Permit required

Yes, a permit is required

Before doing plumbing work on an existing building, including a water heater replacement or tankless conversion, gas line installation or testing, water softener or filtration installation, sewer or water meter work, or septic tank and leach line work.

Confirmed on official page Verified San Bernardino County Land Use Services Department, Building and Safety Division

By Mario Bailey, verified against official sources

Quick answer

San Bernardino County requires a Plumbing permit for plumbing work on an existing building or structure, and "Electrical, Plumbing, Mechanical and Structural Repairs" is on the county's published list of items requiring a permit. The Plumbing application's typical projects include Water Heater, Water Heater - Change Out, Water Heater - Tankless, Gas Line Install/Testing, Water Softener - Installation, Whole House Reverse Osmosis Water Treatment System, Septic Tank, Seepage Pit, Leach Line, Water Meter - Installation and Gas Meter - Reset. There is no like-for-like water heater exemption: the fee ordinance carries a dedicated "Each water heater" line at $156.00, and the county publishes a Water Heater Guide handout.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before doing plumbing work on an existing building, including a water heater replacement or tankless conversion, gas line installation or testing, water softener or filtration installation, sewer or water meter work, or septic tank and leach line work.

What a plumbing permit costs in San Bernardino County

Line item
plumbing permitBy formulaCounty Code 16.0204(c)(1) sets residential plumbing fees effective July 1, 2026 for "Fixture or traps including water drainage piping and backflow protection": $156.00 for 10 fixtures or less, $195.00 for 11 to 25 fixtures, $234.00 for 26 fixtures or more. "Each water heater" is $156.00, "Each sewer line" is $156.00, gas lines of 10 or less are $156.00, and the catch-all line for other residential plumbing work not listed in 16.0204(c)(1) is $156.00 for 10 items or less. Septic system plan review is $195.00. The ordinance states "All plumbing permits include two inspections." A $57.00 intake processing fee under 16.0204(h)(1) is applied to each plumbing permit.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How San Bernardino County compares in California

No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Alameda CountyPermit requiredBuilding Inspection Department Service Fee Schedule (Schedule A, effective...
Contra Costa CountyPermit requiredLand Development Fee Schedule S-002 E.6, "Plumbing Permit (Other) $75.00...
Fresno CountyPermit requiredSection 2512 Plumbing Code Fees, FY 2026-27: Alteration, repair or addition of...
Los AngelesPermit requiredItemized per fixture per LADBS Fee Sch.5 (7/2017), for example a toilet at $23...
Los Angeles CountyPermit requiredPlumbing Code Fee Schedule (Title 28 of the Los Angeles Code, Ord.
Orange CountyPermit requiredPlumbing Permit Application Flat Fee: $363 for FY 2024-25, $383 for FY...
San Bernardino Countythis pagePermit requiredCounty Code 16.0204(c)(1) sets residential plumbing fees effective July 1...

How to apply in San Bernardino County

You apply for a residential plumbing permit at your local building department by filing an application that describes the scope of work and site, along with construction documents, before any regulated plumbing installation, alteration, or repair begins. Minor repairs that do not touch piping or fixtures are generally exempt, and once issued the permit only stays valid if work is started within its time limit.

What most plumbing permit applications include:

  • A permit is required before any owner or authorized agent constructs, alters, repairs, removes, converts, or replaces a plumbing system regulated by the code (IRC R105.1).
  • The application must identify and describe the work, describe the site, state the intended use and occupancy, and be signed by the applicant or an authorized agent (IRC R105.3).
  • Two or more sets of construction documents must accompany the application, drawn with enough clarity to show the location, nature, and extent of the proposed plumbing work and how it will conform to code (IRC R106.1, R106.1.1).
  • Minor plumbing repairs, such as clearing a stoppage or removing and resetting a water closet without rearranging pipes or fixtures, are exempt from permit (IRC R105.2).
  • Once issued, a permit is only valid for a limited window, commonly 180 days, and becomes invalid if the work is not started or is abandoned within that time, though extensions can be requested (IRC R105.3.2, R105.5).

General submittal guidance from 2021 International Residential Code (IRC), Chapter 1 Scope and Administration, Sections R105 Permits and R106 Construction Documents. Source. San Bernardino County Land Use Services Department, Building and Safety Division sets the exact checklist for San Bernardino County.

Where to apply in San Bernardino County:

San Bernardino County Land Use Services Department, Building and Safety Division

  • County Government Center, 385 N. Arrowhead Ave., First Floor, San Bernardino, CA 92415
  • Phone: 909-387-8311

Inspections and closing out your permit

Plumbing inspections are timed to whatever is about to hide the pipe: underground and under-slab piping is checked before concrete covers it, rough-in piping is pressure or water tested before walls close up, and a final inspection checks every fixture and backflow protection once the work is complete.

