Quick answer

Birmingham publishes no solar-specific permit page, but its Technical Code requires a permit to install any electrical system, and the exemption list has no solar exemption, so a solar installation needs an electrical permit from PEP (plus a building permit for the mounting structure). The Zoning Ordinance separately regulates building-mounted solar panels in several districts.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your Alabama Home Builders Licensure Board license active, and under which business name? Verify it on alhobv7prod.glsuite.us.

Alabama's owner-builder rule (Ala. Code 34-14A-6(5); 34-36-13(a)(5); 34-37-15(a)(5), (b)) sets what you may do on your own home without hiring anyone. Read the statute.

When a permit is usually needed

Before installing a solar energy system.

What a solar permit costs in Birmingham

Line item
solar permitBy formulaTechnical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2). Roof or ground structural work is a building permit at the same $9.50 per $1,000 valuation rate.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Birmingham

In Birmingham, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • For Birmingham, the plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • For Birmingham, the site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • For Birmingham, the one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division sets the exact checklist for Birmingham.

Where to apply in Birmingham:

City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division

Inspections and closing out your permit

In Birmingham, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. In Birmingham: where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. In Birmingham: the inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. In Birmingham: pV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. In Birmingham: bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. In Birmingham: at the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. In Birmingham: utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Birmingham permit portal or by phone at (205) 254-2904.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Birmingham?
Birmingham publishes no solar-specific permit page, but its Technical Code requires a permit to install any electrical system, and the exemption list has no solar exemption, so a solar installation needs an electrical permit from PEP (plus a building permit for the mounting structure). The Zoning Ordinance separately regulates building-mounted solar panels in several districts. Always confirm with the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division before starting.
How much does a solar permit cost in Birmingham?
Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2). Roof or ground structural work is a building permit at the same $9.50 per $1,000 valuation rate. See the official fee schedule for current amounts.
Where do you apply for a solar permit in Birmingham?
You can apply through the Birmingham permit portal or contact the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Birmingham?
Under Alabama law (Ala. Code 34-14A-6(5); 34-36-13(a)(5); 34-37-15(a)(5), (b)): Yes. The home builder licensing law does not apply to owners acting as their own contractor and providing all material supervision themselves when building or improving a one- or two-family home on their own property for their own occupancy or use and not offered for sale (34-14A-6(5)a). The exemption cannot be transferred, including through a power of attorney, and selling or offering the home for sale within one year after completion is presumptive evidence it was built for sale (34-14A-6(5)b). Owners may also do their own electrical work on their premises (34-36-13(a)(5)) and their own plumbing in a building they own or occupy (34-37-15), though plumbing work stays subject to inspection under state law and local ordinances. Whether an owner may pull a local building permit is set by the city or county. Confirm how Birmingham applies this before you apply.

From the Library

What else needs a permit in Birmingham

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsBefore any bathroom work beyond painting, papering, flooring, cabinets, countertops and......10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50...
Deck PermitPermit requiredAny size...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50...
Electrical PermitPermit requiredAny size$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..
EV Charger PermitPermit requiredAny size$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..
Fence PermitPermit requiredAny size...1, Chapter 9, Article VIII, Section 3 (Miscellaneous Fees): "Fence Permit"...
HVAC PermitIt dependsBefore installing, replacing, enlarging or relocating a heating, cooling or ventilation...$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..
Plumbing PermitIt dependslength of water service repaired or replaced, and no more than 50% of the service$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..
Pool PermitPermit requiredAny sizeElectrical and plumbing permits: $9.50 per $1,000.00 valuation, minimum $125.00 each...
Roof Replacement PermitIt dependsBefore reroofing a home in a historic or design review district, and before any reroof......10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50...
Shed PermitIt dependsfloor area of an accessory structure for a one- or two-family dwelling; the exemption applies only when the Planning Division approves it...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50...
Water Heater PermitPermit requiredAny size$9.50 per $1000.00 valuation for alterations", "Minimum permit fee ..

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Birmingham documents; the office above sets the local rules.

How this solar permit page for Birmingham was verified. 2 official sources: birminghamal.gov, s3.us-east-2.amazonaws.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Solar Permit requirements across Alabama localities

Solar permit rules nationwide

Permit required
Get quotes