "Inspection (each)" $25.75; new one- and two-family dwellings $0.10 per square foot under roof; "Minimum fee for permit for electrical work shall be fifty dollars ($50.00)". Work found without a permit pays three times the permit fee. Little Rock Code Sec. 8-31(c), as amended through Ord. No. 22,703 (December 16, 2025), read on Municode. See the official fee schedule for current amounts.
Where do you apply for an electrical permit in Little Rock?
You can apply through the Little Rock permit portal or contact the City of Little Rock Planning and Development Department, Building Codes Division directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Little Rock?
Under Arkansas law (Ark. Code 17-25-513(1), (2); 17-38-302(1); 17-28-101(9); 17-28-102(b); 17-28-305(b)(2); 17-25-101(a)(2)): Yes. A person building his or her own residence does not need a residential building contractor license unless they build more than one residence in a calendar year, and the owner of a single family residence may act as his or her own home improvement contractor (17-25-513(1)-(2)). Plumbing work done by a property owner in a building the owner owns and occupies as his or her home is exempt from plumber licensing unless a local ordinance requires a license (17-38-302(1)). The electrical licensing law does not require an individual to hold a license to do electrical work on his or her primary residence, defined as an unattached single-family dwelling, unless other state law or a local ordinance requires it, and a city or county may require the owner to show technical competency first (17-28-102(b), 17-28-305(b)(2)). These are licensing exemptions, not permit exemptions: the owner still needs whatever local permits apply. No state owner-builder disclosure form or resale restriction was found. Confirm how Little Rock applies this before you apply.

From the Library

What else needs a permit in Little Rock

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsPainting, floor coverings, cosmetic changes and fixture trap or supply-line swaps are exempt; moving plumbing, any electrical work or work over $5,000 needs permitsBuilding permit (if required) on the valuation schedule with a $51.50 minimum
Deck PermitPermit requiredAny size...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus...
EV Charger PermitPermit requiredAny size...special equipment, outdoor lighting or any circuits not already covered"...
Fence PermitIt dependsHeight of a residential fence...subsection 8-3 l(c)(l)a." (the building permit valuation schedule), with a $51.50...
HVAC PermitPermit requiredAny size...for replacements, repairs, alterations and additions by total valuation: "$500.00...
Patio PermitIt dependsValue of the work, including material and labor...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus...
Plumbing PermitIt dependsClearing stoppages, temporary leak clamps, replacing a fixture trap or supply lines, and like-for-like gas appliance hookups are exempt; new or altered piping needs a permitRepair/alteration items: "Each plumbing fixture outlet or appliance" $6.18
Pool PermitPermit requiredAny size...8-31(c)(l)a., but minimum fee shall be fee of fifty-one and 50/100 dollars...
Roof Replacement PermitNo permit neededExemptNot published
Shed PermitIt dependsFloor area of a one-story detached tool or storage shed, playhouse or similar accessory structure...except as otherwise specified, shall be fifty-one and 50/100 dollars ($51.50)" plus...
Solar PermitPermit requiredAny size...assessed on the building permit valuation schedule (Sec. 8-31(c)(1)n.), $51.50...
Water Heater PermitPermit requiredAny sizePlumbing permit line item "Water heater .....$17.51" (minimum plumbing permit $50.00)

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Little Rock documents; the office above sets the local rules.

How this electrical permit page for Little Rock was verified. 2 official sources: littlerock.gov, library.municode.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Little Rock Planning and Development Department, Building Codes Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page