Alabama / Birmingham

EV Charger Permit in Birmingham, Alabama

Permit required

Yes, a permit is required

Before installing an EV charger or the circuit that serves it.

Confirmed on official page Verified

Issued byCity of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division

By Mario Bailey, verified against official sources

Quick answer

Birmingham publishes nothing specific to EV chargers; installing one, or the new circuit that feeds it, is installing or altering an electrical system, which needs an electrical permit from PEP under the City's Technical Code and the 2020 NEC.

Who is pulling this permit?

Hire it out

Sponsored

A licensed electrician typically pulls the electrical permit as part of the install. If you have not picked one yet, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before installing an EV charger or the circuit that serves it.

What an EV charger permit costs in Birmingham

Line item
EV charger permitBy formulaTechnical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2).
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Birmingham

In Birmingham, in most of the US, installing a Level 2 (240 volt) home EV charger is handled as an electrical permit built around a load calculation and a single line diagram showing the new dedicated circuit. A Level 1 charger that simply plugs into an existing 120 volt outlet typically needs no permit unless new wiring is added.

What most EV charger permit applications include:

  • For Birmingham, a Level 2 charger needs its own dedicated 240 volt circuit and requires an electrical permit with inspection, since each outlet installed for EV charging must be fed by an individual branch circuit with no other outlets on it (NEC 625.40).
  • For Birmingham, the application includes an electrical load calculation showing the existing service panel has enough spare capacity for the added EVSE demand, worked out using the standard dwelling load calculation method (NEC 220.83).
  • For Birmingham, the breaker or other overcurrent device feeding the charger must be sized for continuous duty, rated at not less than 125 percent of the equipment's maximum load (NEC 625.41).
  • Plan submittal typically includes a single line diagram showing conductor size, breaker size, conduit, and panel rating, plus the charger's manufacturer specifications, since the EVSE itself must be a listed product (NEC 625.5).
  • For charging equipment rated over 60 amps or over 150 volts to ground, the application has to show a disconnecting means installed in a readily accessible location and capable of being locked open (NEC 625.43).
  • For Birmingham, the charger must be shown connected and fastened in place according to the manufacturer's installation instructions, whether it is hardwired or a plug in unit on a dedicated receptacle (NEC 625.44).

General submittal guidance from National Electrical Code (NFPA 70), Article 625 Electric Vehicle Charging System and Article 220 Load Calculations, 2017 to 2023 editions. Source. City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division sets the exact checklist for Birmingham.

Where to apply in Birmingham:

City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division

Inspections and closing out your permit

In Birmingham, a Level 2 EV charger installation gets a rough wiring inspection if any new conductors will be hidden inside walls, ceilings, or run underground, then a final inspection that checks the dedicated circuit, breaker sizing, any required GFCI protection, the disconnect, and the charger's listing before the permit closes.

  1. In Birmingham: if new EVSE conductors will be concealed in a wall or ceiling, or run underground, they must pass a rough wiring inspection before being covered, since that inspection confirms the dedicated branch circuit required for the charger (NEC 625.40).
  2. In Birmingham: at final inspection, the breaker or other overcurrent device serving the charger is checked to confirm it is properly rated for the continuous EV charging load (NEC 625.41).
  3. In Birmingham: any receptacle installed for EV charging, as opposed to a hardwired connection, has to be checked for ground fault circuit interrupter protection (NEC 625.54).
  4. In Birmingham: where the EVSE is rated over 60 amps or 150 volts to ground, the inspector confirms a lockable, readily accessible disconnecting means was installed (NEC 625.43).
  5. In Birmingham: the inspector verifies the charger, along with its fittings and associated equipment, carries a nationally recognized testing laboratory listing (NEC 625.5).
  6. In Birmingham: mounting height is checked against the manufacturer's instructions, with the coupling means generally required to sit at least 18 inches above an indoor floor or 24 inches above outdoor grade unless the equipment is listed otherwise (NEC 625.50).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Birmingham permit portal or by phone at (205) 254-2904.

Inspection sequence from National Electrical Code (NFPA 70), Article 625 Electric Vehicle Charging System, 2017 to 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an EV charger permit in Birmingham?
Birmingham publishes nothing specific to EV chargers; installing one, or the new circuit that feeds it, is installing or altering an electrical system, which needs an electrical permit from PEP under the City's Technical Code and the 2020 NEC. Always confirm with the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division before starting.
How much does an EV charger permit cost in Birmingham?
Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2). See the official fee schedule for current amounts.
Where do you apply for an EV charger permit in Birmingham?
You can apply through the Birmingham permit portal or contact the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division directly. The links are listed on this page.
Can a homeowner pull an EV charger permit themselves in Birmingham?
Under Alabama law (Ala. Code 34-14A-6(5); 34-36-13(a)(5); 34-37-15(a)(5), (b)): Yes. The home builder licensing law does not apply to owners acting as their own contractor and providing all material supervision themselves when building or improving a one- or two-family home on their own property for their own occupancy or use and not offered for sale (34-14A-6(5)a). The exemption cannot be transferred, including through a power of attorney, and selling or offering the home for sale within one year after completion is presumptive evidence it was built for sale (34-14A-6(5)b). Owners may also do their own electrical work on their premises (34-36-13(a)(5)) and their own plumbing in a building they own or occupy (34-37-15), though plumbing work stays subject to inspection under state law and local ordinances. Whether an owner may pull a local building permit is set by the city or county. Confirm how Birmingham applies this before you apply.

From the Library

What else needs a permit in Birmingham

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsBefore any bathroom work beyond painting, papering, flooring, cabinets, countertops and......10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50...
Deck PermitPermit requiredAny size...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50...
Electrical PermitPermit requiredAny size$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..
Fence PermitPermit requiredAny size...1, Chapter 9, Article VIII, Section 3 (Miscellaneous Fees): "Fence Permit"...
HVAC PermitIt dependsBefore installing, replacing, enlarging or relocating a heating, cooling or ventilation...$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..
Plumbing PermitIt dependslength of water service repaired or replaced, and no more than 50% of the service$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..
Pool PermitPermit requiredAny sizeElectrical and plumbing permits: $9.50 per $1,000.00 valuation, minimum $125.00 each...
Roof Replacement PermitIt dependsBefore reroofing a home in a historic or design review district, and before any reroof......10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50...
Shed PermitIt dependsfloor area of an accessory structure for a one- or two-family dwelling; the exemption applies only when the Planning Division approves it...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50...
Solar PermitPermit requiredAny size$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..
Water Heater PermitPermit requiredAny size$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Birmingham documents; the office above sets the local rules.

How this EV charger permit page for Birmingham was verified. 2 official sources: birminghamal.gov, s3.us-east-2.amazonaws.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page