  1. Piping and equipment placed under a slab or floor must be in place and inspected before any concrete is poured or floor sheathing is installed over it (IRC R109.1.1.1).
  2. Rough plumbing, along with the mechanical, gas, and electrical rough-in, must be inspected prior to covering or concealment and before fixtures or appliances are set (IRC R109.1.2).
  3. Rough drain, waste, and vent (DWV) piping is tested with water, air, or (for plastic piping) a vacuum, and must show no evidence of leakage before it is closed in (IRC P2503.5.1).
  4. The water-distribution piping is tested and must hold tight under the system's working pressure, or under a 50 psi air test for non-plastic piping, before it is concealed (IRC P2503.7).
  5. The framing inspection cannot proceed until the plumbing rough inspection, along with the mechanical and electrical rough inspections, has been approved (IRC R109.1.4).
  6. At the final drainage test, each fixture is filled and then drained, and its traps and fixture connections must prove watertight by visual inspection (IRC P2503.5.2).
  7. Final inspection is made after all work required by the permit is complete, and includes confirming backflow protection, such as vacuum breakers on hose bibbs, is installed (IRC R109.1.6, P2902.4.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the San Bernardino County permit portal or by phone at 909-387-8311.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 Inspections and Section P2503 Inspection and Tests. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a plumbing permit in San Bernardino County?
San Bernardino County requires a Plumbing permit for plumbing work on an existing building or structure, and "Electrical, Plumbing, Mechanical and Structural Repairs" is on the county's published list of items requiring a permit. The Plumbing application's typical projects include Water Heater, Water Heater - Change Out, Water Heater - Tankless, Gas Line Install/Testing, Water Softener - Installation, Whole House Reverse Osmosis Water Treatment System, Septic Tank, Seepage Pit, Leach Line, Water Meter - Installation and Gas Meter - Reset. There is no like-for-like water heater exemption: the fee ordinance carries a dedicated "Each water heater" line at $156.00, and the county publishes a Water Heater Guide handout. Always confirm with the San Bernardino County Land Use Services Department, Building and Safety Division before starting.
How much does a plumbing permit cost in San Bernardino County?
County Code 16.0204(c)(1) sets residential plumbing fees effective July 1, 2026 for "Fixture or traps including water drainage piping and backflow protection": $156.00 for 10 fixtures or less, $195.00 for 11 to 25 fixtures, $234.00 for 26 fixtures or more. "Each water heater" is $156.00, "Each sewer line" is $156.00, gas lines of 10 or less are $156.00, and the catch-all line for other residential plumbing work not listed in 16.0204(c)(1) is $156.00 for 10 items or less. Septic system plan review is $195.00. The ordinance states "All plumbing permits include two inspections." A $57.00 intake processing fee under 16.0204(h)(1) is applied to each plumbing permit. See the official fee schedule for current amounts.
Where do you apply for a plumbing permit in San Bernardino County?
You can apply through the San Bernardino County permit portal or contact the San Bernardino County Land Use Services Department, Building and Safety Division directly. The links are listed on this page.
Can a homeowner pull a plumbing permit themselves in San Bernardino County?
Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner-builder from contractor licensing when the owner personally performs the work, or uses only wage employees, on their own property and does not intend the improvements for sale. A homeowner may also directly hire licensed trade contractors for up to four single-family residences a year, or improve their own principal residence without a general contractor's license, as long as they have actually lived there for the 12 months before the work is finished. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a building permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a $500 civil penalty. Confirm how San Bernardino County applies this before you apply.

From the Library

What else needs a permit in San Bernardino County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsfloor area of a detached residential accessory structureDecks are priced off the FY 2026/27 Construction Fee Schedule adopted under County Code...
Electrical PermitPermit requiredNot specifiedCounty Code 16.0204(b)(1) sets residential electrical fees effective July 1, 2026:...
Fence PermitIt dependsheight of a fence or block wallSan Bernardino County Code section 16.0204(g)(3) prices fencing as a flat fee: "Chain...
HVAC PermitPermit requiredNot specifiedCounty Code 16.0204(d)(1) sets residential mechanical fees effective July 1, 2026: "HVAC...
Patio PermitPermit requiredNot specifiedPatio covers are priced off the FY 2026/27 Construction Fee Schedule adopted under...
Pool PermitPermit requiredNot specifiedCounty Code 16.0204(i)(1) sets flat fees effective July 1, 2026 for "Swimming pools...
Roof Replacement PermitPermit requiredNot specifiedCounty Code 16.0204(h)(8) sets a flat re-roof fee effective July 1, 2026: "Re-roofs: A)...
Shed PermitIt dependsfloor area of a detached residential accessory structureSheds are priced off the FY 2026/27 Construction Fee Schedule adopted under County Code...
Solar PermitPermit requiredNot specifiedCounty Code 16.0204(j)(1) sets fees effective July 1, 2026 for "15KW or less...

Plumbing Permit in other California localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not San Bernardino County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with San Bernardino County Land Use Services Department, Building and Safety Division. Rules change; confirm before you build. How we verify.