EV Charger Permit in Birmingham, Alabama
Permit required
Yes, a permit is required
Before installing an EV charger or the circuit that serves it.
Quick answer
Birmingham publishes nothing specific to EV chargers; installing one, or the new circuit that feeds it, is installing or altering an electrical system, which needs an electrical permit from PEP under the City's Technical Code and the 2020 NEC.
- Issued by
- City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division
- Phone
- (205) 254-2904
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
A licensed electrician typically pulls the electrical permit as part of the install. If you have not picked one yet, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
What an EV charger permit costs in Birmingham
- Fee basis
- Project valuation
- Fee schedule in force
- Official scheduleRead .
- Published in
- Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V:
- "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00".
- Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)".
- Work begun before the permit pays a doubled fee (section 104.2).
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in Birmingham
General guide, not specific to this office
What an EV charger permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an EV charger permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division
- City Hall, Room 210, 710 20th Street North, Birmingham, AL 35203
- Phone: (205) 254-2904
- Email: OnlinePermitCenter@birminghamal.gov
Your EV Charger Permit checklist for Birmingham
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: birminghamal.gov: city birmingham permitting.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Birmingham permit portal.
- Keep the office details handy. City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division. Phone: (205) 254-2904. Email: OnlinePermitCenter@birminghamal.gov. Address: City Hall, Room 210, 710 20th Street North, Birmingham, AL 35203.
Compiled from the official sources on this page. Last checked .
What else needs a permit in Birmingham
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Before any bathroom work beyond painting, papering, flooring, cabinets, countertops and... | See schedule |
| Deck Permit | Permit required | Any size | See schedule |
| Electrical Permit | Permit required | Any size | See schedule |
| Fence Permit | Permit required | Any size | Zoning Ordinance, Title 1, Chapter 9, Article VIII, Section 3 (Miscellaneous Fees): "Fence Permit" $40 |
| HVAC Permit | It depends | Before installing, replacing, enlarging or relocating a heating, cooling or ventilation... | See schedule |
| Plumbing Permit | It depends | length of water service repaired or replaced, and no more than 50% of the service | See schedule |
| Pool Permit | Permit required | Any size | Electrical and plumbing permits: $9.50 per $1,000.00 valuation, minimum $125.00 each (Technical Code 2024, Article V) |
| Roof Replacement Permit | It depends | Before reroofing a home in a historic or design review district, and before any reroof... | See schedule |
| Shed Permit | It depends | floor area of an accessory structure for a one- or two-family dwelling; the exemption applies only when the Planning Division approves it | See schedule |
| Solar Permit | Permit required | Any size | See schedule |
| Water Heater Permit | Permit required | Any size | See schedule |
Frequently asked questions
- Do you need an EV charger permit in Birmingham?
- Yes, before installing an EV charger or the circuit that serves it. If you are unsure how that applies to your project, call the permit office at (205) 254-2904 before you start.
- How much does an EV charger permit cost in Birmingham?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 30 Oct 2026. For the figure on your own project, call the permit office at (205) 254-2904.
- Where do you apply for an EV charger permit in Birmingham?
- You can apply through the Birmingham permit portal or contact the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division directly. The links are listed on this page.
- Can a homeowner pull an EV charger permit themselves in Birmingham?
- Under Alabama law (Ala. Code 34-14A-6(5); 34-36-13(a)(5); 34-37-15(a)(5), (b)): Yes. The home builder licensing law does not apply to owners acting as their own contractor and providing all material supervision themselves when building or improving a one- or two-family home on their own property for their own occupancy or use and not offered for sale (34-14A-6(5)a). The exemption cannot be transferred, including through a power of attorney, and selling or offering the home for sale within one year after completion is presumptive evidence it was built for sale (34-14A-6(5)b). Owners may also do their own electrical work on their premises (34-36-13(a)(5)) and their own plumbing in a building they own or occupy (34-37-15), though plumbing work stays subject to inspection under state law and local ordinances. Whether an owner may pull a local building permit is set by the city or county. Confirm how Birmingham applies this before you apply.
From the Library
Everything above, sourced
How this EV charger permit page for Birmingham was verified. 2 official sources: birminghamal.gov, s3.us-east-2.amazonaws.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division. Rules change; confirm before you build. How we verify.